INDOT contract R-46447-A bid tabulation

SIDEWALK CONSTRUCTION AND DRAINAGE IMPROVEMENTS. Let by Indiana DOT on November 5, 2026, Lake, LaPorte. 3 bids received; low bid $1,417,399 by Milestone Contractors LP.

Owner
Indiana DOT
Letting
05 NOV 2026
Pay items
71
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Milestone Contractors LP$1,417,399Low
2Rieth-Riley Construction Co., Inc.$1,563,548+10%
3Gariup Construction Co Inc$1,579,500+11%
INDOT contract R-46447-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Milestone Contractors LP2. Rieth-Riley Construction Co., Inc.3. Gariup Construction Co Inc
0001Construction engineering (105-06845)LS1$11,124$32,638$32,000
0002Liquidated damages (109-08359)DOL1$1.00$1.00$1.00
0003Contract liens (109-08360)DOL1$1.00$1.00$1.00
0004Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00
0005Quality adjustments, temporary traffic control devices and markings (109-08443)DOL1$1.00$1.00$1.00
0006Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00
0007Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00
0008Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00
0009Mobilization and demobilization (110-01001)LS1$50,000$147,735$167,115
0010Tree, 6 in., remove (201-02245)EACH1$600.00$300.00$330.00
0011Tree, 10 in., remove (201-02250)EACH6$1,000.00$400.00$440.00
0012Tree, 18 in., remove (201-02255)EACH3$1,800.00$800.00$850.00
0013Clearing right-of-way (201-52370)LS1$55,704$3,580.00$25,000
0014Curb, concrete, remove (202-02278)LFT40$110.00$80.25$18.00
0015Curb and gutter, remove (202-02279)LFT266$51.00$26.10$14.00
0016Sidewalk concrete, remove (202-52710)SYS81$96.00$65.40$18.00
0017Inlet, remove (202-91385)EACH6$592.65$592.65$1,200.00
0018Concrete, remove (202-93615)SYS100$82.00$64.65$20.00
0019Pipe, remove (202-96133)LFT351.50$21.81$21.81$30.00
0020Excavation, common (203-02000)CYS759$67.00$130.65$65.00
0021Stormwater management budget (205-12108)DOL20,718.75$1.00$1.00$1.00
0022Stormwater management implementation (205-12616)LS1$4,943.82$13,745$10,000
0023SWQCP preparation (205-12618)LS1$1,600.00$2,550.00$2,800.00
0024Subgrade treatment, type III (207-08266)SYS3,004$1.75$1.25$5.00
0025B borrow (211-02050)CYS89$110.00$190.15$55.00
0026Structure backfill, type 1 (211-09264)CYS1,084$47.39$58.49$65.00
0027Flowable backfill, removable (213-09270)CYS57.70$305.21$305.21$350.00
0028Compacted aggregate, no. 53 (301-12234)CYS675$120.00$147.40$72.00
0029HMA patching, full depth, type B (304-12623)TON162$376.00$415.20$160.00
0030Milling, asphalt, 1 1/2 in. (306-08034)SYS3,825$5.00$4.50$4.00
0031Milling, approach (306-08432)SYS253$36.00$16.65$15.00
0032QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001)TON376$184.00$154.00$160.00
0033QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052)TON120$259.00$131.00$230.00
0034Asphalt for tack coat (406-05520)TON1.50$2,394.00$3,105.00$2,700.00
0035Sidewalk, concrete (604-06070)SYS760$100.00$83.05$82.00
0036Curb ramp, concrete (604-08086)SYS133$235.00$170.60$170.00
0037Detectable warning surfaces (604-12083)SYS17$270.00$222.75$280.00
0038Curb, concrete (605-06120)LFT338$56.00$49.50$52.00
0039Curb and gutter, concrete (605-06140)LFT691$76.00$63.41$50.00
0040Curb and gutter, concrete , modified (605-06140)LFT376$76.00$62.25$52.00
0041HMA for approaches, type B (610-07487)TON26$405.00$439.20$430.00
0042PCCP for approaches, 6 in. (610-08446)SYS292$144.00$137.95$86.00
0043Mailbox assembly, reset, single (611-08232)EACH8$1,365.00$684.20$500.00
0044Mobilization and demobilization for seeding (621-01004)EACH1$900.00$600.00$500.00
0045Mulched seeding, type U (621-06560)SYS3,083$1.40$2.18$1.60
0046Sodding (621-06574)SYS375$24.00$14.25$26.00
0047Topsoil processing and distribution (629-000149)SYS3,083$8.00$24.35$10.00
0048Topsoil amendment budget (629-000150)DOL6,166$1.00$1.00$1.00
0049Pipe, type 2, circular, diameter 12 in. (715-05149)LFT555$96.34$97.51$160.00
0050Pipe, type 2, circular, diameter 21 in. (715-05153)LFT70$145.57$148.32$220.00
0051Pipe, type 2, circular, diameter 24 in. (715-05154)LFT1,229$156.69$159.79$210.00
0052Adjust water valve to grade (715-94530)EACH15$807.57$807.57$2,000.00
0053Casting, type 4, furnish and adjust to grade (720-44025)EACH1$1,193.34$1,193.34$1,820.00
0054Manhole, type C4 (720-45410)EACH19$3,784.64$3,854.40$5,600.00
0055Manhole, type C2 (720-90984)EACH2$4,464.41$4,518.64$6,160.00
0056Inlet, type B15 (720-98174)EACH4$3,801.13$3,850.98$5,500.00
0057Catch basin, modified (720-98363)EACH16$5,018.00$5,061.64$6,200.00
0058Road closure sign assembly (801-04308)EACH4$165.00$165.00$180.00
0059Construction sign, type A (801-06640)EACH35$145.00$145.00$160.00
0060Construction sign, type B (801-06645)EACH12$112.00$112.00$120.00
0061Maintaining traffic (801-06775)LS1$14,098$22,540$20,000
0062Barricade, type III-A (801-07118)LFT96$12.75$12.75$14.00
0063Temporary traffic barrier, type 2 (801-08401)LFT112$61.07$151.45$110.00
0064Sign post, square, type 1, reinforced anchor base (802-05701)LFT38.50$35.00$35.00$38.00
0065Sign, sheet assembly, relocate (802-07058)EACH1$230.00$230.00$540.00
0066Sign, sheet, relocate (802-07060)EACH2$150.00$150.00$540.00
0067Light pole, timber, relocate (807-02823)EACH1$6,500.00$6,500.00$9,200.00
0068Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439)LFT96$12.00$12.00$13.00
0069Transverse marking, thermoplastic, parking line, white, 4 in. (808-12273)LFT48$3.00$3.00$3.30
0070Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297)LFT70$12.00$12.00$13.00
0071Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300)LFT245$5.00$5.00$6.00
INDOT contract R-46447-A: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of November 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy