INDOT contract R-43831-A bid tabulation
SMALL STRUCTURE MAINTENANCE AND REPAIR. Let by Indiana DOT on February 11, 2026, Hendricks, Crawfordsville. 6 bids received; low bid $138,055 by Olco Inc.
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 27
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Olco Inc | $138,055 | Low |
| 2 | CLR Inc | $147,688 | +7.0% |
| 3 | Crackers Demo LLC | $158,740 | +15% |
| 4 | Superior Construction Co Inc | $193,000 | +40% |
| 5 | William Charles Construction Company | $224,960 | +63% |
| 6 | Morphey Construction Inc. | $382,068 | +177% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Olco Inc | 2. CLR Inc | 3. Crackers Demo LLC | 4. Superior Construction Co Inc | 5. William Charles Construction Company | 6. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $3,500.00 | $25,000 | $6,000.00 | $3,000.00 | $10,000 | $4,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $9,878.00 | $7,285.00 | $13,500 | $89,171 | $17,000 | $25,000 |
| 0008 | Clearing right-of-way (201-52370) | LS | 1 | $7,671.00 | $1,455.00 | $5,500.00 | $1,900.00 | $5,000.00 | $25,000 |
| 0009 | Stormwater management budget (205-12108) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Stormwater management implementation (205-12616) | LS | 1 | $3,926.00 | $1,000.00 | $7,100.00 | $2,500.00 | $4,500.00 | $2,200.00 |
| 0011 | Right-of-way marker (615-06490) | EACH | 4 | $547.59 | $200.00 | $500.00 | $500.00 | $1,200.00 | $775.00 |
| 0012 | Riprap, class 1 (616-05688) | TON | 38 | $120.93 | $125.00 | $198.98 | $228.00 | $210.00 | $600.00 |
| 0013 | Geotextile for riprap, type 1A (616-12246) | SYS | 42 | $12.93 | $13.00 | $2.77 | $16.00 | $37.00 | $29.00 |
| 0014 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $504.92 | $500.00 | $600.00 | $600.00 | $975.00 | $600.00 |
| 0015 | Mulched seeding, type R (621-06559) | SYS | 600 | $3.51 | $1.90 | $3.48 | $3.48 | $6.00 | $20.00 |
| 0016 | Field office, type A (628-09401) | MOS | 5 | $1,671.14 | $1,000.00 | $1,451.96 | $3,400.00 | $1,000.00 | $3,200.00 |
| 0017 | Cored hole in concrete (702-03607) | EACH | 12 | $150.00 | $300.00 | $195.00 | $350.00 | $245.00 | $1,000.00 |
| 0018 | Threaded tie bar assembly (703-01540) | EACH | 6 | $1,377.37 | $150.00 | $690.00 | $3,650.00 | $862.00 | $1,500.00 |
| 0019 | Patching concrete structures (710-09158) | SFT | 9 | $810.22 | $400.00 | $215.00 | $208.00 | $412.00 | $2,500.00 |
| 0020 | Structural steel (711-51035) | LBS | 870 | $11.62 | $15.00 | $7.00 | $9.00 | $9.00 | $22.00 |
| 0021 | Repair existing structure (711-91996) | LS | 1 | $37,042 | $45,000 | $62,000 | $700.00 | $100,000 | $180,000 |
| 0022 | Epoxy injection, epoxy injection adhesive (727-000188) | GAL | 12 | $30.00 | $30.00 | $65.00 | $65.00 | $48.00 | $65.00 |
| 0023 | Epoxy injection, crack preparation (727-90308) | LFT | 40 | $25.00 | $30.00 | $120.00 | $120.00 | $40.00 | $120.00 |
| 0024 | Epoxy injection, furnishing equipment (727-93560) | LS | 1 | $3,500.00 | $4,150.00 | $965.00 | $965.00 | $5,690.00 | $965.00 |
| 0025 | Construction sign, type A (801-06640) | EACH | 14 | $125.00 | $250.00 | $190.00 | $125.00 | $345.00 | $190.00 |
| 0026 | Maintaining traffic (801-06775) | LS | 1 | $19,662 | $17,547 | $14,000 | $16,603 | $18,000 | $11,000 |
| 0027 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 6 | $500.00 | $1,050.00 | $1,050.00 | $500.00 | $2,200.00 | $1,050.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.