KYTC contract 25-1128 bid tabulation

GRADE & DRAIN WITH ASPHALT SURFACE OUTER LOOP / FEGENBUSH LANE IMPROVEMENTS. Let by Kentucky Transportation Cabinet on December 11, 2025. 4 bids received; low bid $9,778,459 by Louisville Paving Company Inc, +6.8% against the engineer's estimate of $9,157,952.

Owner
Kentucky Transportation Cabinet
Letting
11 DEC 2025
Pay items
167
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Louisville Paving Company Inc$9,778,459Low+7.0%
2Mac Construction & Excavating Inc$10,050,000+3.0%+10%
3Flynn Brothers Contracting Inc$10,487,111+7.0%+15%
4Cleary Construction Inc$10,600,000+8.0%+16%
KYTC contract 25-1128: bids by rank

Engineer's estimate: $9,157,952.

Bid tabulation

LinePay itemUnitQuantity1. Louisville Paving Company Inc2. Mac Construction & Excavating Inc3. Flynn Brothers Contracting Inc4. Cleary Construction Inc
0010Crushed stone baseTON A A9,574$46.00$42.00$50.00$42.00
0020Leveling & wedging PG64-22TON A A500$90.52$112.00$91.63$86.30
0030CL3 asph base 1.00D PG64-22TON A A8,894$84.20$75.00$82.58$82.55
0040Asphalt material for tackTON A A19$0.01$0.01$550.00$621.00
0050Cem conc ent pavement-6 inSQYD A A137$80.41$80.41$96.50$80.41
0060Cem conc ent pavement-8 inSQYD A A447$105.73$105.73$125.00$105.73
0070CL3 asph surf 0.38A PG64-22TON A A2,845$90.52$93.00$90.29$90.30
0080Crushed aggregate size no 2TON A A15,250$40.00$36.00$43.00$39.00
0090Perforated pipe-4 inLF A A400$17.17$25.00$16.00$35.00
0100Cored hole drainage box con-4 inEACH A A50$0.01$85.00$225.00$772.31
0110Adjust manhole frame to gradeEACH A A4$1,546.83$800.00$1,175.00$1,643.26
0120Standard curb and gutterLF A A7,932$28.18$28.18$37.50$28.18
0130Standard header curbLF A A640$43.03$43.03$62.50$43.03
0140Standard barrier median type 4SQYD A A35$171.30$171.30$191.00$171.30
0150Standard barrier median type 5SQYD A A1,504$118.04$118.04$141.00$118.04
0160Barricade-type IIIEACH A A12$116.60$116.60$115.00$116.60
0170Temp ditchLF A A1,277$1.13$2.00$1.00$1.00
0180Clean temp ditchLF A A639$1.13$1.50$1.00$0.01
0190Roadway excavationCUYD A A19,156$42.00$35.00$70.00$56.00
0200WaterMGAL A A50$0.01$5.00$5.00$0.01
0210Right-of-way monument type 1EACH A A70$201.20$201.20$201.20$201.20
0220Clearing and grubbingLS A A1$100,000$600,000$75,000$125,000
0230Concrete-class BCUYD A A65$1,418.24$975.00$1,150.00$1,067.13
0240Temporary signsSQFT A A1,066$6.36$6.36$5.00$6.36
0250Edge keyLF A A253$69.17$16.80$16.70$16.70
0260Fabric-geotextile class 1SQYD A A26,500$1.22$2.00$1.16$2.50
0270Fabric-geotextile class 2 for pipeSQYD A A28,790$2.00$2.00$2.00$2.00
0280Fabric-geotextile class 4ASQYD A A37,500$2.27$3.00$2.34$4.00
0290Handrail-type A-1LF A A90$93.73$92.50$92.50$166.07
0300Maintain & control trafficLS A A1$562,000$636,076$180,000$420,000
0310Portable changeable message signEACH A A5$9,010.00$9,010.00$10,000$7,420.00
0320Mobilization for mill & textLS A A1$10,000$6,105.00$2,500.00$2,500.00
0330Asphalt pave milling & texturingTON A A647$18.25$12.00$20.83$20.80
