INDOT contract R-43847-A bid tabulation
SMALL STRUCTURE PIPE LINING. Let by Indiana DOT on February 11, 2026, Miami, Fort Wayne. 6 bids received; low bid $1,700,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 11 FEB 2026
- Pay items
- 34
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $1,700,000 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $1,830,210 | +8.0% |
| 3 | Temple & Temple Excavating & Paving Inc | $1,843,883 | +8.0% |
| 4 | 3D Company Inc | $1,936,238 | +14% |
| 5 | Infrastructure Systems Inc | $1,997,978 | +18% |
| 6 | Yarberry Companies Inc | $2,105,125 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. Rieth-Riley Construction Co., Inc. | 3. Temple & Temple Excavating & Paving Inc | 4. 3D Company Inc | 5. Infrastructure Systems Inc | 6. Yarberry Companies Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $22,500 | $35,000 | $9,500.00 | $10,840 | $9,000.00 | $20,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $85,000 | $85,510 | $100,000 | $57,740 | $126,000 | $105,000 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $34,000 | $23,500 | $27,500 | $20,345 | $22,000 | $63.00 |
| 0010 | Pipe, remove (202-96133) | LFT | 49 | $100.00 | $210.00 | $160.00 | $121.35 | $100.00 | $150.00 |
| 0011 | Excavation, common (203-02000) | CYS | 192 | $100.00 | $120.00 | $45.00 | $218.45 | $50.00 | $200.00 |
| 0012 | Pump around (205-11626) | EACH | 3 | $10,000 | $19,000 | $10,000 | $9,652.00 | $20,000 | $46,000 |
| 0013 | Stormwater management budget (205-12108) | DOL | 26,700 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $10,800 | $17,000 | $12,260 | $10,000 | $20,000 |
| 0015 | Structure backfill, type 5 (211-09268) | CYS | 168 | $148.00 | $650.00 | $283.00 | $288.77 | $350.00 | $350.00 |
| 0016 | Riprap, class 2 (616-05689) | TON | 187 | $180.00 | $155.00 | $150.00 | $116.07 | $195.00 | $180.00 |
| 0017 | Riprap, revetment (616-06405) | TON | 122 | $200.00 | $110.00 | $100.00 | $88.88 | $200.00 | $150.00 |
| 0018 | Geotextile for riprap, type 1A (616-12246) | SYS | 109 | $5.00 | $14.00 | $10.00 | $5.43 | $7.00 | $15.00 |
| 0019 | Geotextile for riprap, type 2A (616-12248) | SYS | 248 | $5.00 | $8.80 | $10.00 | $5.68 | $7.00 | $15.00 |
| 0020 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $400.00 | $400.00 | $450.00 | $558.85 | $700.00 | $750.00 |
| 0021 | Mulched seeding, type R (621-06559) | SYS | 4,283 | $8.00 | $2.70 | $4.00 | $3.37 | $2.50 | $2.00 |
| 0022 | Concrete, A, substructure (702-51005) | CYS | 15 | $2,000.00 | $2,460.00 | $4,000.00 | $4,625.00 | $3,750.00 | $3,600.00 |
| 0023 | Concrete, A, substructure , for headwalls (702-51005) | CYS | 14 | $2,000.00 | $2,660.00 | $4,000.00 | $4,685.00 | $4,000.00 | $4,000.00 |
| 0024 | Concrete, B, footings (702-51015) | CYS | 55 | $200.00 | $1,015.00 | $1,875.00 | $2,000.00 | $1,350.00 | $1,400.00 |
| 0025 | Surface seal , CV 031-052- 176.15 (709-51821) | LS | 1 | $4,000.00 | $3,000.00 | $3,650.00 | $2,887.00 | $3,500.00 | $3,600.00 |
| 0026 | Surface seal , CV 031-052- 180.80 (709-51821) | LS | 1 | $4,000.00 | $3,000.00 | $3,775.00 | $2,999.00 | $3,500.00 | $3,800.00 |
| 0027 | Liner pipe, steel, deformed, 47.6-58.2 SFT (725-000081) | LFT | 223 | $3,286.00 | $2,920.00 | $2,675.00 | $3,249.00 | $3,300.00 | $3,175.00 |
| 0028 | Pipe liner, cured-in- place, min. area 15.6 SFT (725-11791) | LFT | 254 | $755.00 | $808.00 | $965.00 | $929.00 | $1,000.00 | $945.00 |
| 0029 | Pipe liner, cured-in- place, min. area 26.8 SFT (725-12052) | LFT | 193 | $1,100.00 | $1,290.00 | $1,294.00 | $1,234.00 | $1,300.00 | $1,270.00 |
| 0030 | Construction sign, type A (801-06640) | EACH | 30 | $200.00 | $180.00 | $240.00 | $260.78 | $185.00 | $230.00 |
| 0031 | Construction sign, type B (801-06645) | EACH | 18 | $75.00 | $120.00 | $88.00 | $116.48 | $125.00 | $125.00 |
| 0032 | Maintaining traffic (801-06775) | LS | 1 | $129,597 | $31,000 | $23,500 | $40,280 | $13,500 | $78,000 |
| 0033 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 6 | $1.00 | $5,500.00 | $6,900.00 | $4,775.00 | $6,000.00 | $6,600.00 |
| 0034 | Temporary traffic barrier, type 1 (801-08400) | LFT | 1,720 | $1.00 | $45.00 | $67.00 | $60.45 | $60.00 | $63.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.