INDOT contract R-44529-A bid tabulation
SMALL STRUCTURE REPLACEMENT, MAINTENANCE AND REPAIR. Let by Indiana DOT on September 2, 2026, Whitley, Fort Wayne. 5 bids received; low bid $818,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 68
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $818,000 | Low |
| 2 | Brooks Construction Company Inc | $903,448 | +10% |
| 3 | Pioneer Associates Inc | $974,633 | +19% |
| 4 | Milestone Contractors LP | $989,271 | +21% |
| 5 | Yarberry Companies Inc | $1,314,762 | +61% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. Brooks Construction Company Inc | 3. Pioneer Associates Inc | 4. Milestone Contractors LP | 5. Yarberry Companies Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $8,200.00 | $8,200.00 | $9,000.00 | $21,875 | $30,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $40,950 | $40,000 | $52,500 | $49,464 | $65,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $11,000 | $18,000 | $32,500 | $19,785 | $30,000 |
| 0012 | Guardrail end treatment, remove (202-93741) | EACH | 6 | $150.00 | $350.00 | $350.00 | $350.00 | $630.00 |
| 0013 | Pipe, remove (202-96133) | LFT | 135 | $27.00 | $55.00 | $75.00 | $34.75 | $250.00 |
| 0014 | Excavation, common (203-02000) | CYS | 920 | $45.00 | $90.00 | $55.00 | $73.00 | $100.00 |
| 0015 | Excavation, unclassified (203-02020) | CYS | 78 | $100.00 | $80.00 | $55.00 | $69.75 | $150.00 |
| 0016 | Linear grading (203-08607) | LFT | 96 | $47.00 | $31.00 | $12.00 | $5.00 | $50.00 |
| 0017 | Pump around (205-11626) | EACH | 2 | $15,000 | $7,500.00 | $15,500 | $17,375 | $15,000 |
| 0018 | Stormwater management budget (205-12108) | DOL | 30,065 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Stormwater management implementation (205-12616) | LS | 1 | $712.00 | $1,000.00 | $1,500.00 | $3,075.00 | $15,000 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 230 | $25.00 | $27.00 | $35.00 | $23.75 | $30.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 367 | $46.00 | $43.00 | $55.00 | $51.25 | $60.00 |
| 0022 | Structure backfill, type 1 (211-09264) | CYS | 7 | $107.00 | $375.00 | $130.00 | $2,030.25 | $300.00 |
| 0023 | Structure backfill, type 2 (211-09265) | CYS | 1,023 | $60.00 | $125.00 | $110.00 | $64.75 | $85.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 367 | $6.00 | $6.25 | $7.00 | $5.50 | $10.00 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 54 | $150.00 | $140.00 | $180.00 | $118.00 | $200.00 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 63 | $120.00 | $100.00 | $145.00 | $103.00 | $85.00 |
| 0027 | Compacted aggregate, no. 53 (303-01180) | TON | 187 | $50.00 | $73.00 | $69.39 | $81.00 | $50.00 |
| 0028 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,681 | $6.00 | $7.50 | $5.00 | $4.50 | $100.00 |
| 0029 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 168 | $138.00 | $138.00 | $138.00 | $138.00 | $220.00 |
| 0030 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 47 | $232.00 | $232.00 | $232.00 | $232.00 | $200.00 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 114 | $131.00 | $131.00 | $131.00 | $131.00 | $150.00 |
| 0032 | Joint adhesive (401-11526) | LFT | 1,584 | $0.27 | $0.27 | $0.30 | $0.27 | $3.00 |
| 0033 | Asphalt for tack coat (406-05521) | SYS | 2,939 | $0.39 | $0.39 | $0.40 | $0.39 | $2.00 |
| 0034 | Guardrail terminal system, MGS W-beam, curved, 24 FT (601-000240) | EACH | 3 | $8,700.00 | $3,750.00 | $3,750.00 | $3,750.00 | $9,570.00 |
| 0035 | Guardrail, remove (601-02241) | LFT | 673 | $5.00 | $7.00 | $7.00 | $7.00 | $7.00 |
| 0036 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 400 | $27.00 | $28.00 | $28.00 | $28.00 | $30.00 |
| 0037 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,168.00 | $3,575.00 | $4,538.80 | $3,575.00 | $3,520.00 |
| 0038 | HMA for approaches, type B (610-07487) | TON | 50 | $305.00 | $220.00 | $220.00 | $220.00 | $200.00 |
| 0039 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $295.00 | $300.00 | $300.00 | $300.00 | $250.00 |
| 0040 | Right-of-way marker (615-06490) | EACH | 8 | $175.00 | $210.00 | $210.00 | $210.00 | $220.00 |
| 0041 | Monument, type B (615-06505) | EACH | 2 | $995.00 | $1,800.00 | $1,800.00 | $1,800.00 | $1,100.00 |
| 0042 | Riprap, class 2 (616-05689) | TON | 231 | $115.00 | $114.00 | $120.00 | $133.00 | $200.00 |
| 0043 | Riprap, revetment (616-06405) | TON | 407 | $90.00 | $78.00 | $80.00 | $103.00 | $150.00 |
| 0044 | Geotextile for riprap, type 2B (616-12249) | SYS | 1,204 | $6.00 | $7.00 | $4.00 | $5.25 | $15.00 |
| 0045 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $550.00 | $500.00 | $550.00 | $550.00 | $750.00 |
| 0046 | Erosion control blanket (621-02770) | SYS | 2,808 | $8.00 | $2.00 | $2.30 | $2.28 | $6.00 |
| 0047 | Mulched seeding, type R (621-06559) | SYS | 2,815 | $8.00 | $2.00 | $2.00 | $1.72 | $2.00 |
| 0048 | Water (621-06567) | KGAL | 1 | $10.00 | $0.01 | $10.00 | $10.00 | $1.00 |
| 0049 | Sodding (621-06574) | SYS | 88 | $50.00 | $16.00 | $25.00 | $23.75 | $50.00 |
| 0050 | Field office, type D (628-12683) | MOS | 12 | $2,400.00 | $4,250.00 | $4,600.00 | $5,675.00 | $5,500.00 |
| 0051 | Waterproofing membrane, type 2 (714-000086) | SFT | 2,530 | $5.00 | $4.75 | $5.00 | $3.75 | $5.00 |
| 0052 | Structure, reinforced concrete, box sections, 6 FT X 5 FT (714-11175) | LFT | 115 | $1,500.00 | $1,635.00 | $2,000.00 | $2,200.00 | $1,270.00 |
| 0053 | Pipe, type 3, circular, diameter 36 in. (715-05177) | LFT | 60 | $305.00 | $358.00 | $350.00 | $295.75 | $375.00 |
| 0054 | Pipe end section, diameter 36 in. (715-46040) | EACH | 2 | $3,500.00 | $2,278.00 | $2,000.00 | $1,650.00 | $3,500.00 |
| 0055 | Road closure sign assembly (801-04308) | EACH | 6 | $234.00 | $175.00 | $234.00 | $234.00 | $375.00 |
| 0056 | Detour route marker assembly (801-06625) | EACH | 28 | $138.00 | $85.00 | $138.00 | $138.00 | $200.00 |
| 0057 | Construction sign, type A (801-06640) | EACH | 37 | $184.00 | $175.00 | $184.00 | $184.00 | $250.00 |
| 0058 | Construction sign, type B (801-06645) | EACH | 7 | $101.00 | $75.00 | $101.00 | $101.00 | $170.00 |
| 0059 | Maintaining traffic (801-06775) | LS | 1 | $14,103 | $8,045.35 | $29,950 | $34,772 | $60,000 |
| 0060 | Barricade, type III-A (801-07118) | LFT | 72 | $14.88 | $15.00 | $15.00 | $14.88 | $20.00 |
| 0061 | Barricade, type III-B (801-07119) | LFT | 144 | $14.88 | $15.00 | $15.00 | $14.88 | $20.00 |
| 0062 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 2 | $717.00 | $300.00 | $750.00 | $717.00 | $380.00 |
| 0063 | Grooving for pavement markings (808-12032) | LFT | 1,581 | $0.72 | $2.00 | $1.00 | $0.72 | $4.00 |
| 0064 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 906 | $1.19 | $2.50 | $1.20 | $1.19 | $5.00 |
| 0065 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 598 | $1.19 | $2.50 | $1.20 | $1.19 | $5.00 |
| 0066 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 12 | $19.50 | $80.00 | $40.00 | $19.50 | $100.00 |
| 0067 | Snowplowable raised pavement marker (808-75998) | EACH | 12 | $133.00 | $100.00 | $133.00 | $133.00 | $120.00 |
| 0068 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 77 | $1.94 | $3.00 | $2.00 | $1.94 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.