INDOT contract R-45574-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on July 9, 2025, Fulton, LaPorte. 3 bids received; low bid $721,000 by Morphey Construction Inc..
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 54
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morphey Construction Inc. | $721,000 | Low |
| 2 | Bunn Excavating Inc | $757,776 | +5.0% |
| 3 | Superior Construction Co Inc | $782,142 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morphey Construction Inc. | 2. Bunn Excavating Inc | 3. Superior Construction Co Inc |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $6,296.00 | $5,551.50 | $15,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $36,000 | $27,415 | $39,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $10,000 | $3,051.31 | $5,000.00 |
| 0011 | Present structure, remove, structure no. CV 017-025-12.01 (202-51330) | LS | 1 | $10,000 | $3,610.46 | $15,000 |
| 0012 | Excavation, common (203-02000) | CYS | 110 | $60.00 | $209.35 | $150.00 |
| 0013 | Excavation, unclassified (203-02020) | CYS | 204 | $120.00 | $46.11 | $150.00 |
| 0014 | Borrow (203-02070) | CYS | 180 | $30.00 | $46.91 | $0.01 |
| 0015 | Expanded polystyrene fill (203-08279) | CYS | 118 | $190.00 | $213.20 | $200.00 |
| 0016 | Pump around (205-11626) | EACH | 1 | $10,000 | $23,384 | $15,000 |
| 0017 | Stormwater management budget (205-12108) | DOL | 12,604 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $15,135 | $5,000.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 518 | $50.00 | $47.09 | $50.00 |
| 0020 | B borrow (211-02050) | CYS | 30 | $140.00 | $81.75 | $100.00 |
| 0021 | Structure backfill, type 5 (211-09268) | CYS | 396 | $280.00 | $169.76 | $185.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 518 | $5.00 | $6.14 | $7.00 |
| 0023 | Compacted aggregate, no. 2 (301-12231) | CYS | 59 | $130.00 | $257.21 | $145.00 |
| 0024 | Compacted aggregate, no. 73 (303-07449) | TON | 145 | $60.00 | $78.10 | $40.00 |
| 0025 | Milling, transition (306-08043) | SYS | 234 | $40.00 | $28.22 | $15.00 |
| 0026 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 60 | $315.00 | $366.65 | $240.00 |
| 0027 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 65 | $183.00 | $213.01 | $220.00 |
| 0028 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 162 | $120.00 | $139.68 | $200.00 |
| 0029 | Joint adhesive, surface (401-10258) | LFT | 285 | $1.00 | $0.58 | $5.00 |
| 0030 | Joint adhesive, intermediate (401-10259) | LFT | 185 | $1.00 | $0.58 | $5.00 |
| 0031 | Asphalt for tack coat (406-05520) | TON | 1 | $600.00 | $698.38 | $1,000.00 |
| 0032 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $1,500.00 | $2,909.92 | $3,000.00 |
| 0033 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 285 | $26.00 | $2.47 | $2.12 |
| 0034 | Monument, type B (615-06505) | EACH | 2 | $2,000.00 | $2,153.34 | $3,225.00 |
| 0035 | Riprap, revetment (616-06405) | TON | 136 | $125.00 | $135.91 | $100.00 |
| 0036 | Geomembrane (616-09395) | SYS | 238 | $15.00 | $16.00 | $21.00 |
| 0037 | Geotextile for riprap, type 1A (616-12246) | SYS | 180 | $5.00 | $4.23 | $5.50 |
| 0038 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $400.00 | $872.98 | $400.00 |
| 0039 | Mulched seeding, type R (621-06559) | SYS | 1,870 | $10.00 | $4.07 | $2.76 |
| 0040 | Field office, type C (628-09403) | MOS | 8 | $3,500.00 | $5,425.06 | $1,250.00 |
| 0041 | Waterproofing membrane type 2 (714-000086) | SFT | 3,782 | $3.00 | $3.91 | $2.50 |
| 0042 | Structure, reinforced concrete, box sections, 11 FT X 7 FT (714-11755) | LFT | 122 | $1,900.00 | $2,320.50 | $2,600.00 |
| 0043 | Pipe, type 4, circular, diameter 12 in. (715-05052) | LFT | 6 | $250.00 | $87.48 | $175.00 |
| 0044 | Pipe, type 1, circular, diameter 9 in. (715-09987) | LFT | 6 | $250.00 | $153.79 | $175.00 |
| 0045 | Geotextile for underdrains, type 2B (718-12308) | SYS | 552 | $5.00 | $7.68 | $6.50 |
| 0046 | Road closure sign assembly (801-04308) | EACH | 5 | $150.00 | $60.06 | $258.00 |
| 0047 | Detour route marker assembly (801-06625) | EACH | 28 | $85.00 | $172.27 | $148.00 |
| 0048 | Construction sign, type A (801-06640) | EACH | 17 | $150.00 | $230.47 | $198.00 |
| 0049 | Maintaining traffic (801-06775) | LS | 1 | $10,000 | $10,208 | $26,006 |
| 0050 | Barricade, type III-A (801-07118) | LFT | 60 | $15.00 | $17.47 | $15.01 |
| 0051 | Barricade, type III-B (801-07119) | LFT | 72 | $15.00 | $17.47 | $15.01 |
| 0052 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 570 | $2.00 | $2.35 | $2.02 |
| 0053 | Grooving for pavement markings (808-12032) | LFT | 643 | $3.00 | $1.14 | $0.98 |
| 0054 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 73 | $1.00 | $3.40 | $2.92 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.