KYTC contract 25-2965 bid tabulation

BRIDGE DECK RESTORATION & WATERPROOFING EAST MADISON STREET (KY 3). Let by Kentucky Transportation Cabinet on October 23, 2025. 6 bids received; low bid $1,325,000 by Delong Concrete LLC, -26% against the engineer's estimate of $1,787,944.

Owner
Kentucky Transportation Cabinet
Letting
23 OCT 2025
Pay items
28
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Delong Concrete LLC$1,325,000Low-26%
2M & M Services Co Inc$1,330,5120.0%-26%
3Intech Contracting LLC$1,798,860+36%+1.0%
4American Contracting & Services Inc$2,043,495+54%+14%
5Triton Construction Inc$2,145,000+62%+20%
6Bush & Burchett Inc$2,292,140+73%+28%
KYTC contract 25-2965: bids by rank

Engineer's estimate: $1,787,944.

Bid tabulation

LinePay itemUnitQuantity1. Delong Concrete LLC2. M & M Services Co Inc3. Intech Contracting LLC4. American Contracting & Services Inc5. Triton Construction Inc6. Bush & Burchett Inc
0010Temporary signsSQFT A A150$20.00$9.00$25.00$25.00$15.00$20.00
0020Maintain & control trafficLS A A1$25,000$15,000$95,000$57,000$165,000$300,000
0030Lane closureEACH A A3$8,500.00$12,500$2,500.00$3,500.00$5,000.00$10,000
0040Expan joint replace 2 inLF A A224.30$525.00$525.00$900.00$850.00$1,000.00$1,000.00
0050Expan joint replace 4 inLF A A66.60$1,125.00$550.00$1,100.00$1,400.00$1,200.00$1,250.00
0060Armored edge for concreteLF A A117.20$175.00$105.00$125.00$120.00$125.00$200.00
0070Bridge overlay approach pavementSQYD A A518$56.00$42.00$133.00$131.00$131.00$130.15
0080Temp signal multi phaseEACH A A1$16,500$18,500$15,000$30,000$56,000$30,000
0090Pave striping-perm paint-4 inLF A A5,840$0.55$0.50$0.50$0.50$0.50$0.50
0100Pave striping-temp rem tape-BLF A A2,000$0.05$1.85$2.00$4.32$2.50$3.00
0110Pave striping-temp rem tape-WLF A A4,000$1.62$1.30$1.50$2.62$1.50$2.50
0120Pave striping-temp rem tape-YLF A A4,000$0.01$1.30$0.15$2.62$1.50$2.50
0130Pave marking-thermo R 6 FTEACH A A2$200.00$2.00$150.00$150.00$150.00$150.00
0140Pave marking-R/R xbucks 16 inLF A A46$14.00$25.00$12.00$12.00$12.00$12.00
0150Pave marking-thermo stop bar-24INLF A A230$15.50$25.00$15.00$15.00$15.00$15.00
0160Steel reinforcementLB A A1,070$1.00$1.80$1.00$3.00$3.00$2.00
0170Epoxy sand slurrySQYD A A3,336$28.00$48.00$10.00$20.00$35.00$35.00
0180Conc class M full depth patchCUYD A A23$100.00$850.00$1,000.00$2,000.00$1,500.00$2,000.00
0190Concrete overlay-latexCUYD A A224.20$2,100.00$1,205.00$2,200.00$2,800.00$3,000.00$2,250.00
0200Blast cleaningSQYD A A8,716$8.50$8.00$5.00$7.00$15.00$10.00
0210Machine prep of slabSQYD A A5,380$23.25$14.75$45.00$35.00$25.00$45.00
0220Concrete patching repairSQFT A A200$325.00$170.00$300.00$400.00$265.00$250.00
0230Partial depth patchingCUYD A A157$1.00$1,200.00$1,500.00$1,200.00$1,000.00$1,000.00
0240Bridge cleaningLS A A1$24,000$45,000$30,000$35,000$70,000$60,000
0250Concrete coatingLS A A1$32,000$28,000$30,000$40,000$10,000$120,000
0260Bearing lubricationEACH A A30$500.00$550.00$600.00$3,250.00$900.00$800.00
0270FRP wrapSQFT A A1,078$70.00$105.00$60.00$70.00$50.00$50.00
0280DemobilizationLS A A1$19,973$19,850$26,584$30,244$32,590$34,000
KYTC contract 25-2965: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy