INDOT contract R-44228-A bid tabulation
INSTITUTIONAL AND PARK ROAD MAINTENANCE. Let by Indiana DOT on February 12, 2025, Hendricks, Crawfordsville. 3 bids received; low bid $1,168,943 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 36
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $1,168,943 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $1,208,000 | +3.0% |
| 3 | Calumet Civil Contractors Inc | $1,218,000 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Rieth-Riley Construction Co., Inc. | 3. Calumet Civil Contractors Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $49,000 | $39,701 | $44,893 |
| 0010 | Curb, concrete, remove (202-02278) | LFT | 221 | $13.00 | $16.00 | $12.00 |
| 0011 | Excavation, common (203-02000) | CYS | 1,132 | $39.00 | $50.00 | $31.00 |
| 0012 | Stormwater management budget (205-12108) | DOL | 3,697 | $1.00 | $1.00 | $1.00 |
| 0013 | Stormwater management implementation (205-12616) | LS | 1 | $4,000.00 | $3,000.00 | $8,500.00 |
| 0014 | Subgrade treatment, type II (207-08264) | SYS | 613 | $28.00 | $20.00 | $21.50 |
| 0015 | Geogrid, type IB (214-11796) | SYS | 137 | $6.00 | $5.00 | $6.00 |
| 0016 | Compacted aggregate, no. 53 (301-12234) | CYS | 79 | $83.00 | $78.00 | $75.00 |
| 0017 | Aggregate drainage layer (302-12387) | CYS | 1,000 | $63.00 | $75.00 | $75.00 |
| 0018 | Compacted aggregate, no. 73 (303-07449) | TON | 526 | $65.00 | $40.00 | $54.00 |
| 0019 | HMA patching, full depth, type B (304-12623) | TON | 75 | $215.00 | $180.00 | $153.00 |
| 0020 | HMA patching, partial depth, type B (304-12624) | TON | 140 | $215.00 | $180.00 | $153.00 |
| 0021 | Milling, asphalt, 2 in. (306-08036) | SYS | 69,849 | $1.10 | $1.65 | $1.35 |
| 0022 | QC/QA-HMA, 3, 58S, surface, 12.5 MM (401-000011) | TON | 7,683 | $91.00 | $95.00 | $101.00 |
| 0023 | Joint adhesive, surface (401-10258) | LFT | 30,782 | $0.75 | $0.60 | $0.30 |
| 0024 | Liquid asphalt sealant (401-11785) | LFT | 30,782 | $0.01 | $0.01 | $0.30 |
| 0025 | Asphalt for tack coat (406-05520) | TON | 24 | $1.00 | $0.01 | $1.00 |
| 0026 | HMA for approaches, type B (610-07487) | TON | 105 | $150.00 | $180.00 | $120.00 |
| 0027 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $200.00 | $200.00 | $200.00 |
| 0028 | Sodding (621-06574) | SYS | 74 | $49.25 | $49.25 | $70.00 |
| 0029 | Field office, type C (628-09403) | MOS | 6 | $4,350.00 | $1,500.00 | $3,200.00 |
| 0030 | Computer system equipment (628-11976) | EACH | 1 | $750.00 | $500.00 | $1,500.00 |
| 0031 | Construction sign, type A (801-06640) | EACH | 10 | $186.00 | $186.00 | $250.00 |
| 0032 | Maintaining traffic (801-06775) | LS | 1 | $21,300 | $21,344 | $5,000.00 |
| 0033 | Pavement marking , 8 inch squares with and without black DOT (808-09968) | SFT | 1,000 | $14.50 | $14.50 | $15.00 |
| 0034 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 11,234 | $0.50 | $0.50 | $0.60 |
| 0035 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 11,234 | $0.44 | $0.44 | $0.60 |
| 0036 | Pavement message marking, paint, ADA accessible symbol (808-97222) | EACH | 1 | $190.00 | $190.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.