KYTC contract 25-1305 bid tabulation
GRADE, DRAIN & SURFACE WITH BRIDGE 7TH STREET (KY 1099). Let by Kentucky Transportation Cabinet on April 24, 2025, Fulton, District 1. 2 bids received; low bid $2,590,017 by Harper Construction LLC, -11% against the engineer's estimate of $2,919,061.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 APR 2025
- Pay items
- 114
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Harper Construction LLC | $2,590,017 | Low | -11% |
| 2 | Hal Coffey Contracting LLC | $3,098,195 | +20% | +6.0% |
Engineer's estimate: $2,919,061.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Harper Construction LLC | 2. Hal Coffey Contracting LLC |
|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A | 705 | $65.00 | $39.00 |
| 0020 | Traffic bound base | TON A | 200 | $40.00 | $45.00 |
| 0030 | Crushed aggregate size no 2 | TON A | 210 | $60.00 | $45.00 |
| 0040 | Leveling & wedging PG64-22 | TON A | 299 | $140.00 | $130.00 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A | 658 | $130.00 | $125.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A | 350 | $140.00 | $130.00 |
| 0070 | Cem conc ent pavement-8 in | SQYD A | 326 | $104.00 | $125.00 |
| 0080 | Fabric-geotextile class 1 | SQYD A | 900 | $2.50 | $3.50 |
| 0090 | Remove structure | LS A | 1 | $24,000 | $45,000 |
| 0100 | Joint adhesive | LF A | 1,093 | $4.00 | $4.00 |
| 0110 | Asphalt material for tack non-tracking | TON A | 3.10 | $850.00 | $700.00 |
| 0120 | Standard curb and gutter mod | LF A | 345 | $48.00 | $65.00 |
| 0130 | Barricade-type III | EACH A | 6 | $325.00 | $300.00 |
| 0140 | Remove pavement | SQYD A | 152 | $7.00 | $25.00 |
| 0150 | Temp ditch | LF A | 551 | $0.50 | $0.10 |
| 0160 | Clean temp ditch | LF A | 276 | $0.25 | $0.10 |
| 0170 | Embankment in place | CUYD A | 1,685 | $50.00 | $65.00 |
| 0180 | Water | MGAL A | 5 | $500.00 | $1.00 |
| 0190 | Fence-4 FT chain link | LF A | 84 | $31.25 | $31.25 |
| 0200 | Guardrail terminal section no 1 | EACH A | 4 | $84.99 | $84.99 |
| 0210 | Temp guardrail | LF A | 287.50 | $36.00 | $36.00 |
| 0220 | Right-of-way monument type 1 | EACH A | 14 | $300.00 | $195.00 |
| 0230 | Witness post | EACH A | 3 | $195.00 | $195.00 |
| 0240 | Channel lining class II | TON A | 634 | $55.00 | $58.00 |
| 0250 | Channel lining class III | TON A | 495 | $55.00 | $58.00 |
| 0260 | Clearing and grubbing | LS A | 1 | $25,000 | $55,000 |
| 0270 | Concrete-class B | CUYD A | 1.50 | $275.00 | $650.00 |
| 0280 | Temporary signs | SQFT A | 234 | $15.00 | $12.00 |
| 0290 | Edge key | LF A | 100 | $75.00 | $45.00 |
| 0300 | Fabric-geotextile class 2 for pipe | SQYD A | 1,379 | $2.00 | $2.00 |
| 0310 | Handrail-type A-1 | LF A | 101 | $225.00 | $245.00 |