0335SafeloadingCUYD A A42$215.41$540.00$175.00$500.00
0340Temp silt fenceLF A A2,102$2.11$2.11$2.11$3.00
0350Silt trap type AEACH A A2$892.31$150.00$150.00$320.00
0360Silt trap type BEACH A A9$456.01$150.00$150.00$165.00
0370Silt trap type CEACH A A75$188.56$165.00$165.00$275.00
0380Clean silt trap type AEACH A A2$123.46$30.00$35.00$1.00
0390Clean silt trap type BEACH A A9$123.46$35.00$35.00$1.00
0400Clean silt trap type CEACH A A75$21.82$35.00$20.00$1.00
0410Sidewalk-4 in concreteSQYD A A3,425$71.47$68.00$75.00$57.40
0420StakingLS A A1$100,000$150,000$55,000$188,000
0430Erosion control blanketSQYD A A1,537$2.36$2.36$2.36$2.36
0440Temp mulchSQYD A A27,564$0.25$0.25$0.25$0.25
0450Temp seeding and protectionSQYD A A20,694$0.32$0.32$0.32$0.32
0460Initial fertilizerTON A A1.30$964.00$964.00$964.00$964.00
0470Maintenance fertilizerTON A A2.10$964.00$964.00$964.00$964.00
0480Seeding and protectionSQYD A A37,196$0.47$0.47$0.47$0.47
0490SoddingSQYD A A4,257$5.95$5.95$5.95$5.95
0500Agricultural limestoneTON A A26$97.00$97.00$97.00$97.00
0510Pave striping-temp paint-6 inLF A A16,000$0.23$0.23$0.23$0.23
0520Pave striping-thermo-6 in WLF A A11,854$1.15$1.15$1.15$1.15
0530Pave striping-thermo-6 in YLF A A14,207$1.15$1.15$1.15$1.15
0540Pave striping-thermo-12 in YLF A A150$3.00$3.00$3.00$3.00
0550Pave striping-temp rem tape-WLF A A5,000$2.25$2.25$2.25$2.25
0560Pave striping-temp rem tape-YLF A A5,000$2.25$2.25$2.25$2.25
0570Pave marking-thermo X-walk-6 inLF A A1,308$3.50$3.50$3.50$3.50
0580Pave marking-thermo stop bar-24INLF A A356$12.95$12.95$12.95$12.95
0590Pave marking-thermo cross-hatchSQFT A A589$4.95$4.95$4.95$4.95
0600Pave marking-thermo curv arrowEACH A A63$115.00$115.00$115.00$115.00
0610Inlaid pavement marker-MWEACH A A24$32.00$32.00$32.00$32.00
0620Inlaid pavement marker-MYEACH A A83$32.00$32.00$32.00$32.00
0630Inlaid pavement marker-byEACH A A25$32.00$32.00$32.00$32.00
0640Fuel adjustmentDOLL A A20,714$1.00$1.00$1.00$1.00
0650Asphalt adjustmentDOLL A A65,707$1.00$1.00$1.00$1.00
0670Longitudinal edge keyLF A A3,390$10.29$3.73$4.66$6.95
0680Pave mark thermo cone cap-solid yellowSQFT A A163$5.95$5.95$5.95$5.95
0690Water blasting existing stripeLF A A15,000$0.01$0.79$0.79$0.79
0700Qwick curb median separatorLF A A168$126.02$126.00$126.02$126.02
0710Detectable warningsSQFT A A1,196$48.60$48.60$55.00$48.60
0720Turf reinforcement mat 1SQYD A A207$7.44$7.44$7.44$7.44
0730Pave mark thermo-lane reduction arrowEACH A A9$395.00$395.00$395.00$395.00
0735Pipeline inspectionLF A A6,737$2.35$3.00$2.35$2.35
0740Electronic delivery MGMT system - aggLS A A1$0.01$1,000.00$1.00$0.01
0750Entrance pipe-15 inLF A A146$102.74$82.00$100.00$95.00
0760Entrance pipe-24 inLF A A84$154.76$110.00$117.00$140.00
0770Storm sewer pipe-15 inLF A A2,580$87.21$124.00$80.00$115.00
0780Storm sewer pipe-18 inLF A A2,953$118.52$125.00$90.00$140.00
0790Storm sewer pipe-24 inLF A A447$167.79$185.00$121.00$190.00
0800Storm sewer pipe-30 inLF A A257$194.55$220.00$160.00$195.00
