GRADE & DRAIN WITH ASPHALT SURFACE TURN LANES AT AA HIGHWAY (KY 9) & KY 709 INTERSECTION. Let by Kentucky Transportation Cabinet on June 5, 2025. 3 bids received; low bid $449,180 by Riegler Blacktop Inc, -2.6% against the engineer's estimate of $461,395.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 05 JUN 2025
- Pay items
- 54
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Riegler Blacktop Inc | $449,180 | Low | -3.0% |
| 2 | Eaton Asphalt Paving Co Inc | $454,854 | +1.0% | -1.0% |
| 3 | Bluegrass Contracting Corporation | $539,885 | +20% | +17% |
Engineer's estimate: $461,395.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Riegler Blacktop Inc | 2. Eaton Asphalt Paving Co Inc | 3. Bluegrass Contracting Corporation |
|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 1,146 | $48.00 | $54.00 | $51.00 |
| 0020 | Geogrid reinforcement for subgrade | SQYD A A | 1,661 | $5.00 | $3.00 | $3.00 |
| 0030 | Asphalt seal aggregate | TON A A | 1.80 | $500.00 | $1,600.00 | $1,600.00 |
| 0040 | Asphalt seal coat | TON A A | 0.20 | $5,000.00 | $9,965.00 | $10,400 |
| 0050 | CL4 asph base 1.00D PG64-22 | TON A A | 204 | $106.00 | $142.00 | $154.00 |
| 0060 | CL4 asph base 1.00D PG76-22 | TON A A | 209 | $120.00 | $150.00 | $162.00 |
| 0070 | CL4 asph surf 0.38A PG76-22 | TON A A | 78 | $260.00 | $225.00 | $260.00 |
| 0080 | Asphalt material for tack | TON A A | 0.80 | $1.00 | $1.00 | $25.00 |
| 0090 | JPC pavement-11 in | SQYD A A | 677 | $125.00 | $136.00 | $130.00 |
| 0100 | Fabric-geotextile class 1 | SQYD A A | 1,661 | $2.00 | $2.25 | $2.00 |
| 0110 | Barricade-type III | EACH A A | 3 | $216.68 | $175.00 | $215.00 |
| 0120 | Roadway excavation | CUYD A A | 919 | $42.00 | $44.25 | $50.00 |
| 0130 | Guardrail-steel W beam-S face | LF A A | 12.50 | $100.00 | $100.00 | $114.00 |
| 0140 | Guardrail end treatment type 1 | EACH A A | 1 | $4,500.00 | $4,500.00 | $5,100.00 |
| 0150 | Remove guardrail | LF A A | 200 | $3.00 | $3.00 | $3.50 |
| 0160 | Temporary signs | SQFT A A | 185 | $6.13 | $5.00 | $12.00 |
| 0170 | Edge key | LF A A | 16 | $25.00 | $48.69 | $50.00 |
| 0180 | Maintain & control traffic | LS A A | 1 | $33,000 | $4,425.00 | $55,000 |
| 0190 | Portable changeable message sign | EACH A A | 4 | $800.00 | $1,200.00 | $2,550.00 |
| 0200 | Safeloading | CUYD A A | 2 | $3,000.00 | $1,350.00 | $2,000.00 |
| 0210 | Edgeline rumble strips | LF A A | 325 | $15.20 | $15.20 | $19.00 |
| 0220 | Temp silt fence | LF A A | 491 | $5.00 | $3.50 | $3.00 |
| 0230 | Erosion control blanket | SQYD A A | 321 | $5.00 | $6.00 | $7.00 |
| 0240 | Seeding and protection | SQYD A A | 576 | $2.00 | $1.75 | $2.00 |
| 0250 | Pave striping-perm paint-6 in | LF A A | 565 | $0.50 | $0.50 | $0.60 |
| 0260 | Pave striping-thermo-6 in W | LF A A | 765 | $3.00 | $3.00 | $3.50 |
| 0270 | Pave marking-thermo stop bar-24IN | LF A A | 39 | $12.00 | $12.00 | $13.50 |
| 0280 | Pave marking-thermo curv arrow | EACH A A | 7 | $125.00 | $125.00 | $140.00 |
| 0290 | S manhole abandon/remove | EACH A A | 1 | $2,000.00 | $3,500.00 | $1,750.00 |
| 0300 | Joint adhesive | LF A A | 595 | $0.75 | $1.95 | $2.25 |
| 0310 | Longitudinal edge key | LF A A | 595 | $3.00 | $10.00 | $10.00 |
| 0320 | Longitudinal saw cut | LF A A | 595 | $2.00 | $3.50 | $5.00 |
| 0330 | Electronic delivery MGMT system - agg | LS A A | 1 | $1.00 | $0.01 | $2,500.00 |
| 0340 | SBM alum sheet signs .080 in | SQFT A A | 52 | $29.09 | $50.00 | $56.50 |
| 0350 | Steel post type 1 | LF A A | 36 | $26.64 | $50.00 | $56.50 |
| 0360 | Barcode sign inventory | EACH A A | 10 | $45.68 | $25.00 | $30.00 |
| 0370 | Conduit-1 1/4 in | LF A A | 440 | $8.00 | $8.00 | $9.00 |
| 0380 | Trenching and backfilling | LF A A | 500 | $6.00 | $6.00 | $6.75 |
| 0390 | Cable-no. 14/5C | LF A A | 440 | $3.00 | $3.00 | $3.50 |
| 0400 | Cable-no. 14/7C | LF A A | 1,610 | $3.00 | $3.00 | $3.50 |
| 0410 | Messenger-15400 LB | LF A A | 650 | $12.00 | $12.00 | $13.50 |
| 0420 | Install steel strain pole | EACH A A | 4 | $10,000 | $10,000 | $11,300 |
| 0430 | Temp relocation of signal head | EACH A A | 18 | $200.00 | $200.00 | $225.00 |
| 0440 | Install span mounted sign | EACH A A | 3 | $350.00 | $350.00 | $400.00 |
| 0450 | Install LED signal-3 section | EACH A A | 9 | $550.00 | $550.00 | $625.00 |
| 0460 | Install LED signal-5 section | EACH A A | 1 | $550.00 | $550.00 | $625.00 |
| 0470 | Install LED signal- 4 section | EACH A A | 2 | $550.00 | $550.00 | $625.00 |
| 0480 | Remove & reinstall coordinating unit | EACH A A | 1 | $3,500.00 | $3,500.00 | $4,000.00 |
| 0490 | Traffic signal pole base | CUYD A A | 36 | $250.00 | $250.00 | $285.00 |
| 0500 | PVC conduit-2 in-schedule 80 | LF A A | 60 | $6.00 | $6.00 | $7.00 |
| 0510 | Install signal controller-TY atc | EACH A A | 1 | $12,500 | $12,500 | $14,000 |
| 0520 | Remove signal equipment | EACH A A | 1 | $7,500.00 | $7,500.00 | $8,500.00 |
| 0530 | Install radar presence detector type A | EACH A A | 4 | $1,500.00 | $1,500.00 | $1,700.00 |
| 0540 | Demobilization | LS A A | 1 | $6,700.00 | $6,830.00 | $7,979.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of June 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.