KYTC contract 25-2922 bid tabulation
BRIDGE DECK RESTORATION & WATERPROOFING VARIOUS ROUTES IN ROWAN COUNTY - 2 LOCATIONS. Let by Kentucky Transportation Cabinet on March 20, 2025, Rowan, District 9. 4 bids received; low bid $610,602 by M & M Services Co Inc, -38% against the engineer's estimate of $980,352.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 MAR 2025
- Pay items
- 43
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M & M Services Co Inc | $610,602 | Low | -38% |
| 2 | Intech Contracting LLC | $872,624 | +43% | -11% |
| 3 | Delong Concrete LLC | $1,000,000 | +64% | +2.0% |
| 4 | American Contracting & Services Inc | $1,100,651 | +80% | +12% |
Engineer's estimate: $980,352.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M & M Services Co Inc | 2. Intech Contracting LLC | 3. Delong Concrete LLC | 4. American Contracting & Services Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Temporary signs | SQFT A | 100 | $9.00 | $15.00 | $15.00 | $25.00 |
| 0020 | Maintain & control traffic | LS A | 1 | $8,500.00 | $30,000 | $25,000 | $17,000 |
| 0030 | Lane closure | EACH A | 2 | $3,900.00 | $1,500.00 | $12,500 | $5,000.00 |
| 0040 | Portable changeable message sign | EACH A | 4 | $900.00 | $1,750.00 | $1,500.00 | $2,000.00 |
| 0050 | Expan joint replace 4 in | LF A | 60 | $514.00 | $888.00 | $800.00 | $900.00 |
| 0060 | Armored edge for concrete | LF A | 60 | $95.00 | $100.00 | $250.00 | $125.00 |
| 0070 | Bridge overlay approach pavement | SQYD A | 289 | $42.00 | $125.00 | $87.00 | $123.00 |
| 0080 | Temp signal 2 phase | EACH A | 1 | $3,400.00 | $7,700.00 | $10,500 | $5,500.00 |
| 0090 | Pave striping-perm paint-4 in | LF A | 1,828 | $0.35 | $1.00 | $1.50 | $2.00 |
| 0100 | Pave striping-temp rem tape-B | LF A | 1,000 | $1.75 | $2.00 | $2.00 | $3.00 |
| 0110 | Pave striping-temp rem tape-W | LF A | 2,000 | $1.19 | $1.00 | $1.50 | $1.80 |
| 0120 | Pave striping-temp rem tape-Y | LF A | 2,000 | $1.19 | $1.00 | $0.02 | $1.80 |
| 0130 | Steel reinforcement | LB A | 270 | $1.00 | $2.00 | $5.00 | $3.00 |
| 0140 | Epoxy sand slurry | SQYD A | 205 | $39.00 | $24.00 | $40.00 | $30.00 |
| 0150 | Rem epoxy bit foreign overlay | SQYD A | 1,030 | $16.00 | $40.00 | $32.00 | $45.00 |
| 0160 | Conc class M full depth patch | CUYD A | 10 | $800.00 | $1,200.00 | $4,500.00 | $2,500.00 |
| 0170 | Concrete overlay-latex | CUYD A | 42.90 | $1,200.00 | $1,900.00 | $1,850.00 | $2,850.00 |
| 0180 | Blast cleaning | SQYD A | 1,234 | $9.00 | $7.00 | $14.00 | $10.00 |
| 0190 | Partial depth patching | CUYD A | 31 | $1,100.00 | $1,000.00 | $1,500.00 | $1,100.00 |
| 0200 | Bridge cleaning | LS A | 1 | $8,500.00 | $3,500.00 | $15,000 | $9,000.00 |
| 0210 | Concrete coating | LS A | 1 | $10,550 | $8,000.00 | $18,500 | $10,000 |
| 0220 | Bearing lubrication | EACH A | 8 | $420.00 | $500.00 | $500.00 | $2,200.00 |
| 0230 | Temporary signs | SQFT A | 100 | $8.00 | $15.00 | $20.00 | $25.00 |
| 0240 | Maintain & control traffic | LS A | 1 | $9,100.00 | $30,000 | $25,000 | $17,000 |
| 0250 | Lane closure | EACH A | 2 | $3,900.00 | $1,500.00 | $12,500 | $5,000.00 |
| 0260 | Expan joint replace 4 in | LF A | 52 | $515.00 | $888.00 | $800.00 | $900.00 |
| 0270 | Armored edge for concrete | LF A | 52 | $90.00 | $100.00 | $250.00 | $125.00 |
| 0280 | Bridge overlay approach pavement | SQYD A | 289 | $38.00 | $125.00 | $89.00 | $123.00 |
| 0290 | Temp signal 2 phase | EACH A | 1 | $3,400.00 | $7,700.00 | $10,500 | $5,500.00 |
| 0300 | Pave striping-perm paint-4 in | LF A | 2,888 | $0.20 | $1.00 | $1.21 | $2.00 |
| 0310 | Pave striping-temp rem tape-B | LF A | 1,000 | $1.72 | $2.00 | $2.00 | $3.00 |
| 0320 | Pave striping-temp rem tape-W | LF A | 2,000 | $1.15 | $1.00 | $1.65 | $1.80 |
| 0330 | Pave striping-temp rem tape-Y | LF A | 2,000 | $1.15 | $1.00 | $0.02 | $1.80 |
| 0340 | Steel reinforcement | LB A | 270 | $85.00 | $2.00 | $5.00 | $3.00 |
| 0350 | Epoxy sand slurry | SQYD A | 415 | $39.00 | $24.00 | $41.00 | $30.00 |
| 0360 | Rem epoxy bit foreign overlay | SQYD A | 2,096 | $16.00 | $39.00 | $26.00 | $45.00 |
| 0370 | Conc class M full depth patch | CUYD A | 21 | $800.00 | $1,200.00 | $2,000.00 | $2,500.00 |
| 0380 | Concrete overlay-latex | CUYD A | 87.30 | $1,185.00 | $1,900.00 | $1,650.00 | $2,400.00 |
| 0390 | Blast cleaning | SQYD A | 2,512 | $9.00 | $7.00 | $14.00 | $10.00 |
| 0400 | Partial depth patching | CUYD A | 65 | $1,100.00 | $1,000.00 | $1,250.00 | $1,100.00 |
| 0410 | Bridge cleaning | LS A | 1 | $9,000.00 | $3,500.00 | $20,000 | $20,000 |
| 0420 | Bearing lubrication | EACH A | 8 | $405.00 | $500.00 | $650.00 | $2,600.00 |
| 0430 | Demobilization | LS A | 1 | $9,023.67 | $12,896 | $15,745 | $16,290 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.