0810Storm sewer pipe-36 inLF A A40$250.00$350.00$290.00$300.00
0820Storm sewer pipe-48 inLF A A60$333.33$360.00$350.00$240.00
0830Storm sewer pipe-24 in equivLF A A117$170.94$120.00$160.00$130.00
0840Storm sewer pipe-48 in equivLF A A53$471.70$420.00$400.00$285.00
0850Pipe culvert headwall-15 inEACH A A3$2,500.00$1,240.00$2,500.00$3,000.00
0860Pipe culvert headwall-18 inEACH A A2$3,750.00$1,410.00$2,500.00$3,250.00
0870Pipe culvert headwall-24 inEACH A A3$3,333.33$2,025.00$3,250.00$3,500.00
0880Pipe culvert headwall-24 in equivEACH A A1$5,000.00$3,410.00$3,250.00$3,500.00
0890Pipe culvert headwall-36 inEACH A A1$5,000.00$4,920.00$4,700.00$4,000.00
0900Pipe culvert headwall-48 inEACH A A1$7,500.00$5,700.00$6,500.00$4,250.00
0910Pipe culvert headwall-48 in equivEACH A A1$7,500.00$8,400.00$6,500.00$4,250.00
0920Sloped box outlet type 1-15 inEACH A A2$2,500.00$2,650.00$4,250.00$3,850.00
0930Curb box inlet type AEACH A A40$5,808.92$6,800.00$7,750.00$8,750.00
0940Curb box inlet type FEACH A A7$2,815.90$2,950.00$3,850.00$7,750.00
0950Drop box inlet type 3EACH A A2$9,272.30$6,400.00$11,000$9,000.00
0960Drop box inlet type 11EACH A A10$2,827.74$3,400.00$3,350.00$4,250.00
0970Drop box inlet type 13GEACH A A15$2,799.12$4,330.00$3,500.00$5,000.00
0980Junction box-30 inEACH A A1$3,573.63$3,800.00$4,000.00$15,000
0990Junction boxEACH A A2$13,685$16,000$20,000$9,000.00
1000Channel lining class IITON A A9$136.78$155.00$100.00$120.00
1010Channel lining class IIITON A A76$133.04$160.00$120.00$130.00
1020Concrete-class ACUYD A A8.34$537.05$945.00$810.00$500.00
1030Pole baseEACH A A2$3,943.46$1,750.00$1,750.00$1,750.00
1040SBM alum sheet signs .080 inSQFT A A407$50.75$40.00$50.75$50.75
1050Steel post type 1LF A A659$33.31$35.00$33.31$33.31
1060Steel post mile markersEACH A A2$326.36$35.00$326.36$326.36
1070Remove & relocate signsEACH A A1$679.62$350.00$679.62$679.62
1080Remove signEACH A A8$205.71$100.00$205.71$205.71
1090GMSS type DEACH A A3$527.51$350.00$527.50$527.51
1100Install luminaire poleEACH A A2$1,520.00$2,200.00$2,200.00$2,200.00
1110Install-beacon controller-2 circuitEACH A A2$1,511.14$3,000.00$3,000.00$3,000.00
1120Barcode sign inventoryEACH A A87$51.43$40.00$51.43$51.43
1130Remove signal equipmentEACH A A2$1,645.67$4,000.00$4,000.00$4,000.00
1140Trenching and backfillingLF A A240$6.00$6.00$6.00$6.00
1150Cable-no. 14/5CLF A A3,690$3.00$3.00$3.00$3.00
1160Cable-no. 14/7CLF A A2,825$3.00$3.00$3.00$3.00
1170Messenger-15400 LBLF A A1,055$8.00$8.00$8.00$8.00
1180Install steel strain poleEACH A A8$7,500.00$7,500.00$7,500.00$7,500.00
1190Temp relocation of signal headEACH A A12$150.00$150.00$150.00$150.00
1200Install span mounted signEACH A A2$225.00$225.00$225.00$225.00
1210Install pedestrian head-LEDEACH A A12$300.00$300.00$300.00$300.00
1220Install LED signal-3 sectionEACH A A17$350.00$350.00$350.00$350.00
1230Install LED signal-5 sectionEACH A A1$425.00$425.00$425.00$425.00
1240Install LED signal- 4 sectionEACH A A3$425.00$425.00$425.00$425.00
