INDOT contract R-44758-A bid tabulation
TREE REMOVAL AND TRIMMING. Let by Indiana DOT on January 15, 2025, Various, LaPorte. 4 bids received; low bid $287,485 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 21
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $287,485 | Low |
| 2 | Yardberry Landscape Company | $311,130 | +8.0% |
| 3 | Homer Tree Service Inc | $337,155 | +17% |
| 4 | Morphey Construction Inc. | $680,000 | +137% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Yardberry Landscape Company | 3. Homer Tree Service Inc | 4. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $23,685 | $30,000 | $19,800 | $1.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $30,285 | $15,000 | $32,750 | $128,800 |
| 0008 | Tree, 6 in., remove (201-02245) | EACH | 3 | $710.00 | $800.00 | $1,000.00 | $2,700.00 |
| 0009 | Tree, 10 in., remove (201-02250) | EACH | 5 | $1,030.00 | $1,200.00 | $1,500.00 | $3,300.00 |
| 0010 | Tree, 18 in., remove (201-02255) | EACH | 7 | $1,885.00 | $2,000.00 | $1,900.00 | $4,000.00 |
| 0011 | Tree, 30 in., remove (201-02260) | EACH | 3 | $3,250.00 | $3,000.00 | $4,800.00 | $9,500.00 |
| 0012 | Clearing and grubbing (201-06587) | ACRE | 1.13 | $58,770 | $80,000 | $120,000 | $180,000 |
| 0013 | Stormwater management budget (205-12108) | DOL | 20,425 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0014 | Stormwater management implementation (205-12616) | LS | 1 | $8,735.00 | $5,000.00 | $20,425 | $40,000 |
| 0015 | Guardrail, reset (601-06035) | LFT | 50 | $438.00 | $100.00 | $275.00 | $100.00 |
| 0016 | Fence, chain link, reset (603-06065) | LFT | 80 | $162.00 | $100.00 | $101.75 | $100.00 |
| 0017 | Field office, type C (628-09403) | MOS | 6 | $5,265.00 | $2,500.00 | $3,500.00 | $3,000.00 |
| 0018 | Construction sign, type A (801-06640) | EACH | 60 | $307.00 | $225.00 | $192.50 | $200.00 |
| 0019 | Construction sign, type B (801-06645) | EACH | 16 | $175.00 | $150.00 | $110.00 | $100.00 |
| 0020 | Flashing arrow sign (801-06710) | DAY | 100 | $25.00 | $50.00 | $27.50 | $20.00 |
| 0021 | Maintaining traffic (801-06775) | LS | 1 | $17,545 | $70,000 | $11,000 | $159,669 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.