KYTC contract 25-2285 bid tabulation
ASPHALT RESURFACING HURSTBOURNE PARKWAY (KY 1747). Let by Kentucky Transportation Cabinet on October 23, 2025. 5 bids received; low bid $3,269,800 by Flynn Brothers Contracting Inc, -20% against the engineer's estimate of $4,070,978.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 OCT 2025
- Pay items
- 70
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Flynn Brothers Contracting Inc | $3,269,800 | Low | -20% |
| 2 | Louisville Paving Company Inc | $3,349,949 | +2.0% | -18% |
| 3 | Hall Contracting of Kentucky Inc | $3,588,500 | +10% | -12% |
| 4 | Mac Construction & Excavating Inc | $3,718,516 | +14% | -9.0% |
| 5 | E & B Paving LLC | $3,840,000 | +17% | -6.0% |
Engineer's estimate: $4,070,978.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Flynn Brothers Contracting Inc | 2. Louisville Paving Company Inc | 3. Hall Contracting of Kentucky Inc | 4. Mac Construction & Excavating Inc | 5. E & B Paving LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 1,503 | $74.55 | $77.00 | $83.50 | $100.00 | $92.00 |
| 0020 | CL3 asph surf 0.38D PG64-22 | TON A A | 485 | $74.55 | $77.00 | $86.00 | $93.00 | $100.00 |
| 0030 | CL4 asph surf 0.38A PG76-22 | TON A A | 20,455 | $76.45 | $91.50 | $93.00 | $104.00 | $92.00 |
| 0040 | Adjust manhole frame to grade | EACH A A | 15 | $161.25 | $500.00 | $200.00 | $118.00 | $212.00 |
| 0050 | Temporary signs | SQFT A A | 750 | $4.00 | $4.00 | $4.00 | $6.36 | $6.00 |
| 0060 | Maintain & control traffic | LS A A | 1 | $230,000 | $179,000 | $122,492 | $138,031 | $215,960 |
| 0070 | Portable changeable message sign | EACH A A | 4 | $636.00 | $800.00 | $1,550.00 | $1,060.00 | $1,000.00 |
| 0080 | Mobilization for mill & text | LS A A | 1 | $3,250.00 | $2,500.00 | $5,450.00 | $20,000 | $50,000 |
| 0090 | Asphalt pave milling & texturing | TON A A | 20,940 | $11.65 | $7.01 | $17.15 | $5.08 | $10.00 |
| 0100 | Sidewalk-4 in concrete | SQYD A A | 50 | $421.00 | $136.00 | $250.00 | $218.81 | $320.04 |
| 0110 | Arrow panel | EACH A A | 4 | $477.00 | $477.00 | $1,150.00 | $636.00 | $600.00 |
| 0120 | Base failure repair | SQYD A A | 635 | $56.40 | $47.00 | $59.00 | $74.00 | $58.36 |
| 0130 | Adjust water valve | EACH A A | 3 | $105.00 | $400.00 | $100.00 | $104.34 | $486.87 |
| 0140 | Conduit-1 1/4 in | LF A A | 280 | $7.17 | $7.17 | $7.17 | $7.17 | $13.43 |
| 0150 | Conduit-2 in | LF A A | 50 | $9.91 | $9.91 | $9.91 | $9.91 | $17.38 |
| 0160 | Trenching and backfilling | LF A A | 280 | $10.00 | $10.00 | $10.00 | $10.00 | $7.10 |
| 0170 | Piezoelectric sensor | EACH A A | 9 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,598.68 |
| 0180 | Loop wire | LF A A | 7,900 | $0.25 | $0.25 | $0.25 | $0.25 | $0.81 |
| 0190 | Loop saw slot and fill | LF A A | 1,600 | $8.00 | $8.00 | $8.00 | $8.00 | $27.43 |
| 0200 | Remove and replace sidewalk | SQYD A A | 4 | $535.00 | $85.00 | $175.00 | $1,360.76 | $1,260.19 |
| 0210 | Pave striping-temp paint-4 in | LF A A | 175,500 | $0.21 | $0.21 | $0.21 | $0.21 | $0.21 |
| 0220 | Pave striping-perm paint-4 in | LF A A | 2,400 | $0.23 | $0.23 | $0.23 | $0.23 | $0.23 |
| 0230 | Pave striping-perm paint-6 in | LF A A | 1,250 | $0.27 | $0.27 | $0.27 | $0.27 | $0.27 |
| 0240 | Pave striping-thermo-6 in W | LF A A | 108,500 | $1.10 | $1.10 | $1.10 | $1.10 | $1.60 |
| 0250 | Pave striping-thermo-6 in Y | LF A A | 67,000 | $1.10 | $1.10 | $1.10 | $1.10 | $1.60 |
| 0260 | Pave striping-thermo-12 in W | LF A A | 8,665 | $2.20 | $2.20 | $2.20 | $2.20 | $2.20 |
| 0270 | Pave striping-thermo-12 in Y | LF A A | 2,485 | $2.45 | $2.45 | $2.45 | $2.45 | $2.45 |
| 0280 | Pave striping-dur TY 1-6 in W | LF A A | 728 | $7.25 | $7.25 | $7.25 | $7.25 | $7.25 |
| 0290 | Pave striping-dur TY 1-6 in Y | LF A A | 678 | $7.25 | $7.25 | $7.25 | $7.25 | $7.25 |
| 0300 | Pave marking-thermo X-walk-6 in | LF A A | 11,620 | $3.25 | $3.25 | $3.25 | $3.25 | $3.25 |
| 0310 | Pave marking-thermo stop bar-24IN | LF A A | 2,813 | $12.95 | $12.95 | $12.95 | $12.95 | $12.95 |
