INDOT contract R-45209-A bid tabulation
ROAD RECONSTRUCTION. Let by Indiana DOT on January 14, 2026, Marion, Greenfield. 4 bids received; low bid $5,298,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 183
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $5,298,000 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $5,437,076 | +3.0% |
| 3 | Beaty Construction Inc | $5,467,778 | +3.0% |
| 4 | William Charles Construction Company | $5,820,000 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. Rieth-Riley Construction Co., Inc. | 3. Beaty Construction Inc | 4. William Charles Construction Company |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $40,000 | $25,500 | $115,000 | $75,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $265,000 | $329,724 | $470,826 | $459,875 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $20,000 | $79,178 | $61,972 | $50,000 |
| 0011 | Pavement removal (202-02240) | SYS | 3,982 | $35.00 | $36.36 | $27.83 | $42.00 |
| 0012 | Curb, concrete, remove (202-02278) | LFT | 1,224 | $22.00 | $38.16 | $8.24 | $15.00 |
| 0013 | Parking meter , days (202-04650) | EACH | 1,000 | $32.00 | $32.00 | $32.00 | $32.00 |
| 0014 | Parking meter , paybox reinstallation (202-04650) | EACH | 3 | $110.00 | $110.00 | $110.00 | $110.00 |
| 0015 | Parking meter , reinstallation (202-04650) | EACH | 22 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0016 | Sidewalk concrete, remove (202-52710) | SYS | 1,949 | $28.00 | $37.04 | $37.04 | $25.00 |
| 0017 | Inlet, remove (202-91385) | EACH | 30 | $800.00 | $786.67 | $1,417.08 | $310.00 |
| 0018 | Manhole, remove (202-93047) | EACH | 3 | $1,000.00 | $949.88 | $2,770.09 | $3,600.00 |
| 0019 | Pipe, remove (202-96133) | LFT | 609 | $30.00 | $46.32 | $116.77 | $120.00 |
| 0020 | Transportation of salvageable items (202-96151) | LS | 1 | $1,000.00 | $1,229.10 | $7,825.96 | $11,160 |
| 0021 | Excavation, common (203-02000) | CYS | 1,490 | $70.00 | $100.91 | $42.92 | $60.00 |
| 0022 | Stormwater management budget (205-12108) | DOL | 3,140 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0023 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $40,576 | $27,291 | $4,200.00 |
| 0024 | SWQCP preparation (205-12618) | LS | 1 | $1,600.00 | $3,000.00 | $2,300.00 | $4,270.00 |
| 0025 | Subgrade treatment, type II (207-08264) | SYS | 3,299 | $30.00 | $33.65 | $28.92 | $34.00 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 16 | $180.00 | $306.32 | $130.21 | $140.00 |
| 0027 | Structure backfill, type 2 (211-09265) | CYS | 149 | $80.00 | $69.95 | $77.64 | $116.00 |
| 0028 | Structure backfill, type 5 (211-09268) | CYS | 6 | $300.00 | $289.58 | $314.81 | $255.00 |
| 0029 | Geotextile for pavement, type 2B (214-12239) | SYS | 990 | $5.00 | $6.66 | $4.75 | $2.50 |
| 0030 | Compacted aggregate, no. 2 (301-12231) | CYS | 340 | $100.00 | $100.77 | $61.01 | $110.00 |
| 0031 | Subbase for PCCP (302-06464) | CYS | 825 | $100.00 | $138.54 | $95.96 | $100.00 |
| 0032 | Dense graded subbase (302-07455) | CYS | 315 | $100.00 | $129.89 | $191.07 | $117.00 |
| 0033 | Compacted aggregate, no. 53, temporary for driveways (303-08210) | TON | 150 | $50.00 | $106.69 | $110.86 | $60.00 |
| 0034 | Brick pavement, remove and salvage (305-95873) | SYS | 100 | $20.00 | $79.10 | $54.84 | $85.00 |
| 0035 | Milling, transition (306-08043) | SYS | 306 | $10.00 | $88.90 | $14.71 | $3.00 |
| 0036 | HMA wedge and level, type B (402-07451) | TON | 84 | $170.00 | $351.10 | $300.00 | $570.00 |
| 0037 | HMA for temporary pavement, type B (402-10084) | TON | 50 | $140.00 | $339.27 | $200.00 | $630.00 |
| 0038 | PCCP, 9 in. (502-06457) | SYS | 3,252 | $130.00 | $139.29 | $93.72 | $140.00 |
| 0039 | PCCP, 6 in. (502-06627) | SYS | 1,890 | $125.00 | $96.39 | $100.27 | $95.00 |
| 0040 | PCCP, 12.5 in. (502-08204) | SYS | 41 | $600.00 | $352.47 | $387.62 | $615.00 |
| 0041 | PCCP, 5 in. , variable depth (502-12313) | SYS | 166 | $140.00 | $115.88 | $78.89 | $185.00 |
| 0042 | Retrofitted tie bars (503-03489) | EACH | 267 | $20.00 | $32.18 | $44.02 | $42.00 |
| 0043 | D-1 contraction joint (503-05240) | LFT | 1,821 | $10.00 | $20.90 | $15.12 | $12.00 |
| 0044 | Pavers , type 1, clay (604-04740) | SFT | 47,868 | $25.00 | $22.45 | $22.45 | $22.45 |
| 0045 | Pavers , type 2, clay, thin veneer (604-04740) | SFT | 3,461 | $21.00 | $17.88 | $17.88 | $17.88 |
| 0046 | Sidewalk, concrete (604-06070) | SYS | 51 | $140.00 | $145.17 | $112.17 | $260.00 |
| 0047 | Curb ramp, concrete (604-08086) | SYS | 324 | $450.00 | $265.23 | $162.74 | $165.00 |
| 0048 | Detectable warning surfaces , DPW modified (604-12083) | SYS | 35 | $400.00 | $392.13 | $350.17 | $1,175.00 |
| 0049 | Curb, concrete (605-06120) | LFT | 13 | $160.00 | $124.21 | $101.61 | $375.00 |
| 0050 | Curb, concrete , modified (605-06120) | LFT | 648 | $100.00 | $65.24 | $80.70 | $75.00 |
| 0051 | Curb, concrete , modified 2 (605-06120) | LFT | 679 | $90.00 | $73.14 | $82.56 | $75.00 |
| 0052 | Curb, concrete , modified 3 (605-06120) | LFT | 35 | $165.00 | $129.61 | $273.56 | $178.00 |
| 0053 | Curb, concrete , modified 4 (605-06120) | LFT | 148 | $150.00 | $67.38 | $169.30 | $65.00 |
| 0054 | Curb, concrete , modified 5 (605-06120) | LFT | 94 | $190.00 | $71.60 | $51.04 | $115.00 |
| 0055 | Curb, concrete, type B , modified (605-06121) | LFT | 16 | $190.00 | $99.21 | $168.73 | $290.00 |
| 0056 | Center curb, concrete, type B , modified (605-06205) | LFT | 15 | $300.00 | $140.00 | $192.12 | $300.00 |
| 0057 | HMA for approaches, type B (610-07487) | TON | 26 | $200.00 | $376.21 | $200.00 | $570.00 |
| 0058 | Bench , type 1 (618-03812) | EACH | 9 | $4,000.00 | $3,614.55 | $3,000.00 | $5,155.00 |
| 0059 | Bicycle rack , type 1 (618-04181) | EACH | 11 | $2,000.00 | $1,762.99 | $1,500.00 | $2,200.00 |
| 0060 | Trash receptacle (618-97672) | EACH | 5 | $2,000.00 | $991.64 | $2,000.00 | $2,580.00 |
| 0061 | Topsoil , amended planting soil (621-06570) | CYS | 150 | $200.00 | $175.00 | $150.00 | $250.00 |
| 0062 | Topsoil , planting soil, stormwater mix (621-06570) | CYS | 23 | $300.00 | $250.00 | $300.00 | $355.00 |
| 0063 | Topsoil , structural soil (621-06570) | CYS | 524 | $250.00 | $275.33 | $157.38 | $235.00 |
| 0064 | Mulch, hardwood shredded bark (621-98038) | CYS | 41 | $100.00 | $100.00 | $100.00 | $142.00 |
| 0065 | Planter , urn, type 1 (622-03948) | EACH | 10 | $1,000.00 | $1,331.92 | $1,000.00 | $2,825.00 |
