INDOT contract R-46048-A bid tabulation
PAVEMENT PATCHING. Let by Indiana DOT on May 7, 2025, Lake, LaPorte. 3 bids received; low bid $6,469,555 by Superior Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 07 MAY 2025
- Pay items
- 52
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Construction Co Inc | $6,469,555 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $7,889,198 | +22% |
| 3 | Milestone Contractors LP | $8,574,870 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Construction Co Inc | 2. Rieth-Riley Construction Co., Inc. | 3. Milestone Contractors LP |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $75,000 | $8,050.00 | $40,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $330,000 | $320,325 | $340,000 |
| 0008 | Barrier wall, concrete, remove (202-94954) | LFT | 635 | $50.00 | $61.50 | $30.00 |
| 0009 | Lean concrete base, 9 in. (305-12695) | SYS | 3,150 | $75.00 | $50.00 | $70.00 |
| 0010 | Retrofitted tie bars (503-03489) | EACH | 375 | $45.00 | $40.00 | $65.00 |
| 0011 | D-1 contraction joint (503-05240) | LFT | 960 | $35.00 | $40.00 | $44.00 |
| 0012 | PCCP patching, full depth (506-06333) | SYS | 2,825 | $475.00 | $450.00 | $600.00 |
| 0013 | Concrete barrier (602-01064) | LFT | 635 | $150.00 | $196.00 | $170.00 |
| 0014 | Computer system equipment (628-11976) | EACH | 3 | $500.00 | $1,300.00 | $1,400.00 |
| 0015 | Field office, type D (628-12683) | MOS | 16 | $2,500.00 | $4,630.00 | $3,100.00 |
| 0016 | Field drilled hole in concrete (702-51863) | EACH | 4 | $100.00 | $268.00 | $750.00 |
| 0017 | Mobile barrier budget (801-000093) | DOL | 140,000 | $1.00 | $1.00 | $1.00 |
| 0018 | Construction sign, type C (801-03290) | EACH | 8 | $274.00 | $274.00 | $274.00 |
| 0019 | Road closure sign assembly (801-04308) | EACH | 20 | $291.00 | $291.00 | $291.00 |
| 0020 | Patroller (801-06198) | DAY | 155 | $2,485.00 | $1,910.00 | $1,200.00 |
| 0021 | Temporary pavement marking, 6 in. (801-06206) | LFT | 1,199,458 | $0.31 | $0.31 | $0.31 |
| 0022 | Construction sign, type A (801-06640) | EACH | 85 | $238.00 | $238.00 | $238.00 |
| 0023 | Flashing arrow sign (801-06710) | DAY | 84 | $15.00 | $15.00 | $15.00 |
| 0024 | Maintaining traffic (801-06775) | LS | 1 | $981,917 | $523,000 | $595,000 |
| 0025 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 8 | $2,500.00 | $10,825 | $18,000 |
| 0026 | Barricade, type III-A (801-07118) | LFT | 544 | $15.76 | $15.76 | $16.00 |
| 0027 | Temporary traffic barrier, type 1 (801-08400) | LFT | 25,936 | $10.00 | $45.50 | $48.00 |
| 0028 | Temporary traffic barrier, type 2 (801-08401) | LFT | 15,816 | $10.00 | $32.25 | $60.00 |
| 0029 | Temporary traffic barrier, anchored, type 1 (801-08507) | LFT | 400 | $10.00 | $82.50 | $62.00 |
| 0030 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 3,900 | $15.00 | $56.50 | $62.00 |
| 0031 | Portable changeable message sign (801-11642) | EACH | 26 | $5,456.00 | $5,456.00 | $5,456.00 |
| 0032 | Truck mounted attenuator (801-12042) | DAY | 310 | $1.00 | $191.00 | $300.00 |
| 0033 | Automated work zone information system (801-12544) | EACH | 18 | $100.00 | $3,879.00 | $3,879.00 |
| 0034 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 32 | $10.00 | $1,283.00 | $1,283.00 |
| 0035 | Temporary pavement marking, 10 in. (801-12955) | LFT | 43,957 | $1.64 | $1.64 | $1.64 |
| 0036 | Temporary crossover, type B (801-52817) | EACH | 1 | $4,500.00 | $55,854 | $28,000 |
| 0037 | Temporary buzz strips (801-97643) | LFT | 7,992 | $1.00 | $19.80 | $19.80 |
| 0038 | Transverse marking, remove (808-06368) | LFT | 814 | $7.18 | $7.18 | $7.18 |
| 0039 | Line, remove (808-06716) | LFT | 1,444,561 | $0.49 | $0.49 | $0.50 |
| 0040 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0041 | Transverse marking, multi-component, crosshatch line, white, 24 in. (808-10038) | LFT | 814 | $13.22 | $13.22 | $13.22 |
| 0042 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 58,945 | $0.77 | $0.77 | $0.77 |
| 0043 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 60,717 | $0.77 | $0.77 | $0.77 |
| 0044 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 30,940 | $0.79 | $0.79 | $0.79 |
| 0045 | Grooving for pavement markings (808-12032) | LFT | 3,304 | $0.72 | $0.72 | $0.72 |
| 0046 | Line, multi-component, dotted, white, 6 in. (808-12353) | LFT | 3,369 | $2.11 | $2.11 | $2.11 |
| 0047 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 12,866 | $2.69 | $2.69 | $2.69 |
| 0048 | Line, multi-component, broken, black, 6 in. (808-12949) | LFT | 30,940 | $1.64 | $1.64 | $1.64 |
| 0049 | Line, multi-component, dotted, black, 6 in. (808-12951) | LFT | 3,369 | $2.21 | $2.21 | $2.21 |
| 0050 | Prismatic reflector (808-75994) | EACH | 6,044 | $8.44 | $8.44 | $8.44 |
| 0051 | Snowplowable raised pavement marker (808-75998) | EACH | 209 | $32.75 | $32.75 | $32.75 |
| 0052 | PCCP patching, full depth , overnight patching with mobile barrier (506-06333) | SYS | 325 | $1,900.00 | $2,570.00 | $1,450.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.