| 0320 | Pave marking-thermo cross-hatch | SQFT A A | 280 | $4.95 | $4.95 | $4.95 | $4.95 | $4.95 |
| 0330 | Pave marking-thermo STR arrow | EACH A A | 16 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 0340 | Pave marking-thermo curv arrow | EACH A A | 383 | $145.00 | $145.00 | $145.00 | $145.00 | $145.00 |
| 0350 | Pave marking-thermo comb arrow | EACH A A | 25 | $165.00 | $165.00 | $165.00 | $165.00 | $165.00 |
| 0360 | Pave marking-thermo only | EACH A A | 30 | $295.00 | $295.00 | $295.00 | $295.00 | $295.00 |
| 0370 | Remove pavement marker type V | EACH A A | 2,835 | $5.00 | $4.50 | $4.50 | $2.75 | $2.75 |
| 0380 | Fuel adjustment | DOLL A A | 32,291 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0390 | Asphalt adjustment | DOLL A A | 81,105 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0400 | Galvanized steel cabinet | EACH A A | 6 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $884.98 |
| 0410 | Wood post | EACH A A | 18 | $500.00 | $500.00 | $500.00 | $500.00 | $453.13 |
| 0420 | Electrical junction box type A | EACH A A | 6 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $1,447.17 |
| 0430 | Law enforcement officer | HOUR A A | 1,000 | $65.00 | $30.00 | $95.00 | $85.00 | $60.00 |
| 0440 | Electrical junction box-10 X 8 X 4 | EACH A A | 6 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $454.37 |
| 0450 | Pave mark thermo cone cap-solid yellow | SQFT A A | 60 | $6.95 | $6.95 | $6.95 | $6.95 | $6.95 |
| 0460 | Pave marking-thermo yield bar-36 in | LF A A | 90 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 |
| 0470 | Pavement marking-thermo letters | EACH A A | 28 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0480 | Detectable warnings | SQFT A A | 61 | $75.00 | $34.00 | $35.00 | $47.16 | $123.83 |
| 0490 | Detectable warnings | SQFT A A | 120 | $65.00 | $39.00 | $65.00 | $78.52 | $99.68 |
| 0500 | Pave mark-thermo-X-walk-24 in | LF A A | 510 | $13.25 | $13.25 | $13.25 | $13.25 | $13.25 |
| 0510 | Pave mark thermo-lane reduction arrow | EACH A A | 6 | $425.00 | $425.00 | $425.00 | $425.00 | $425.00 |
| 0520 | Pave mark thermo chevron | SQFT A A | 320 | $4.95 | $4.95 | $4.95 | $4.95 | $4.95 |
| 0530 | Pave marking-thermo dotted lane exten | LF A A | 3,760 | $2.95 | $2.95 | $2.95 | $2.95 | $2.95 |
| 0540 | Pave mark thermo-wrong way arrow | EACH A A | 8 | $375.00 | $375.00 | $375.00 | $375.00 | $375.00 |
| 0550 | Lane separator curb | LF A A | 260 | $17.00 | $20.00 | $20.00 | $78.00 | $56.00 |
| 0560 | Pave marking-thermo U-turn | EACH A A | 3 | $225.00 | $225.00 | $225.00 | $225.00 | $225.00 |
| 0570 | Pave marking-thermo elong route shield | EACH A A | 7 | $3,200.00 | $3,200.00 | $3,200.00 | $3,200.00 | $3,200.00 |
| 0580 | Asphalt material for tack non-tracking | TON A A | 120 | $425.00 | $0.01 | $0.01 | $0.01 | $95.00 |
| 0590 | Install radar presence detector type A | EACH A A | 62 | $1,305.00 | $1,305.00 | $1,305.00 | $1,305.00 | $981.38 |
| 0600 | Install radar advance detector type B | EACH A A | 1 | $1,305.00 | $1,305.00 | $1,305.00 | $1,305.00 | $981.38 |
| 0610 | Pave stripe-wet ref cont tape-6 in W | LF A A | 245 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 0620 | Standard curb and gutter mod | LF A A | 122 | $84.95 | $87.00 | $60.00 | $128.92 | $74.61 |
| 0630 | Standard header curb mod | LF A A | 16 | $100.00 | $91.00 | $283.00 | $136.58 | $351.61 |
| 0640 | Temporary signs | SQFT A A | 750 | $4.00 | $4.00 | $4.00 | $6.36 | $6.00 |
| 0650 | Maintain & control traffic | LS A A | 1 | $17,300 | $43,092 | $1,920.00 | $64,173 | $148,663 |
| 0660 | Base failure repair | SQYD A A | 67 | $219.55 | $300.00 | $144.00 | $244.67 | $198.92 |
| 0670 | Concrete-class A | CUYD A A | 10 | $365.00 | $650.00 | $771.00 | $1,481.53 | $1,395.84 |
| 0680 | Remove non-mountable median | SQYD A A | 20 | $375.85 | $70.00 | $150.00 | $72.76 | $447.70 |
| 0690 | Remove mountable median | SQYD A A | 18 | $375.85 | $70.00 | $126.50 | $80.84 | $165.82 |
| 0700 | Demobilization | LS A A | 1 | $51,520 | $53,000 | $53,827 | $60,000 | $60,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.