| 0066 | Planter , urn, type 2 (622-03948) | EACH | 22 | $1,700.00 | $2,124.94 | $1,500.00 | $2,730.00 |
| 0067 | Tree grate (622-04648) | EACH | 14 | $7,500.00 | $4,252.24 | $6,000.00 | $3,160.00 |
| 0068 | Plant, annual (622-05605) | EACH | 616 | $20.00 | $18.30 | $18.30 | $26.00 |
| 0069 | Plant, deciduous tree, single stem, over 3.5 in. (622-05652) | EACH | 17 | $700.00 | $700.00 | $700.00 | $1,000.00 |
| 0070 | Plant, perennial , 1 gallon (622-05654) | EACH | 258 | $16.00 | $15.70 | $15.70 | $22.00 |
| 0071 | Plant, perennial , 3 gallon (622-05654) | EACH | 135 | $55.00 | $54.25 | $54.25 | $78.00 |
| 0072 | Plant, perennial , 5 gallon (622-05654) | EACH | 12 | $73.00 | $72.80 | $72.80 | $100.00 |
| 0073 | Plant, perennial , no. 32, plug (622-05654) | EACH | 448 | $9.00 | $8.35 | $8.35 | $12.00 |
| 0074 | Field office, type C (628-09403) | MOS | 20 | $1,000.00 | $5,595.88 | $3,320.00 | $4,270.00 |
| 0075 | Computer system equipment (628-11976) | EACH | 1 | $1,000.00 | $1,165.81 | $1,200.00 | $2,135.00 |
| 0076 | Patching concrete structures (710-09158) | SFT | 100 | $60.00 | $147.68 | $155.00 | $165.00 |
| 0077 | Waterproofing membrane, type 2 (714-000086) | SFT | 1,783 | $7.00 | $6.81 | $8.00 | $3.75 |
| 0078 | Waterproofing membrane, type 3 (714-000087) | SFT | 5,474 | $8.00 | $8.01 | $9.00 | $3.75 |
| 0079 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 1,056 | $25.00 | $9.90 | $19.98 | $30.00 |
| 0080 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 528 | $115.00 | $103.57 | $113.16 | $146.00 |
| 0081 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 25 | $125.00 | $106.19 | $172.40 | $360.00 |
| 0082 | Stormwater treatment system (715-08048) | EACH | 2 | $20,000 | $21,071 | $14,900 | $20,000 |
| 0083 | HMA for structure installation, type B (715-08305) | TON | 15 | $200.00 | $578.70 | $180.00 | $570.00 |
| 0084 | Video inspection for pipe (715-09064) | LFT | 631 | $4.00 | $1.95 | $4.50 | $7.50 |
| 0085 | Geotextile for underdrains, type 2A (718-12307) | SYS | 743 | $3.00 | $7.26 | $3.25 | $5.00 |
| 0086 | Aggregate for underdrains (718-52610) | CYS | 75 | $120.00 | $128.00 | $69.00 | $48.00 |
| 0087 | Manhole, type C15 (720-03757) | EACH | 1 | $5,000.00 | $5,822.61 | $5,283.25 | $5,725.00 |
| 0088 | Trench drain , irrigation (720-07309) | LFT | 209 | $600.00 | $485.56 | $542.00 | $60.00 |
| 0089 | Casting, manhole, adjust to grade (720-12798) | EACH | 2 | $1,000.00 | $524.07 | $902.73 | $2,000.00 |
| 0090 | Casting, manhole, adjust to grade , sidewalk grate (720-12798) | EACH | 2 | $1,500.00 | $524.07 | $5,360.35 | $2,660.00 |
| 0091 | Inlet, type A8 (720-45015) | EACH | 1 | $3,300.00 | $3,176.21 | $2,565.02 | $4,180.00 |
| 0092 | Inlet, type E7 (720-45030) | EACH | 1 | $3,000.00 | $3,204.05 | $2,597.05 | $4,280.00 |
| 0093 | Inlet, type J10 (720-45045) | EACH | 2 | $3,600.00 | $4,129.90 | $2,712.36 | $5,190.00 |
| 0094 | Inlet, type F7, modified (720-45135) | EACH | 2 | $3,100.00 | $3,399.66 | $2,612.90 | $4,150.00 |
| 0095 | Catch basin, type K10 (720-45250) | EACH | 1 | $4,000.00 | $4,180.04 | $2,961.59 | $4,875.00 |