| 0320 | Maintain & control traffic | LS A | 1 | $155,000 | $72,000 |
| 0330 | Diversions (by-pass detours) | LS A | 1 | $20,000 | $55,000 |
| 0340 | Safeloading | CUYD A | 5.60 | $450.00 | $325.00 |
| 0350 | Edgeline rumble strips | LF A | 1,460 | $3.25 | $3.25 |
| 0360 | Temp silt fence | LF A | 551 | $2.00 | $2.00 |
| 0370 | Silt trap type A | EACH A | 3 | $200.00 | $250.00 |
| 0380 | Silt trap type B | EACH A | 3 | $200.00 | $250.00 |
| 0390 | Silt trap type C | EACH A | 3 | $200.00 | $250.00 |
| 0400 | Clean silt trap type A | EACH A | 3 | $75.00 | $50.00 |
| 0410 | Clean silt trap type B | EACH A | 3 | $75.00 | $50.00 |
| 0420 | Clean silt trap type C | EACH A | 3 | $75.00 | $50.00 |
| 0430 | Sidewalk-4 in concrete | SQYD A | 233 | $80.00 | $105.00 |
| 0440 | Staking | LS A | 1 | $40,000 | $35,000 |
| 0450 | Remove structure | LS A | 1 | $22,000 | $45,000 |
| 0460 | Temp signal multi phase | EACH A | 3 | $10,500 | $20,000 |
| 0470 | Erosion control blanket | SQYD A | 458 | $4.00 | $4.00 |
| 0480 | Temp mulch | SQYD A | 8,115 | $0.40 | $0.40 |
| 0490 | Temp seeding and protection | SQYD A | 6,148 | $0.57 | $0.57 |
| 0500 | Initial fertilizer | TON A | 0.40 | $1,200.00 | $1,200.00 |
| 0510 | Maintenance fertilizer | TON A | 0.20 | $1,200.00 | $1,200.00 |
| 0520 | Seeding and protection | SQYD A | 6,459 | $0.76 | $0.76 |
| 0530 | Agricultural limestone | TON A | 4 | $900.00 | $900.00 |
| 0540 | SBM alum sheet signs .080 in | SQFT A | 97 | $56.30 | $56.30 |
| 0550 | SBM alum sheet signs .125 in | SQFT A | 31 | $65.46 | $65.46 |
| 0560 | Steel post type 2 | LF A | 152 | $32.47 | $32.47 |
| 0570 | Pave striping-temp paint-4 in | LF A | 5,500 | $0.25 | $0.25 |
| 0580 | Pave striping-perm paint-4 in | LF A | 3,856 | $0.50 | $0.50 |
| 0590 | Pave marking-thermo stop bar-24IN | LF A | 104 | $20.00 | $20.00 |
| 0600 | Sawcut pavement | LF A | 98 | $19.00 | $25.00 |
| 0610 | Longitudinal edge key | LF A | 1,980 | $5.00 | $10.00 |
| 0620 | Pave mark temp paint stop bar-24 in | LF A | 33 | $5.00 | $5.00 |
| 0630 | Detectable warnings | SQFT A | 30 | $55.00 | $55.00 |
| 0640 | Turf reinforcement mat 1 | SQYD A | 187 | $7.50 | $7.50 |
| 0650 | Barcode sign inventory | EACH A | 31 | $55.27 | $55.27 |
| 0660 | Pipeline inspection | LF A | 538 | $13.00 | $2.84 |
| 0670 | Entrance pipe-15 in | LF A | 89 | $37.00 | $70.00 |
| 0680 | Entrance pipe-18 in | LF A | 161 | $40.00 | $75.00 |
| 0690 | Entrance pipe-30 in equiv | LF A | 29 | $77.00 | $135.00 |
| 0700 | Culvert pipe-15 in | LF A | 18 | $68.00 | $90.00 |
| 0710 | Storm sewer pipe-15 in | LF A | 137 | $58.00 | $85.00 |
| 0720 | Storm sewer pipe-24 in | LF A | 232 | $93.00 | $100.00 |
| 0730 | Storm sewer pipe-30 in | LF A | 120 | $125.00 | $155.00 |
