KYTC contract 25-2218 bid tabulation
ASPHALT RESURFACING PRESTON HIGHWAY (KY 61). Let by Kentucky Transportation Cabinet on June 5, 2025. 5 bids received; low bid $869,350 by Hall Contracting of Kentucky Inc, -22% against the engineer's estimate of $1,108,415.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 05 JUN 2025
- Pay items
- 49
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hall Contracting of Kentucky Inc | $869,350 | Low | -22% |
| 2 | E & B Paving LLC | $924,916 | +6.0% | -17% |
| 3 | Flynn Brothers Contracting Inc | $934,242 | +7.0% | -16% |
| 4 | Mac Construction & Excavating Inc | $970,211 | +12% | -12% |
| 5 | Louisville Paving Company Inc | $992,270 | +14% | -10% |
Engineer's estimate: $1,108,415.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hall Contracting of Kentucky Inc | 2. E & B Paving LLC | 3. Flynn Brothers Contracting Inc | 4. Mac Construction & Excavating Inc | 5. Louisville Paving Company Inc |
|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 40 | $25.00 | $210.00 | $92.50 | $176.20 | $64.00 |
| 0020 | Leveling & wedging PG64-22 | TON A A | 700 | $83.00 | $80.00 | $78.00 | $84.50 | $84.00 |
| 0030 | CL4 asph surf 0.38A PG76-22 | TON A A | 4,950 | $83.00 | $80.00 | $81.95 | $87.47 | $95.50 |
| 0040 | Adjust manhole frame to grade | EACH A A | 37 | $100.00 | $160.00 | $136.45 | $265.85 | $300.00 |
| 0050 | Standard header curb mod | LF A A | 16 | $125.00 | $175.00 | $182.95 | $350.20 | $120.00 |
| 0060 | Temporary signs | SQFT A A | 450 | $4.00 | $7.00 | $4.00 | $7.00 | $4.00 |
| 0065 | Maintain & control traffic | LS A A | 1 | $54,232 | $72,037 | $95,000 | $54,550 | $89,200 |
| 0070 | Portable changeable message sign | EACH A A | 2 | $550.00 | $500.00 | $660.00 | $1,100.00 | $700.00 |
| 0080 | Mobilization for mill & text | LS A A | 1 | $2,500.00 | $5,000.00 | $1,365.00 | $1,500.00 | $1,500.00 |
| 0090 | Asphalt pave milling & texturing | TON A A | 4,950 | $12.00 | $15.00 | $12.15 | $19.44 | $14.00 |
| 0100 | Edgeline rumble strips | LF A A | 3,250 | $1.17 | $3.00 | $2.48 | $2.25 | $2.25 |
| 0110 | Sidewalk-4 in concrete | SQYD A A | 4 | $250.00 | $670.00 | $1,005.00 | $978.95 | $190.00 |
| 0120 | Arrow panel | EACH A A | 2 | $250.00 | $300.00 | $660.00 | $650.00 | $400.00 |
| 0130 | Base failure repair | SQYD A A | 330 | $80.00 | $90.00 | $81.50 | $73.45 | $72.00 |
| 0140 | Adjust water valve | EACH A A | 60 | $100.00 | $18.00 | $100.00 | $196.50 | $100.00 |
| 0150 | Conduit-1 1/4 in | LF A A | 55 | $6.71 | $6.71 | $6.71 | $28.25 | $6.71 |
| 0160 | Conduit-2 in | LF A A | 15 | $9.29 | $9.29 | $9.29 | $32.30 | $9.29 |
| 0170 | Trenching and backfilling | LF A A | 60 | $11.00 | $11.00 | $11.00 | $8.75 | $11.00 |
| 0180 | Piezoelectric sensor | EACH A A | 4 | $3,500.00 | $3,500.00 | $3,500.00 | $3,012.00 | $3,500.00 |
| 0190 | Loop wire | LF A A | 2,650 | $0.30 | $0.30 | $0.30 | $1.50 | $0.30 |
| 0200 | Loop saw slot and fill | LF A A | 545 | $8.01 | $8.01 | $8.01 | $12.20 | $8.01 |