| 0096 | Manhole, type C4, modified (720-45510) | EACH | 3 | $4,700.00 | $3,155.91 | $4,543.75 | $4,795.00 |
| 0097 | Manhole, type J4 (720-95422) | EACH | 2 | $5,200.00 | $6,556.08 | $4,709.97 | $5,420.00 |
| 0098 | Inlet, type B15 (720-98174) | EACH | 2 | $4,500.00 | $4,571.74 | $3,094.20 | $7,390.00 |
| 0099 | Inlet, type C15 (720-98555) | EACH | 5 | $4,500.00 | $4,571.74 | $3,179.32 | $6,055.00 |
| 0100 | Catch basin, type C15 (720-99417) | EACH | 1 | $5,000.00 | $4,902.84 | $3,831.74 | $7,220.00 |
| 0101 | Construction sign, type C (801-03290) | EACH | 2 | $650.00 | $650.00 | $425.00 | $925.00 |
| 0102 | Construction sign, type C , modified (801-03290) | EACH | 3 | $650.00 | $650.00 | $425.00 | $925.00 |
| 0103 | Road closure sign assembly (801-04308) | EACH | 2 | $1,000.00 | $1,000.00 | $279.00 | $1,425.00 |
| 0104 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 6,235 | $2.50 | $2.50 | $1.67 | $3.50 |
| 0105 | Detour route marker assembly (801-06625) | EACH | 16 | $275.00 | $275.00 | $214.00 | $390.00 |
| 0106 | Construction sign, type A (801-06640) | EACH | 11 | $350.00 | $350.00 | $277.00 | $500.00 |
| 0107 | Construction sign, type B (801-06645) | EACH | 47 | $125.00 | $125.00 | $99.00 | $178.00 |
| 0108 | Flashing arrow sign (801-06710) | DAY | 595 | $5.00 | $5.00 | $12.00 | $7.00 |
| 0109 | Tubular marker, permanent , remove and reset (801-06735) | EACH | 12 | $300.00 | $500.00 | $120.00 | $710.00 |
| 0110 | Maintaining traffic (801-06775) | LS | 1 | $249,335 | $106,126 | $485,766 | $80,000 |
| 0111 | Barricade, type III-A (801-07118) | LFT | 177 | $30.00 | $30.00 | $18.00 | $42.00 |
| 0112 | Temporary pavement marking, 24 in. (801-07612) | LFT | 40 | $12.00 | $12.00 | $12.00 | $17.00 |
| 0113 | Temporary traffic barrier, type 2 , modified (801-08401) | LFT | 600 | $25.00 | $227.15 | $120.26 | $330.00 |
| 0114 | Temporary curb ramp (801-11990) | EACH | 5 | $3,440.55 | $2,812.44 | $3,760.00 | $7,100.00 |
| 0115 | Law enforcement officer (801-12324) | HRS | 400 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0116 | Temporary pedestrian channelizer (801-12862) | LFT | 76 | $30.00 | $88.67 | $79.00 | $42.00 |
| 0117 | Sign, sheet, remove (802-04089) | EACH | 3 | $100.00 | $100.00 | $100.00 | $142.00 |
| 0118 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 57 | $46.00 | $46.00 | $46.00 | $65.00 |
| 0119 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 64 | $55.00 | $55.00 | $55.00 | $80.00 |
| 0120 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 20 | $70.00 | $70.00 | $70.00 | $100.00 |
| 0121 | Sign post, type , banner arm (802-11648) | EACH | 32 | $975.00 | $975.00 | $975.00 | $1,390.00 |
| 0122 | Traffic signal equipment, remove (805-01300) | EACH | 2 | $5,205.00 | $5,205.00 | $5,205.00 | $7,410.00 |
| 0123 | Handhole, signal, type 1 (805-01842) | EACH | 6 | $3,000.00 | $3,000.00 | $3,000.00 | $4,270.00 |
| 0124 | Transportation of salvageable signal equipment (805-02087) | LS | 1 | $1,550.00 | $1,550.00 | $1,550.00 | $2,205.00 |
| 0125 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 10 | $1,500.00 | $1,500.00 | $1,500.00 | $2,135.00 |
| 0126 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 7 | $2,000.00 | $2,000.00 | $2,000.00 | $2,850.00 |
