KYTC contract 25-2962 bid tabulation

BRIDGE DECK RESTORATION & WATERPROOFING VARIOUS ROUTES IN BOYLE AND GARRARD COUNTIES ~ 3 LOCATIONS. Let by Kentucky Transportation Cabinet on February 20, 2025, Boyle, Garrard, District 7. 4 bids received; low bid $476,668 by Delong Concrete LLC, -21% against the engineer's estimate of $605,478.

Owner
Kentucky Transportation Cabinet
Letting
20 FEB 2025
Pay items
61
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Delong Concrete LLC$476,668Low-21%
2M & M Services Co Inc$525,736+10%-13%
3Intech Contracting LLC$685,352+44%+13%
4American Contracting & Services Inc$757,471+59%+25%
KYTC contract 25-2962: bids by rank

Engineer's estimate: $605,478.

Bid tabulation

LinePay itemUnitQuantity1. Delong Concrete LLC2. M & M Services Co Inc3. Intech Contracting LLC4. American Contracting & Services Inc
0010Remove concrete masonryCUYD A1.30$1,000.00$4,500.00$4,000.00$4,000.00
0020Temporary signsSQFT A100$15.00$10.00$5.00$20.00
0030Maintain & control trafficLS A1$8,500.00$7,500.00$35,000$10,000
0040Lane closureEACH A2$3,200.00$3,900.00$250.00$5,000.00
0050Armored edge for concreteLF A68$300.00$355.00$125.00$170.00
0060Eliminate transverse jointLF A68$500.00$550.00$515.00$560.00
0070Bridge overlay approach pavementSQYD A534$42.00$49.00$58.00$50.00
0080Temp signal 2 phaseEACH A1$7,500.00$4,200.00$1,500.00$6,000.00
0090Pave striping-perm paint-4 inLF A552$2.52$2.00$1.00$3.00
0100Pave striping-temp rem tape-BLF A1,000$0.05$1.80$2.00$3.00
0110Pave striping-temp rem tape-WLF A2,000$0.05$1.50$1.50$1.80
0120Pave striping-temp rem tape-YLF A2,000$0.05$1.50$0.15$1.80
0130Concrete-class ACUYD A1.30$3,000.00$950.00$8,000.00$5,000.00
0140Steel reinforcementLB A510$5.00$1.50$1.50$3.00
0150Jack & support bridge spanLS A1$22,500$45,000$66,900$30,000
0160Epoxy sand slurrySQYD A77$40.00$55.00$25.00$35.00
0170Rem epoxy bit foreign overlaySQYD A203$40.00$24.00$95.00$85.00
0180Conc class M full depth patchCUYD A4$350.00$850.00$2,500.00$2,500.00
0190Concrete overlay-latexCUYD A8.40$2,500.00$1,378.00$4,500.00$8,300.00
0200Blast cleaningSQYD A280$20.00$11.00$8.00$10.00
0210Partial depth patchingCUYD A6$1,500.00$1,390.00$1,350.00$1,100.00
0220Bridge cleaningLS A1$2,000.00$9,500.00$3,500.00$10,000
0230Concrete coatingLS A1$10,000$11,000$5,500.00$12,000
0240Bearing lubricationEACH A8$300.00$495.00$450.00$1,000.00
0250Temporary signsSQFT A100$2.50$9.00$5.00$20.00
0260Maintain & control trafficLS A1$9,000.00$7,800.00$20,000$10,000
0270Lane closureEACH A2$3,425.00$4,100.00$250.00$5,000.00
0280Armored edge for concreteLF A64.50$300.00$355.00$450.00$330.00
0290Eliminate transverse jointLF A35.40$525.00$550.00$600.00$680.00
0300Bridge overlay approach pavementSQYD A425$44.00$49.00$58.00$50.00
0310Temp signal multi phaseEACH A1$200.00$4,100.00$1,500.00$7,500.00
0320Pave striping-perm paint-4 inLF A472$2.52$2.00$1.00$3.00
0330Pave striping-temp rem tape-BLF A1,000$0.05$1.80$2.00$3.00
0340Pave striping-temp rem tape-WLF A2,000$0.05$1.50$1.50$1.80
0350Pave striping-temp rem tape-YLF A2,000$0.05$1.50$0.15$1.80
0360Steel reinforcementLB A525$3.00$1.20$1.50$3.00
0370Epoxy sand slurrySQYD A70$40.00$55.00$25.00$35.00
0380Conc class M full depth patchCUYD A1$1,000.00$950.00$3,000.00$2,500.00
0390Concrete overlay-latexCUYD A12.30$2,250.00$1,390.00$3,000.00$5,700.00
0400Blast cleaningSQYD A364$18.00$11.00$8.00$10.00
0410Machine prep of slabSQYD A295$22.00$18.00$75.00$65.00
0420Partial depth patchingCUYD A10$1,250.00$1,390.00$1,300.00$1,100.00
0430Temporary signsSQFT A100$2.50$9.00$5.00$20.00
0440Maintain & control trafficLS A1$9,000.00$7,800.00$20,000$10,000
0450Lane closureEACH A2$3,425.00$3,900.00$250.00$5,000.00
0460Armored edge for concreteLF A80.10$300.00$355.00$450.00$330.00
0470Eliminate transverse jointLF A43.60$525.00$550.00$600.00$680.00
0480Bridge overlay approach pavementSQYD A425$42.00$49.00$58.00$50.00
0490Temp signal multi phaseEACH A1$200.00$4,100.00$1,500.00$7,500.00
0500Pave striping-perm paint-4 inLF A470$2.52$2.00$1.00$3.00
0510Pave striping-temp rem tape-BLF A1,000$0.05$1.80$2.00$3.00
0520Pave striping-temp rem tape-WLF A2,000$0.05$1.50$1.50$1.80
0530Pave striping-temp rem tape-YLF A2,000$0.05$1.50$0.15$1.80
0540Steel reinforcementLB A525$3.00$1.50$1.50$3.00
0550Epoxy sand slurrySQYD A71$40.00$55.00$25.00$35.00
0560Conc class M full depth patchCUYD A1$1,000.00$950.00$3,000.00$2,500.00
0570Concrete overlay-latexCUYD A12.40$2,250.00$1,395.00$3,200.00$5,700.00
0580Blast cleaningSQYD A367$18.00$11.00$8.00$10.00
0590Machine prep of slabSQYD A296$22.00$18.00$75.00$65.00
0600Partial depth patchingCUYD A10$1,250.00$1,390.00$1,300.00$1,100.00
0610DemobilizationLS A1$7,045.00$8,350.00$10,128$11,211
KYTC contract 25-2962: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of February 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way