1250Install coordinating unitEACH A A2$1,500.00$1,500.00$1,500.00$1,500.00
1260Install pedestrian detectorEACH A A12$125.00$125.00$125.00$125.00
1270Traffic signal pole baseCUYD A A36$350.00$350.00$350.00$350.00
1280Install signal pedestalEACH A A1$1,750.00$1,750.00$1,750.00$1,750.00
1290Install pedestal postEACH A A8$375.00$375.00$375.00$375.00
1300Tether wireLF A A1,055$8.00$8.00$8.00$8.00
1310PVC conduit-1 1/4 in-schedule 80LF A A140$6.00$6.00$6.00$6.00
1320PVC conduit-2 in-schedule 80LF A A180$8.50$8.50$8.50$8.50
1330Install signal controller-TY atcEACH A A2$14,200$14,200$14,200$14,200
1340Remove signal equipmentEACH A A2$8,500.00$8,500.00$8,500.00$8,500.00
1350Install radar presence detector type AEACH A A7$1,200.00$1,200.00$1,200.00$1,200.00
1360Plug pipeEACH A A13$643.50$2,745.00$750.00$1,850.00
1370SafeloadingCUYD A A423$297.00$140.00$175.00$275.00
1380W encasement steel bored range 5LF A A230$821.41$925.00$1,142.66$1,020.00
1390W fire hydrant assemblyEACH A A6$9,702.00$8,300.00$9,386.24$10,000
1400W fire hydrant removeEACH A A6$2,079.00$700.00$1,189.56$1,250.00
1410W meter relocateEACH A A27$673.20$2,400.00$3,109.37$1,100.00
1420W meter/fire service combo vaultEACH A A7$45,540$8,000.00$36,137$20,000
1430W pipe ductile iron 04 inchLF A A95$242.55$248.00$142.17$315.00
1440W pipe ductile iron 06 inchLF A A290$158.40$188.00$160.43$345.00
1450W pipe ductile iron 08 inchLF A A95$249.48$268.00$211.78$465.00
1460W pipe ductile iron 12 inchLF A A4,045$170.28$200.00$233.74$225.00
1470W pipe ductile iron 24 inchLF A A635$770.28$650.00$856.35$785.00
1480W tapping sleeve and valve size 2EACH A A1$25,915$50,000$35,969$50,000
1490W tie-in 06 inchEACH A A3$7,771.50$5,000.00$4,130.65$5,500.00
1500W tie-in 08 inchEACH A A1$8,217.00$6,700.00$4,963.99$6,000.00
1510W tie-in 12 inchEACH A A5$9,405.00$6,010.00$7,771.90$6,750.00
1520W tie-in 24 inchEACH A A2$71,662$50,000$29,865$40,000
1530W valve 04 inchEACH A A1$1,881.00$2,200.00$2,370.37$2,250.00
1540W valve 06 inchEACH A A5$2,128.50$2,210.00$2,660.17$2,500.00
1550W valve 08 inchEACH A A1$2,970.00$3,030.00$3,567.67$3,500.00
1560W valve 12 inchEACH A A9$4,752.00$7,000.00$6,095.40$6,500.00
1570W valve 24 inchEACH A A1$53,460$60,000$45,342$60,000
1580W serv copper long side 1 inEACH A A3$7,326.00$5,450.00$23,596$15,000
1590W serv copper long side 2 inEACH A A1$17,622$8,400.00$28,043$18,000
1600W serv copper long side 3/4 inEACH A A1$3,960.00$4,200.00$20,616$12,000
1610W serv copper short side 1 inEACH A A2$3,267.00$3,600.00$5,754.03$2,750.00
1620W serv copper short side 3/4 inEACH A A9$2,673.00$1,660.00$5,708.40$2,250.00
1630W serv copper short side 5/8 inEACH A A12$2,475.00$1,620.00$4,788.71$2,100.00
1640W serv copper long side 5/8 inEACH A A3$10,395$3,640.00$19,528$10,000
1650MobilizationLS A A1$430,000$450,000$475,000$492,000
1660DemobilizationLS A A1$140,000$160,000$155,000$150,750
KYTC contract 25-1128: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy