KYTC contract 25-2963 bid tabulation
BRIDGE DECK RESTORATION & WATERPROOFING US 41 ALT AND KY 107 ~ 2 BRIDGES. Let by Kentucky Transportation Cabinet on March 20, 2025, Christian, District 2. 3 bids received; low bid $500,576 by Delong Concrete LLC, -5.0% against the engineer's estimate of $527,014.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 MAR 2025
- Pay items
- 46
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Delong Concrete LLC | $500,576 | Low | -5.0% |
| 2 | American Contracting & Services Inc | $710,163 | +42% | +35% |
| 3 | Intech Contracting LLC | $749,603 | +50% | +42% |
Engineer's estimate: $527,014.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Delong Concrete LLC | 2. American Contracting & Services Inc | 3. Intech Contracting LLC |
|---|---|---|---|---|---|---|
| 0010 | Relocate temp conc barrier | LF A | 1,533 | $1.00 | $15.00 | $12.00 |
| 0020 | Temporary signs | SQFT A | 140 | $20.00 | $25.00 | $10.00 |
| 0030 | Maintain & control traffic | LS A | 1 | $22,500 | $15,000 | $50,000 |
| 0040 | Lane closure | EACH A | 4 | $10,050 | $3,000.00 | $2,000.00 |
| 0045 | Portable changeable message sign | EACH A | 2 | $1,500.00 | $1,500.00 | $3,300.00 |
| 0050 | Arrow panel | EACH A | 1 | $2,000.00 | $1,500.00 | $2,000.00 |
| 0060 | Relocate crash cushion | EACH A | 3 | $4,000.00 | $4,000.00 | $2,000.00 |
| 0070 | Conc barrier wall type 9T | LF A | 511 | $2.00 | $65.00 | $120.00 |
| 0080 | Armored edge for concrete | LF A | 140.60 | $285.00 | $340.00 | $550.00 |
| 0090 | Bridge overlay approach pavement | SQYD A | 782 | $32.00 | $50.00 | $31.00 |
| 0100 | Pave striping-perm paint-4 in | LF A | 1,266 | $1.50 | $1.25 | $1.25 |
| 0110 | Pave striping-temp rem tape-B | LF A | 2,000 | $0.05 | $3.00 | $2.00 |
| 0120 | Pave striping-temp rem tape-W | LF A | 4,000 | $0.02 | $1.80 | $1.60 |
| 0130 | Pave striping-temp rem tape-Y | LF A | 4,000 | $0.02 | $1.80 | $1.60 |
| 0140 | Steel reinforcement | LB A | 1,785 | $2.00 | $3.00 | $2.00 |
| 0150 | Epoxy sand slurry | SQYD A | 317 | $35.00 | $30.00 | $14.00 |
| 0160 | Rem epoxy bit foreign overlay | SQYD A | 868 | $25.00 | $50.00 | $92.00 |
| 0170 | Conc class M full depth patch | CUYD A | 2 | $1,000.00 | $4,000.00 | $2,000.00 |
| 0180 | Concrete overlay-latex | CUYD A | 36.10 | $1,696.95 | $3,500.00 | $2,200.00 |
| 0190 | Joint sealing | LF A | 192 | $95.00 | $30.00 | $17.00 |
| 0200 | Blast cleaning | SQYD A | 1,184 | $14.00 | $10.00 | $10.00 |
| 0210 | Temp crash cushion | EACH A | 1 | $4,000.00 | $7,000.00 | $10,000 |
| 0220 | Partial depth patching | CUYD A | 32 | $1,200.00 | $1,100.00 | $900.00 |
| 0230 | Deck drain retrofit | EACH A | 7 | $250.00 | $550.00 | $300.00 |
| 0240 | Deck drain retrofit | EACH A | 6 | $250.00 | $500.00 | $700.00 |
| 0250 | Temporary signs | SQFT A | 149 | $10.00 | $25.00 | $10.00 |
| 0260 | Maintain & control traffic | LS A | 1 | $5,000.00 | $15,000 | $50,000 |
| 0270 | Lane closure | EACH A | 2 | $2,500.00 | $4,500.00 | $2,000.00 |
| 0275 | Portable changeable message sign | EACH A | 2 | $1,500.00 | $1,500.00 | $3,300.00 |
| 0280 | Armored edge for concrete | LF A | 46 | $600.00 | $480.00 | $550.00 |
| 0290 | Eliminate transverse joint | LF A | 23 | $934.78 | $1,000.00 | $750.00 |
| 0300 | Bridge overlay approach pavement | SQYD A | 512 | $46.00 | $60.00 | $41.00 |
| 0310 | Temp signal 2 phase | EACH A | 1 | $7,500.00 | $5,200.00 | $7,700.00 |
| 0320 | Pave striping-perm paint-4 in | LF A | 444 | $4.50 | $3.38 | $1.25 |
| 0330 | Pave striping-temp rem tape-B | LF A | 1,000 | $0.02 | $3.00 | $2.00 |
| 0340 | Pave striping-temp rem tape-W | LF A | 2,000 | $0.02 | $1.80 | $1.60 |
| 0350 | Pave striping-temp rem tape-Y | LF A | 2,000 | $0.02 | $1.80 | $0.10 |
| 0360 | Steel reinforcement | LB A | 435 | $2.00 | $3.00 | $2.00 |
| 0370 | Epoxy sand slurry | SQYD A | 72 | $45.00 | $30.00 | $30.00 |
| 0380 | Conc class M full depth patch | CUYD A | 2 | $1,000.00 | $4,000.00 | $2,000.00 |
| 0390 | Concrete overlay-latex | CUYD A | 10.20 | $2,500.00 | $5,150.00 | $3,500.00 |
| 0400 | Blast cleaning | SQYD A | 317 | $16.00 | $10.00 | $10.00 |
| 0410 | Machine prep of slab | SQYD A | 246 | $36.00 | $50.00 | $130.00 |
| 0420 | Partial depth patching | CUYD A | 10 | $1,250.00 | $1,100.00 | $900.00 |
| 0430 | Deck drain retrofit | EACH A | 24 | $250.00 | $600.00 | $300.00 |
| 0440 | Demobilization | LS A | 1 | $7,398.00 | $10,510 | $11,078 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.