| 0127 | Conduit, rigid PVC, 1.50 in. , schedule 40 (805-03083) | LFT | 221 | $50.00 | $50.00 | $50.00 | $72.00 |
| 0128 | Conduit, PVC, 1 in. schedule 40 (805-03972) | LFT | 205 | $27.00 | $27.00 | $27.00 | $40.00 |
| 0129 | Video vehicle detector system (805-04782) | EACH | 1 | $30,500 | $30,500 | $30,500 | $44,000 |
| 0130 | Controller and cabinet , relocate and rewire (805-04952) | EACH | 1 | $8,500.00 | $8,500.00 | $8,500.00 | $12,100 |
| 0131 | Signal pole, pedestal, 4 FT (805-05405) | EACH | 5 | $1,500.00 | $1,500.00 | $1,500.00 | $2,135.00 |
| 0132 | Signal cable , preemption (805-08129) | LFT | 181 | $9.00 | $9.00 | $9.00 | $13.00 |
| 0133 | Conduit, PVC, 2 in. schedule 40 (805-08214) | LFT | 1,644 | $40.00 | $40.00 | $45.00 | $57.00 |
| 0134 | Cellular modem kit (805-08244) | EACH | 1 | $3,440.00 | $3,440.00 | $3,440.00 | $4,900.00 |
| 0135 | Backplate, signal (805-08487) | EACH | 10 | $1,200.00 | $1,200.00 | $1,200.00 | $1,705.00 |
| 0136 | Signal cantilever structure, single arm 35 FT , modified, painting (805-11377) | EACH | 2 | $6,500.00 | $6,500.00 | $6,500.00 | $9,250.00 |
| 0137 | Signal cantilever structure, single arm 45 FT , modified, indy DPW standard (805-11379) | EACH | 1 | $21,000 | $21,000 | $21,000 | $30,000 |
| 0138 | Signal cantilever structure, drilled shaft foundation, type B , modified, indy DPW standard (805-11384) | EACH | 1 | $7,800.00 | $7,800.00 | $7,800.00 | $11,000 |
| 0139 | Signal cantilever structure, dual arm 40 FT , modified, 20 FT, painting (805-11394) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $9,250.00 |
| 0140 | Conduit, rigid fiberglass, 2 in. (805-11816) | LFT | 1,088 | $80.00 | $80.00 | $80.00 | $115.00 |
| 0141 | Pedestrian push button, APS (805-11817) | EACH | 14 | $1,750.00 | $1,750.00 | $1,750.00 | $2,500.00 |
| 0142 | Traffic signal head, no. 3 (805-78205) | EACH | 5 | $1,270.00 | $1,270.00 | $1,270.00 | $1,800.00 |
| 0143 | Traffic signal head, no. 3 (805-78205) | EACH | 1 | $1,270.00 | $1,270.00 | $1,270.00 | $1,800.00 |
| 0144 | Signal service (805-78445) | EACH | 1 | $6,500.00 | $6,500.00 | $6,500.00 | $9,250.00 |
| 0145 | Signal cable, service, copper, 3C/8 gauge (805-78467) | LFT | 16 | $8.00 | $7.85 | $7.85 | $12.00 |
| 0146 | Signal cable, control, copper, 3C/14 gauge (805-78480) | LFT | 1,239 | $4.00 | $3.75 | $3.75 | $5.50 |
| 0147 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 2,235 | $5.00 | $4.50 | $4.50 | $6.50 |
| 0148 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 193 | $6.00 | $5.50 | $5.50 | $7.75 |
| 0149 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 183 | $7.00 | $6.25 | $6.25 | $9.00 |
| 0150 | Signal cable, control, copper, 11C/14 gauge (805-78500) | LFT | 442 | $7.00 | $7.00 | $7.00 | $10.00 |
| 0151 | Controller cabinet foundation, type M (805-78930) | EACH | 1 | $4,400.00 | $4,400.00 | $4,400.00 | $6,265.00 |
| 0152 | Signal pole, pedestal, 10 FT (805-90005) | EACH | 2 | $1,800.00 | $1,800.00 | $1,800.00 | $2,565.00 |
| 0153 | Conduit, PVC, 4 in. , schedule 40 (805-95568) | LFT | 565 | $44.00 | $44.00 | $9.58 | $62.00 |
| 0154 | Conduit, PVC, 4 in. , schedule 80 (805-95568) | LFT | 111 | $50.00 | $50.00 | $50.00 | $70.00 |
