KYTC contract 25-1303 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE KY 2154. Let by Kentucky Transportation Cabinet on February 20, 2025, Marion, District 4. 3 bids received; low bid $2,871,680 by Rame Contracting LLC, +2.4% against the engineer's estimate of $2,805,184.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 FEB 2025
- Pay items
- 118
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rame Contracting LLC | $2,871,680 | Low | +2.0% |
| 2 | Cleary Construction Inc | $3,142,000 | +9.0% | +12% |
| 3 | Bluegrass Contracting Corporation | $3,399,910 | +18% | +21% |
Engineer's estimate: $2,805,184.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rame Contracting LLC | 2. Cleary Construction Inc | 3. Bluegrass Contracting Corporation |
|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A | 1,023 | $60.00 | $65.00 | $47.50 |
| 0020 | Traffic bound base | TON A | 200 | $50.00 | $52.00 | $55.00 |
| 0030 | Asphalt seal aggregate | TON A | 17 | $185.00 | $185.00 | $360.00 |
| 0040 | Asphalt seal coat | TON A | 2.01 | $2,425.00 | $2,425.00 | $1,600.00 |
| 0050 | Leveling & wedging PG76-22 | TON A | 781 | $143.00 | $143.00 | $161.50 |
| 0060 | CL2 asph base 1.00D PG64-22 | TON A | 189 | $133.00 | $133.00 | $150.25 |
| 0070 | CL3 asph base 1.00D PG64-22 | TON A | 535 | $133.00 | $133.00 | $150.25 |
| 0080 | CL3 asph base 1.00D PG76-22 | TON A | 134 | $152.50 | $152.50 | $172.25 |
| 0090 | CL2 asph surf 0.38D PG64-22 | TON A | 283 | $136.50 | $136.50 | $154.25 |
| 0100 | CL3 asph surf 0.38B PG76-22 | TON A | 895 | $140.50 | $140.50 | $158.75 |
| 0110 | JPC pavement-8 in | SQYD A | 858 | $115.94 | $113.61 | $195.00 |
| 0120 | Mobilization for mill & text | LS A | 1 | $3,000.00 | $3,000.00 | $6,750.00 |
| 0130 | Mobilization for mill & text | LS A | 1 | $3,000.00 | $3,000.00 | $6,750.00 |
| 0140 | Asphalt pave milling & texturing | TON A | 869 | $42.50 | $30.00 | $26.00 |
| 0150 | Asphalt material for tack non-tracking | TON A | 7.20 | $700.00 | $700.00 | $800.00 |
| 0160 | Crushed aggregate size no 2 | TON A | 1,410 | $47.00 | $62.00 | $52.00 |
| 0170 | Flume inlet type 2 | EACH A | 14 | $4,811.90 | $4,669.04 | $7,650.00 |
| 0180 | Adjust manhole | EACH A | 1 | $3,000.00 | $1,500.00 | $975.00 |
| 0190 | Standard curb and gutter | LF A | 3,749 | $37.82 | $37.82 | $49.00 |
| 0200 | Standard curb and gutter mod | LF A | 309 | $30.92 | $30.92 | $49.00 |
| 0210 | Lip curb and gutter | LF A | 1,195 | $37.23 | $37.23 | $45.00 |
| 0220 | Standard header curb | LF A | 340 | $26.22 | $26.22 | $60.00 |
| 0230 | Delineator for guardrail BI directional white | EACH A | 46 | $15.00 | $15.00 | $17.00 |
| 0240 | Barricade-type III | EACH A | 16 | $125.84 | $100.00 | $225.00 |
| 0250 | Remove pavement | SQYD A | 2,081 | $6.25 | $16.00 | $19.50 |
| 0260 | Temp ditch | LF A | 2,427 | $0.10 | $1.00 | $3.50 |
| 0270 | Clean temp ditch | LF A | 1,213 | $0.05 | $0.01 | $2.00 |
| 0280 | Embankment in place | CUYD A | 4,631 | $36.50 | $50.00 | $39.50 |
| 0290 | Water | MGAL A | 107.30 | $0.10 | $0.01 | $15.00 |
| 0300 | Guardrail-steel W beam-S face | LF A | 4,544 | $26.50 | $26.50 | $30.00 |
| 0310 | Guardrail terminal section no 1 | EACH A | 4 | $110.00 | $110.00 | $125.00 |
| 0320 | Guardrail end treatment type 1 | EACH A | 1 | $4,000.00 | $4,000.00 | $4,500.00 |