| 0210 | Remove and replace sidewalk | SQYD A A | 4 | $250.00 | $1,462.80 | $385.00 | $1,502.10 | $195.00 |
| 0220 | Pave striping-temp paint-4 in | LF A A | 55,000 | $0.26 | $0.26 | $0.26 | $0.25 | $0.26 |
| 0230 | Pave striping-thermo-6 in W | LF A A | 27,000 | $1.35 | $1.35 | $1.35 | $1.35 | $1.35 |
| 0240 | Pave striping-thermo-6 in Y | LF A A | 25,000 | $1.35 | $1.35 | $1.35 | $1.35 | $1.35 |
| 0250 | Pave striping-thermo-12 in W | LF A A | 270 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0260 | Pave striping-thermo-12 in Y | LF A A | 115 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 0270 | Pave marking-thermo X-walk-6 in | LF A A | 2,200 | $3.85 | $3.85 | $3.85 | $3.85 | $3.85 |
| 0280 | Pave marking-thermo stop bar-24IN | LF A A | 766 | $13.25 | $13.25 | $13.25 | $13.25 | $13.25 |
| 0290 | Pave marking-thermo curv arrow | EACH A A | 69 | $150.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0300 | Pave marking-thermo comb arrow | EACH A A | 6 | $185.00 | $185.00 | $185.00 | $185.00 | $185.00 |
| 0310 | Remove pavement marker type V | EACH A A | 580 | $4.00 | $6.01 | $5.00 | $4.00 | $4.00 |
| 0320 | Fuel adjustment | DOLL A A | 7,713 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0330 | Asphalt adjustment | DOLL A A | 19,372 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0340 | Galvanized steel cabinet | EACH A A | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,990.00 | $1,000.00 |
| 0350 | Wood post | EACH A A | 3 | $500.00 | $500.00 | $500.00 | $586.00 | $500.00 |
| 0360 | Electrical junction box type A | EACH A A | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $3,258.00 | $2,500.00 |
| 0370 | Law enforcement officer | HOUR A A | 120 | $80.00 | $80.00 | $78.59 | $85.00 | $120.00 |
| 0380 | Electrical junction box-10 X 8 X 4 | EACH A A | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $780.00 | $1,000.00 |
| 0390 | Pave mark thermo cone cap-solid yellow | SQFT A A | 30 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 0400 | Pave marking-thermo yield bar-36 in | LF A A | 70 | $32.00 | $32.00 | $32.00 | $32.00 | $32.00 |
| 0410 | Detectable warnings | SQFT A A | 16 | $50.00 | $73.50 | $53.99 | $53.50 | $34.00 |
| 0420 | Pave mark-thermo-X-walk-24 in | LF A A | 580 | $13.25 | $13.25 | $13.25 | $13.25 | $13.25 |
| 0430 | Pave mark thermo chevron | SQFT A A | 120 | $6.95 | $6.95 | $6.95 | $6.95 | $6.95 |
| 0440 | Pave marking-thermo dotted lane exten | LF A A | 196 | $3.85 | $3.85 | $3.85 | $3.85 | $3.85 |
| 0450 | Asphalt material for tack non-tracking | TON A A | 32 | $0.01 | $1.00 | $524.38 | $0.01 | $0.01 |
| 0460 | Install radar presence detector type A | EACH A A | 23 | $1,200.00 | $1,200.00 | $1,200.00 | $1,145.00 | $1,200.00 |
| 0470 | Install radar advance detector type B | EACH A A | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $1,145.00 | $1,200.00 |
| 0480 | Demobilization | LS A A | 1 | $13,040 | $26,200 | $14,672 | $15,000 | $15,084 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of June 5, 2025. Compiled by Mirage Metrics.