INDOT contract R-46453-A bid tabulation
SMALL STRUCTURES AND DRAINS CONSTRUCTION. Let by Indiana DOT on May 7, 2026, Putnam, Crawfordsville. 3 bids received; low bid $1,935,552 by Superior Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 07 MAY 2026
- Pay items
- 74
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Construction Co Inc | $1,935,552 | Low |
| 2 | Morphey Construction Inc. | $2,674,000 | +38% |
| 3 | Milestone Contractors South LLC | $2,892,231 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Construction Co Inc | 2. Morphey Construction Inc. | 3. Milestone Contractors South LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $15,000 | $11,120 | $20,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 14 | $650.00 | $300.00 | $1,610.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $95,000 | $120,000 | $135,235 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $38,500 | $31,000 | $55,000 |
| 0013 | Excavation, common (203-02000) | CYS | 667 | $195.00 | $67.00 | $125.00 |
| 0014 | Pump around (205-11626) | EACH | 7 | $500.00 | $13,000 | $1,000.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 20,800 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $10,000 | $730.00 | $10,000 |
| 0017 | Subgrade treatment, type II (207-08264) | SYS | 31 | $55.00 | $40.00 | $160.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 5,583 | $30.00 | $49.00 | $60.00 |
| 0019 | Structure backfill, type 1 (211-09264) | CYS | 379 | $37.00 | $85.00 | $165.00 |
| 0020 | Structure backfill, type 2 (211-09265) | CYS | 3 | $51.00 | $110.00 | $655.00 |
| 0021 | Geogrid, type IB (214-11796) | SYS | 5,613 | $2.50 | $3.00 | $2.50 |
| 0022 | Compacted aggregate, no. 5 (301-12232) | CYS | 18 | $120.00 | $118.00 | $330.00 |
| 0023 | Compacted aggregate, no. 53 (303-01180) | TON | 568 | $30.00 | $80.00 | $100.00 |
| 0024 | Widening with HMA, type C (304-07494) | TON | 1,333 | $123.00 | $353.00 | $280.00 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,821 | $4.35 | $34.00 | $25.00 |
| 0026 | Milling, approach (306-08432) | SYS | 171 | $4.35 | $28.00 | $45.00 |
| 0027 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 533 | $283.00 | $515.00 | $515.00 |
| 0028 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 320 | $355.00 | $515.00 | $515.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 1,020 | $156.00 | $235.00 | $235.00 |
| 0030 | Joint adhesive (401-11526) | LFT | 4,295 | $0.65 | $5.50 | $5.50 |
| 0031 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 4,990 | $6.50 | $8.00 | $8.00 |
| 0032 | Asphalt for tack coat (406-05520) | TON | 7 | $2,000.00 | $990.00 | $990.00 |
| 0033 | Guardrail, reset (601-06035) | LFT | 137.50 | $36.00 | $60.00 | $40.00 |
| 0034 | Fence, relocate (603-03398) | LFT | 24 | $120.00 | $275.00 | $135.00 |
| 0035 | HMA for approaches, type B (610-07487) | TON | 17 | $738.00 | $335.00 | $240.00 |
| 0036 | HMA for approaches, type C (610-07488) | TON | 15 | $365.00 | $365.00 | $270.00 |
| 0037 | Riprap, class 1 (616-05688) | TON | 11 | $160.00 | $190.00 | $410.00 |
| 0038 | Riprap, uniform (616-06451) | TON | 37 | $190.00 | $150.00 | $325.00 |
| 0039 | Geotextile for riprap, type 2A (616-12248) | SYS | 109 | $15.00 | $5.00 | $10.00 |
| 0040 | Geotextile for riprap, type 2B (616-12249) | SYS | 82 | $23.50 | $5.00 | $20.00 |
| 0041 | Mobilization and demobilization for seeding (621-01004) | EACH | 7 | $550.00 | $550.00 | $105.00 |
| 0042 | Mulched seeding, type R (621-06559) | SYS | 196 | $20.29 | $40.00 | $25.00 |
| 0043 | Mulched seeding, type U (621-06560) | SYS | 29 | $51.09 | $50.00 | $130.00 |
| 0044 | Field office, type C (628-09403) | MOS | 6 | $3,200.00 | $4,000.00 | $4,000.00 |
| 0045 | Computer system equipment (628-11976) | EACH | 2 | $500.00 | $900.00 | $1,500.00 |
| 0046 | Headwall reconstruct (714-96273) | LS | 1 | $5,000.00 | $11,000 | $31,000 |
| 0047 | Pipe end section, min. area 6.5 SFT (715-04694) | EACH | 1 | $2,200.00 | $3,700.00 | $4,500.00 |
| 0048 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 61 | $252.00 | $600.00 | $555.00 |
| 0049 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 169 | $134.00 | $550.00 | $475.00 |
| 0050 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 55 | $161.00 | $450.00 | $495.00 |
| 0051 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 82 | $229.00 | $300.00 | $555.00 |
| 0052 | Pipe, type 3, circular, diameter 21 in. (715-05172) | LFT | 8 | $160.00 | $500.00 | $1,000.00 |
| 0053 | Pipe, type 1, deformed, min. area 6.5 SFT (715-05238) | LFT | 64 | $336.00 | $550.00 | $720.00 |
| 0054 | Pipe end section, diameter 15 in. (715-46005) | EACH | 3 | $801.00 | $2,000.00 | $2,500.00 |
| 0055 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $1,011.00 | $2,000.00 | $2,500.00 |
| 0056 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 4,200 | $1.50 | $1.50 | $2.00 |
| 0057 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 168 | $6.50 | $6.50 | $10.00 |
| 0058 | Construction sign, type A (801-06640) | EACH | 11 | $100.00 | $100.00 | $200.00 |
| 0059 | Construction sign, type B (801-06645) | EACH | 6 | $80.00 | $80.00 | $80.00 |
| 0060 | Maintaining traffic (801-06775) | LS | 1 | $250,000 | $139,483 | $261,831 |
| 0061 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $29,500 | $31,000 | $30,000 |
| 0062 | Barricade, type III-A (801-07118) | LFT | 24 | $20.00 | $20.00 | $15.00 |
| 0063 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 150 | $138.00 | $700.00 | $530.00 |
| 0064 | Portable signal (801-12081) | LS | 1 | $34,047 | $16,500 | $20,000 |
| 0065 | Line, remove (808-06716) | LFT | 3,640 | $1.00 | $1.00 | $1.00 |
| 0066 | Grooving for pavement markings (808-12032) | LFT | 5,196 | $1.30 | $1.30 | $1.00 |
| 0067 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 4,224 | $1.30 | $1.30 | $1.00 |
| 0068 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 777 | $1.30 | $1.30 | $1.00 |
| 0069 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 195 | $1.30 | $1.30 | $2.00 |
| 0070 | Additional , headwall procurement (105-06807) | LS | 1 | $174,007 | $7,500.00 | $61,000 |
| 0071 | Construction sign, type C (801-03290) | EACH | 2 | $175.00 | $175.00 | $245.00 |
| 0072 | Road closure sign assembly (801-04308) | EACH | 2 | $205.00 | $250.00 | $270.00 |
| 0073 | Detour route marker assembly (801-06625) | EACH | 22 | $145.00 | $145.00 | $145.00 |
| 0074 | Portable changeable message sign (801-11642) | EACH | 3 | $5,500.00 | $5,500.00 | $2,750.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 7, 2026. Compiled by Mirage Metrics.