| 0330 | Guardrail end treatment type 2A | EACH A | 5 | $1,200.00 | $1,200.00 | $1,350.00 |
| 0340 | Remove guardrail | LF A | 5,864 | $4.00 | $4.00 | $4.50 |
| 0350 | Guardrail end treatment type 4A | EACH A | 2 | $4,000.00 | $4,000.00 | $4,500.00 |
| 0360 | Remove guardrail end treatment | EACH A | 2 | $850.00 | $850.00 | $975.00 |
| 0370 | Channel lining class II | TON A | 311 | $85.00 | $80.00 | $70.00 |
| 0380 | Clearing and grubbing | LS A | 1 | $5,000.00 | $65,000 | $52,500 |
| 0390 | Concrete-class B | CUYD A | 74.69 | $890.55 | $890.55 | $410.00 |
| 0400 | Temporary signs | SQFT A | 500 | $5.10 | $4.00 | $14.50 |
| 0410 | Edge key | LF A | 298 | $53.61 | $90.00 | $101.00 |
| 0420 | Fabric-geotextile class 1 | SQYD A | 6,574 | $3.00 | $3.50 | $2.25 |
| 0430 | Fabric-geotextile class 2 for pipe | SQYD A | 271 | $2.00 | $2.00 | $2.00 |
| 0440 | Maintain & control traffic | LS A | 1 | $275,500 | $282,000 | $122,000 |
| 0450 | Portable changeable message sign | EACH A | 8 | $2,000.00 | $3,180.00 | $5,175.00 |
| 0460 | Edgeline rumble strips | LF A | 6,517 | $0.50 | $0.50 | $0.60 |
| 0470 | Temp silt fence | LF A | 2,427 | $3.00 | $4.05 | $3.90 |
| 0480 | Silt trap type A | EACH A | 9 | $250.00 | $410.14 | $330.00 |
| 0490 | Silt trap type B | EACH A | 9 | $250.00 | $207.77 | $330.00 |
| 0500 | Silt trap type C | EACH A | 9 | $250.00 | $354.94 | $330.00 |
| 0510 | Clean silt trap type A | EACH A | 9 | $10.00 | $184.08 | $100.00 |
| 0520 | Clean silt trap type B | EACH A | 9 | $10.00 | $120.12 | $100.00 |
| 0530 | Clean silt trap type C | EACH A | 9 | $10.00 | $124.90 | $100.00 |
| 0540 | Sidewalk-4 in concrete | SQYD A | 961 | $82.72 | $82.72 | $132.00 |
| 0550 | Staking | LS A | 1 | $47,900 | $110,000 | $75,000 |
| 0560 | Remove pole base | EACH A | 4 | $1,300.00 | $650.00 | $1,100.00 |
| 0570 | Erosion control blanket | SQYD A | 100 | $2.75 | $2.75 | $3.00 |
| 0580 | Temp mulch | SQYD A | 27,856 | $0.32 | $0.32 | $0.40 |
| 0590 | Temp seeding and protection | SQYD A | 20,787 | $0.34 | $0.34 | $0.40 |
| 0600 | Initial fertilizer | TON A | 1.40 | $1,500.00 | $1,500.00 | $1,700.00 |
| 0610 | Maintenance fertilizer | TON A | 2.10 | $1,500.00 | $1,500.00 | $1,700.00 |
| 0620 | Seeding and protection | SQYD A | 41,576 | $0.60 | $0.60 | $0.70 |
| 0630 | Sodding | SQYD A | 488 | $18.00 | $18.00 | $20.00 |
| 0640 | Agricultural limestone | TON A | 25.80 | $85.00 | $85.00 | $95.00 |
| 0650 | Topsoil furnished and placed | CUYD A | 861 | $72.95 | $70.00 | $66.50 |
| 0660 | Pave striping-temp paint-6 in | LF A | 40,574 | $0.26 | $0.26 | $0.30 |
| 0670 | Pave striping-thermo-6 in W | LF A | 12,270 | $1.25 | $1.25 | $1.40 |
| 0680 | Pave striping-thermo-6 in Y | LF A | 8,017 | $1.25 | $1.25 | $1.40 |
| 0690 | Pave marking-thermo cross-hatch | SQFT A | 970 | $8.00 | $8.00 | $9.00 |
| 0700 | Pave marking-paint cross-hatch | SQFT A | 1,940 | $4.00 | $4.00 | $4.50 |
| 0710 | Pave marking-thermo curv arrow | EACH A | 1 | $150.00 | $150.00 | $170.00 |
| 0720 | Joint adhesive | LF A | 21,257 | $0.42 | $0.42 | $0.50 |
| 0730 | Pave mark temp paint stop bar | LF A | 240 | $9.00 | $9.00 | $10.00 |
| 0740 | Pave mark temp paint line arrow | EACH A | 2 | $85.00 | $85.00 | $95.00 |
| 0750 | Object marker TY 3 | EACH A | 1 | $95.00 | $95.00 | $110.00 |
| 0760 | Electrical junction box type C | EACH A | 4 | $3,500.00 | $3,500.00 | $4,600.00 |
| 0770 | Centerline rumble strips | LF A | 4,362 | $0.85 | $0.85 | $0.95 |
| 0780 | Sawcut pavement | LF A | 2,533 | $4.00 | $2.00 | $3.00 |
| 0790 | Longitudinal edge key | LF A | 2,193 | $8.00 | $8.00 | $9.00 |
| 0800 | Relocate signal head | EACH A | 8 | $250.00 | $250.00 | $1,715.00 |
| 0810 | Pave marking-thermo yield bar-36 in | LF A | 120 | $30.00 | $30.00 | $34.00 |
| 0820 | Turf reinforcement mat 1 | SQYD A | 156 | $12.50 | $12.50 | $14.00 |
| 0830 | Conduit under roadway | LF A | 288 | $29.95 | $29.95 | $40.00 |
| 0840 | Island curb and gutter(modified) | LF A | 566 | $38.35 | $38.35 | $45.00 |
| 0850 | Pipeline inspection | LF A | 390 | $6.41 | $6.41 | $7.25 |
| 0860 | Remove signal equipment | EACH A | 1 | $14,530 | $14,530 | $32,400 |
| 0870 | Crushed aggregate size no 2 | TON A | 6 | $125.00 | $320.00 | $56.00 |
| 0880 | Culvert pipe-36 in | LF A | 15 | $478.00 | $375.00 | $320.00 |
| 0890 | Storm sewer pipe-18 in | LF A | 390 | $215.00 | $140.00 | $197.00 |
| 0900 | Perforated pipe-4 in | LF A | 1,645 | $11.00 | $35.00 | $23.50 |
| 0910 | Non-perforated pipe-4 in | LF A | 50 | $11.00 | $36.00 | $25.00 |
| 0920 | Perf pipe headwall TY 1-4 in | EACH A | 2 | $1,425.00 | $1,800.00 | $1,250.00 |
| 0930 | Perf pipe headwall TY 3-4 in | EACH A | 4 | $1,425.00 | $1,900.00 | $1,350.00 |
| 0940 | Pipe culvert headwall-18 in | EACH A | 4 | $2,750.00 | $2,500.00 | $2,500.00 |
| 0950 | Pipe culvert headwall-36 in | EACH A | 1 | $4,200.00 | $4,250.00 | $3,300.00 |
| 0960 | Remove pipe | LF A | 4 | $145.00 | $155.00 | $55.00 |
| 0970 | Drop box inlet type 13G | EACH A | 6 | $6,600.00 | $6,250.00 | $5,100.00 |
| 0980 | Drop box inlet type 13S | EACH A | 3 | $9,400.00 | $8,500.00 | $8,150.00 |
| 0990 | Cored hole drainage box con-4 in | EACH A | 2 | $725.00 | $1,200.00 | $575.00 |
| 1000 | Remove headwall | EACH A | 1 | $235.00 | $675.00 | $450.00 |
| 1010 | Pole 40 FT MTG HT | EACH A | 23 | $2,750.00 | $2,750.00 | $3,350.00 |
| 1020 | Bracket 8 FT | EACH A | 16 | $600.00 | $600.00 | $780.00 |
| 1030 | Bracket 10 FT | EACH A | 7 | $850.00 | $850.00 | $1,030.00 |
| 1040 | Pole base | EACH A | 23 | $2,250.00 | $2,250.00 | $3,535.00 |
| 1050 | Transformer base | EACH A | 23 | $1,000.00 | $1,000.00 | $2,050.00 |
| 1060 | Lighting control equipment | EACH A | 2 | $14,700 | $14,700 | $40,750 |
| 1070 | Fused connector kit | EACH A | 46 | $150.00 | $150.00 | $325.00 |
| 1080 | Trenching and backfilling | LF A | 3,080 | $10.26 | $10.26 | $7.25 |
| 1090 | Wire-no. 12 | LF A | 3,805 | $0.19 | $0.19 | $1.85 |
| 1100 | Pole 45 FT wooden | EACH A | 2 | $2,500.00 | $2,500.00 | $4,500.00 |
| 1110 | Electrical junction box type A | EACH A | 6 | $3,000.00 | $3,000.00 | $2,500.00 |
| 1120 | Bore and jack conduit | LF A | 660 | $18.65 | $18.65 | $64.00 |
| 1130 | Wire-no. 10 | LF A | 14,100 | $1.67 | $1.67 | $2.00 |
| 1140 | LED luminaire | EACH A | 23 | $1,500.00 | $1,500.00 | $850.00 |
| 1150 | PVC conduit-1 1/4 in-schedule 80 | LF A | 2,805 | $1.14 | $1.14 | $8.75 |
| 1160 | PVC conduit-2 in-schedule 80 | LF A | 940 | $1.76 | $1.76 | $12.00 |
| 1170 | Mobilization | LS A | 1 | $134,675 | $146,000 | $159,000 |
| 1180 | Demobilization | LS A | 1 | $40,450 | $47,179 | $47,978 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of February 20, 2025. Compiled by Mirage Metrics.