INDOT contract R-45629-A bid tabulation
ADA SIDEWALK RAMP CONSTRUCTION. Let by Indiana DOT on March 11, 2026, Marion, Greenfield. 5 bids received; low bid $204,299 by Olco Inc.
- Owner
- Indiana DOT
- Letting
- 11 MAR 2026
- Pay items
- 46
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Olco Inc | $204,299 | Low |
| 2 | Edward & Jones Concrete Inc | $237,644 | +16% |
| 3 | Calumet Civil Contractors Inc | $331,000 | +62% |
| 4 | Yarberry Companies Inc | $341,353 | +67% |
| 5 | Morphey Construction Inc. | $379,000 | +86% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Olco Inc | 2. Edward & Jones Concrete Inc | 3. Calumet Civil Contractors Inc | 4. Yarberry Companies Inc | 5. Morphey Construction Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $7,300.00 | $25,000 | $2,300.00 | $45,000 | $5,000.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $12,508 | $25,000 | $13,900 | $16,500 | $18,950 |
| 0008 | Clearing right-of-way (201-52370) | LS | 1 | $17,134 | $25,000 | $33,100 | $20,000 | $38,900 |
| 0009 | Curb, concrete, remove (202-02278) | LFT | 30 | $47.52 | $24.31 | $146.00 | $75.00 | $50.00 |
| 0010 | Curb and gutter, remove (202-02279) | LFT | 10 | $98.94 | $30.26 | $219.00 | $100.00 | $50.00 |
| 0011 | Sidewalk concrete, remove (202-52710) | SYS | 9 | $158.40 | $24.02 | $123.00 | $75.00 | $50.00 |
| 0012 | Signal pole foundation, remove (202-93995) | EACH | 1 | $1,800.00 | $2,242.03 | $600.00 | $1,000.00 | $1,550.00 |
| 0013 | Signal pole, remove (202-93999) | EACH | 1 | $100.00 | $124.56 | $500.00 | $1,000.00 | $500.00 |
| 0014 | Gutter, concrete, remove (202-96128) | LFT | 7 | $141.35 | $37.44 | $155.00 | $100.00 | $50.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $9,532.00 | $2,491.15 | $2,000.00 | $15,000 | $5,000.00 |
| 0017 | Compacted aggregate, no. 53 (301-12234) | CYS | 2 | $426.26 | $281.52 | $463.00 | $400.00 | $300.00 |
| 0018 | Sidewalk, concrete (604-06070) | SYS | 11 | $300.02 | $186.65 | $352.00 | $200.00 | $170.00 |
| 0019 | Curb ramp, concrete (604-08086) | SYS | 92 | $385.61 | $305.22 | $378.00 | $500.00 | $600.00 |
| 0020 | Detectable warning surfaces (604-12083) | SYS | 9 | $754.38 | $719.25 | $505.00 | $500.00 | $400.00 |
| 0021 | Detectable warning surfaces, retrofit (604-12084) | SYS | 8 | $1,115.91 | $1,441.78 | $511.00 | $500.00 | $600.00 |
| 0022 | Curb, concrete (605-06120) | LFT | 30 | $181.52 | $46.79 | $429.00 | $100.00 | $150.00 |
| 0023 | Curb and gutter, concrete (605-06140) | LFT | 10 | $289.23 | $50.35 | $241.00 | $150.00 | $150.00 |
| 0024 | Gutter, concrete, type A (607-06175) | LFT | 7 | $472.18 | $70.95 | $172.00 | $150.00 | $150.00 |
| 0025 | Water (621-06567) | KGAL | 1 | $904.60 | $31.14 | $25.00 | $1.00 | $100.00 |
| 0026 | Sodding, nursery (621-06575) | SYS | 35 | $44.16 | $145.98 | $279.00 | $75.00 | $50.00 |
| 0027 | Field office, type C (628-09403) | MOS | 12 | $1,338.00 | $50.00 | $3,200.00 | $3,500.00 | $5,000.00 |
| 0028 | Temporary transverse pavement marking, 6 in. (801-06214) | LFT | 213 | $2.50 | $3.11 | $5.00 | $7.00 | $3.00 |
| 0029 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 16 | $10.00 | $12.46 | $20.00 | $12.00 | $10.00 |
| 0030 | Construction sign, type A (801-06640) | EACH | 13 | $200.00 | $249.11 | $275.00 | $250.00 | $200.00 |
| 0031 | Construction sign, type B (801-06645) | EACH | 18 | $100.00 | $124.56 | $100.00 | $130.00 | $100.00 |
| 0032 | Maintaining traffic (801-06775) | LS | 1 | $24,456 | $40,000 | $93,295 | $35,000 | $77,281 |
| 0033 | Temporary curb ramp (801-11990) | EACH | 4 | $635.59 | $3,113.93 | $2,000.00 | $20.00 | $3,000.00 |
| 0034 | Temporary accessible pedestrian path (801-12641) | SYS | 45 | $55.99 | $56.05 | $100.00 | $300.00 | $100.00 |
| 0035 | Temporary pedestrian channelizer (801-12862) | LFT | 72 | $15.00 | $18.68 | $55.00 | $150.00 | $15.00 |
| 0036 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 3 | $300.00 | $373.67 | $375.00 | $330.00 | $300.00 |
| 0037 | Traffic signal equipment, remove (805-01300) | EACH | 8 | $100.00 | $124.56 | $225.00 | $440.00 | $500.00 |
| 0038 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 8 | $560.00 | $697.52 | $900.00 | $1,760.00 | $2,000.00 |
| 0039 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 2 | $1,800.00 | $2,242.03 | $2,500.00 | $2,150.00 | $4,500.00 |
| 0040 | Signal pole, pedestal, 4 FT (805-05405) | EACH | 2 | $700.00 | $871.90 | $1,000.00 | $2,150.00 | $2,000.00 |
| 0041 | Conduit, PVC, 2 in. (805-06595) | LFT | 182 | $18.00 | $22.42 | $30.00 | $55.00 | $50.00 |
| 0042 | Pedestrian push button, APS (805-11817) | EACH | 8 | $1,100.00 | $1,370.13 | $1,150.00 | $2,000.00 | $2,500.00 |
| 0043 | Line, remove (808-06716) | LFT | 395 | $2.00 | $2.49 | $5.00 | $10.00 | $2.00 |
| 0044 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 31 | $20.00 | $24.91 | $30.00 | $25.00 | $20.00 |
| 0045 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 365 | $5.00 | $6.23 | $7.50 | $7.00 | $5.00 |
| 0046 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 202 | $7.00 | $8.72 | $5.00 | $7.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of March 11, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.