| 0740 | Storm sewer pipe-36 in | LF A | 233 | $157.00 | $200.00 |
| 0750 | Pipe culvert headwall-30 in | EACH A | 1 | $5,000.00 | $5,500.00 |
| 0760 | Curb box inlet type A | EACH A | 1 | $7,800.00 | $10,200 |
| 0770 | Drop box inlet type 1 | EACH A | 2 | $4,600.00 | $6,800.00 |
| 0780 | Drop box inlet type 2 | EACH A | 4 | $5,400.00 | $7,500.00 |
| 0790 | Drop box inlet type 14 | EACH A | 2 | $4,000.00 | $6,500.00 |
| 0800 | Drop box inlet TY 13S(mod) | EACH A | 1 | $8,300.00 | $10,200 |
| 0810 | Drainage junction box TY B | EACH A | 1 | $3,500.00 | $6,500.00 |
| 0830 | Foundation preparation | LS A | 1 | $74,000 | $180,000 |
| 0840 | Concrete-class A | CUYD A | 790.80 | $765.00 | $890.00 |
| 0850 | Steel reinforcement | LB A | 114,387 | $1.45 | $1.95 |
| 0860 | Low flow diversion curb | LS A | 1 | $21,000 | $15,000 |
| 0870 | Remove pipe | LF A | 175 | $42.00 | $48.51 |
| 0880 | G pipe polyethylene/plastic 04 inch | LF A | 695 | $48.00 | $55.44 |
| 0890 | G tie-in special | EACH A | 6 | $3,500.00 | $4,042.50 |
| 0900 | G cap existing main | EACH A | 12 | $2,400.00 | $2,772.00 |
| 0910 | Remove pipe | LF A | 327 | $70.00 | $80.85 |
| 0920 | Plug pipe | EACH A | 5 | $5,100.00 | $5,890.50 |
| 0930 | Adjust manhole frame to grade | EACH A | 1 | $1,650.00 | $1,905.75 |
| 0940 | Channel lining class II | TON A | 9 | $75.00 | $58.00 |
| 0950 | Channel lining class III | TON A | 12 | $80.00 | $58.00 |
| 0960 | Concrete-class A | CUYD A | 4 | $500.00 | $577.50 |
| 0970 | S bypass pumping | EACH A | 1 | $10,000 | $11,550 |
| 0980 | S force main PVC 02 inch | LF A | 257 | $45.00 | $51.98 |
| 0990 | S force main PVC 08 inch | LF A | 144 | $126.00 | $145.53 |
| 1000 | S manhole | EACH A | 3 | $14,600 | $16,863 |
| 1010 | S manhole abandon/remove | EACH A | 2 | $6,500.00 | $7,507.50 |
| 1020 | S manhole with drop | EACH A | 1 | $16,100 | $18,596 |
| 1030 | S pipe ductile iron 08 inch | LF A | 234 | $238.00 | $274.89 |
| 1040 | S pipe PVC 08 inch | LF A | 109 | $158.00 | $182.49 |
| 1050 | Cored hole conn to exist manhole | EACH A | 1 | $2,500.00 | $2,887.50 |
| 1060 | Pipeline inspection | LF A | 343 | $13.00 | $28.88 |
| 1070 | Remove pipe | LF A | 410 | $55.00 | $63.53 |
| 1080 | W cap existing main | EACH A | 5 | $5,200.00 | $6,006.00 |
| 1090 | W fire hydrant assembly | EACH A | 1 | $13,800 | $15,939 |
| 1100 | W meter adjust | EACH A | 1 | $3,600.00 | $4,158.00 |
| 1110 | W tie-in 06 inch | EACH A | 6 | $8,600.00 | $9,933.00 |
| 1120 | W valve box adjust | EACH A | 4 | $1,800.00 | $2,079.00 |
| 1130 | W pipe PVC 06 inch inst | LF A | 652 | $70.00 | $80.85 |
| 1140 | Mobilization | LS A | 1 | $106,600 | $145,000 |
| 1150 | Demobilization | LS A | 1 | $36,800 | $44,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.