| 0155 | Service point, II, modified (807-02194) | EACH | 1 | $14,500 | $14,500 | $14,500 | $20,645 |
| 0156 | Lighting receptacle, single, waterproof (807-02819) | EACH | 15 | $850.00 | $850.00 | $850.00 | $1,210.00 |
| 0157 | Handhole, rectangular (807-08612) | EACH | 15 | $1,825.00 | $1,825.00 | $1,825.00 | $2,600.00 |
| 0158 | Wire, no. 6 copper, 1/C (807-11712) | LFT | 1,434 | $6.00 | $5.50 | $5.50 | $8.00 |
| 0159 | Lighting foundation, concrete, with grounding, 24 in. diameter X 72 in. (807-12184) | EACH | 16 | $2,300.00 | $2,300.00 | $2,300.00 | $3,275.00 |
| 0160 | Metered service point (807-12354) | EACH | 1 | $5,900.00 | $5,900.00 | $5,900.00 | $8,400.00 |
| 0161 | Wire, no. 4 copper, 1/C (807-86843) | LFT | 1,146 | $6.00 | $6.00 | $6.00 | $8.50 |
| 0162 | Light pole, handhole cover , receptacle in-use (807-91704) | EACH | 15 | $100.00 | $100.00 | $100.00 | $142.00 |
| 0163 | Wire, no. 8 copper, 1/C (807-95888) | LFT | 1,443 | $5.00 | $4.50 | $4.50 | $6.00 |
| 0164 | Wire, no. 10 copper, 1/C (807-95889) | LFT | 1,465 | $4.00 | $4.00 | $4.00 | $5.00 |
| 0165 | Pavement message marking, thermoplastic, bike symbol (808-02977) | EACH | 3 | $750.00 | $750.00 | $250.00 | $1,070.00 |
| 0166 | Pavement message marking , mma, bus (808-06609) | EACH | 1 | $525.00 | $1,000.00 | $525.00 | $1,425.00 |
| 0167 | Line, thermoplastic, broken, white, 4 in. (808-06701) | LFT | 199 | $2.00 | $2.00 | $3.59 | $3.00 |
| 0168 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 1,047 | $2.00 | $2.00 | $1.19 | $3.00 |
| 0170 | Pavement marking , mma, red (808-09968) | SFT | 666 | $10.00 | $27.50 | $10.00 | $40.00 |
| 0171 | Line, thermoplastic, dotted, white, 4 in. (808-11482) | LFT | 20 | $10.00 | $10.00 | $3.59 | $15.00 |
| 0172 | Line, thermoplastic, dotted, yellow, 4 in. (808-11493) | LFT | 112 | $10.00 | $10.00 | $3.59 | $15.00 |
| 0173 | Transverse marking, thermoplastic, parking line, white, 4 in. (808-12273) | LFT | 77 | $10.00 | $10.00 | $3.59 | $14.00 |
| 0174 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 84 | $2.00 | $2.00 | $1.19 | $2.85 |
| 0175 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 209 | $7.00 | $7.00 | $4.76 | $10.00 |
| 0176 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 56 | $14.00 | $14.00 | $9.51 | $20.00 |
| 0177 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 4 | $150.00 | $150.00 | $198.00 | $210.00 |
| 0178 | Pavement message marking, thermoplastic, 'only' (808-75325) | EACH | 1 | $500.00 | $500.00 | $267.00 | $710.00 |
| 0179 | Splice enclosure , conduit intercept (809-04969) | EACH | 1 | $1,050.00 | $200.00 | $100.00 | $5,000.00 |
| 0180 | Track, remove (202-91351) | LFT | 150 | $30.00 | $146.12 | $86.00 | $22.00 |
| 0181 | Signal pole foundation, remove (202-93995) | EACH | 1 | $500.00 | $1,050.00 | $1,050.00 | $1,500.00 |
| 0182 | Concrete, remove (202-99080) | CYS | 50 | $200.00 | $645.19 | $130.00 | $76.00 |
| 0183 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 8 | $1,500.00 | $699.49 | $1,463.00 | $2,500.00 |
| 0184 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 8 | $1,500.00 | $408.03 | $1,199.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.