KYTC contract 25-2042 bid tabulation
ASPHALT RESURFACING BARDSTOWN ROAD (US 31E). Let by Kentucky Transportation Cabinet on January 23, 2025, Jefferson, District 5. 5 bids received; low bid $1,978,600 by Flynn Brothers Contracting Inc, -30% against the engineer's estimate of $2,812,387.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 JAN 2025
- Pay items
- 46
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Flynn Brothers Contracting Inc | $1,978,600 | Low | -30% |
| 2 | E & B Paving LLC | $1,996,691 | +1.0% | -29% |
| 3 | Hall Contracting of Kentucky Inc | $2,064,000 | +4.0% | -27% |
| 4 | Louisville Paving Company Inc | $2,165,015 | +9.0% | -23% |
| 5 | Mac Construction & Excavating Inc | $2,176,714 | +10% | -23% |
Engineer's estimate: $2,812,387.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Flynn Brothers Contracting Inc | 2. E & B Paving LLC | 3. Hall Contracting of Kentucky Inc | 4. Louisville Paving Company Inc | 5. Mac Construction & Excavating Inc |
|---|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A | 1,510 | $70.20 | $69.00 | $80.00 | $73.00 | $85.00 |
| 0020 | CL2 asph surf 0.38D PG64-22 | TON A | 3,750 | $71.70 | $69.00 | $80.00 | $73.00 | $80.00 |
| 0030 | CL4 asph surf 0.38A PG76-22 | TON A | 11,650 | $80.35 | $79.00 | $90.00 | $93.75 | $94.00 |
| 0040 | Temporary signs | SQFT A | 470 | $6.29 | $7.42 | $4.00 | $4.00 | $7.50 |
| 0050 | Maintain & control traffic | LS A | 1 | $115,100 | $114,344 | $8,048.40 | $53,002 | $9,000.00 |
| 0060 | Portable changeable message sign | EACH A | 2 | $209.57 | $1,060.00 | $2,850.00 | $636.00 | $500.00 |
| 0070 | Mobilization for mill & text | LS A | 1 | $3,405.54 | $400.00 | $3,500.00 | $3,000.00 | $400.00 |
| 0080 | Asphalt pave milling & texturing | TON A | 240 | $33.43 | $17.83 | $43.00 | $31.50 | $64.50 |
| 0090 | Edgeline rumble strips | LF A | 85,250 | $0.16 | $0.15 | $0.15 | $0.15 | $0.15 |
| 0100 | Sidewalk-4 in concrete | SQYD A | 22 | $275.28 | $155.00 | $360.00 | $118.00 | $86.83 |
| 0110 | Arrow panel | EACH A | 2 | $419.15 | $1.00 | $650.00 | $424.00 | $300.00 |
| 0120 | Base failure repair | SQYD A | 2,675 | $33.48 | $40.00 | $45.00 | $35.00 | $55.00 |
| 0130 | Conduit-1 1/4 in | LF A | 80 | $5.45 | $5.20 | $5.20 | $5.20 | $26.00 |
| 0140 | Conduit-2 in | LF A | 20 | $7.56 | $7.21 | $7.21 | $7.21 | $29.00 |
| 0150 | Trenching and backfilling | LF A | 90 | $11.53 | $11.00 | $11.00 | $11.00 | $10.00 |
| 0160 | Piezoelectric sensor | EACH A | 8 | $1,870.43 | $1,785.00 | $1,785.00 | $1,785.00 | $2,940.00 |
| 0170 | Loop wire | LF A | 1,600 | $0.31 | $0.30 | $0.30 | $0.30 | $1.40 |
| 0180 | Loop saw slot and fill | LF A | 430 | $13.10 | $12.50 | $12.50 | $12.50 | $12.00 |
| 0190 | Pave striping-temp paint-4 in | LF A | 107,000 | $0.21 | $0.01 | $0.20 | $0.20 | $0.20 |
| 0200 | Pave striping-perm paint-4 in | LF A | 1,100 | $0.52 | $0.50 | $0.50 | $0.50 | $0.50 |
| 0210 | Pave striping-thermo-6 in W | LF A | 61,000 | $1.21 | $1.15 | $1.15 | $1.15 | $1.15 |
| 0220 | Pave striping-thermo-6 in Y | LF A | 46,000 | $1.21 | $1.15 | $1.15 | $1.15 | $1.15 |
| 0230 | Pave striping-thermo-12 in Y | LF A | 4,080 | $2.51 | $2.40 | $2.40 | $2.40 | $2.40 |
| 0240 | Pave striping-dur TY 1-6 in W | LF A | 810 | $10.48 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0250 | Pave striping-dur TY 1-6 in Y | LF A | 810 | $10.48 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0260 | Pave marking-thermo X-walk-6 in | LF A | 670 | $3.93 | $3.75 | $3.75 | $3.75 | $3.75 |
| 0270 | Pave marking-thermo stop bar-24IN | LF A | 577 | $12.57 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0280 | Pave marking-thermo curv arrow | EACH A | 127 | $130.98 | $125.00 | $125.00 | $125.00 | $125.00 |
| 0290 | Pave marking-thermo comb arrow | EACH A | 3 | $157.18 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0300 | Fuel adjustment | DOLL A | 26,259 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0310 | Asphalt adjustment | DOLL A | 65,922 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0320 | Galvanized steel cabinet | EACH A | 2 | $1,047.86 | $1,000.00 | $1,000.00 | $1,000.00 | $2,020.00 |
| 0330 | Wood post | EACH A | 4 | $261.97 | $250.00 | $250.00 | $250.00 | $580.00 |
| 0340 | Electrical junction box type A | EACH A | 2 | $2,095.72 | $2,000.00 | $2,000.00 | $2,000.00 | $3,460.00 |
| 0345 | Law enforcement officer | HOUR A | 225 | $78.59 | $78.00 | $95.00 | $90.00 | $75.00 |
| 0350 | Detectable warnings | SQFT A | 30 | $62.87 | $48.25 | $50.00 | $32.00 | $46.35 |
| 0360 | Pave stripe-wet ref tape-6 in W | LF A | 200 | $20.96 | $20.00 | $20.00 | $20.00 | $20.00 |
| 0370 | Pave marking-thermo dotted lane exten | LF A | 2,070 | $3.09 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0380 | Remove pavement marker | EACH A | 818 | $17.84 | $5.32 | $4.50 | $21.90 | $7.85 |
| 0390 | Pave marking-thermo U-turn | EACH A | 4 | $314.36 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0400 | Asphalt material for tack non-tracking | TON A | 90 | $0.01 | $0.01 | $0.01 | $0.01 | $0.03 |
| 0410 | Install radar presence detector type A | EACH A | 15 | $916.88 | $875.00 | $875.00 | $875.00 | $1,090.00 |
| 0420 | Install radar advance detector type B | EACH A | 4 | $916.88 | $875.00 | $875.00 | $875.00 | $1,090.00 |
| 0430 | Electronic delivery MGMT system | LS A | 1 | $0.01 | $0.01 | $1.00 | $1.00 | $1,000.00 |
| 0440 | Mobilization | LS A | 1 | $4,593.56 | $89,000 | $19,805 | $95,000 | $36,036 |
| 0450 | Demobilization | LS A | 1 | $30,669 | $28,000 | $30,955 | $32,600 | $31,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.