KYTC contract 25-2979 bid tabulation
BRIDGE REPAIR MISCELLANEOUS WORK ROBERT H. FOGLESONG BRIDGE OVER TUG FORK AND NS RR (US 119). Let by Kentucky Transportation Cabinet on September 25, 2025. 7 bids received; low bid $2,563,187 by M & M Services Co Inc, -9.0% against the engineer's estimate of $2,817,007.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 SEP 2025
- Pay items
- 37
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M & M Services Co Inc | $2,563,187 | Low | -9.0% |
| 2 | Intech Contracting LLC | $2,868,557 | +12% | +2.0% |
| 3 | Delong Concrete LLC | $2,877,971 | +12% | +2.0% |
| 4 | Bush & Burchett Inc | $3,016,200 | +18% | +7.0% |
| 5 | American Contracting & Services Inc | $3,561,186 | +39% | +26% |
| 6 | Triton Construction Inc | $3,840,000 | +50% | +36% |
| 7 | Southern Road & Bridge LLC | $5,962,817 | +133% | +112% |
Engineer's estimate: $2,817,007.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M & M Services Co Inc | 2. Intech Contracting LLC | 3. Delong Concrete LLC | 4. Bush & Burchett Inc | 5. American Contracting & Services Inc | 6. Triton Construction Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Relocate temp conc barrier | LF A A | 1,070 | $13.00 | $15.00 | $15.00 | $20.00 | $10.00 | $10.00 |
| 0020 | Barricade-type III | EACH A A | 2 | $225.00 | $100.00 | $250.00 | $200.00 | $500.00 | $200.00 |
| 0030 | Temporary signs | SQFT A A | 308 | $9.00 | $7.00 | $15.00 | $15.00 | $20.00 | $15.00 |
| 0040 | Maintain & control traffic | LS A A | 1 | $425,000 | $365,000 | $150,000 | $600,000 | $100,000 | $200,000 |
| 0050 | Portable changeable message sign | EACH A A | 2 | $7,500.00 | $5,000.00 | $10,000 | $2,000.00 | $7,000.00 | $5,000.00 |
| 0060 | Arrow panel | EACH A A | 2 | $450.00 | $1,000.00 | $3,500.00 | $2,000.00 | $4,500.00 | $3,000.00 |
| 0070 | Relocate crash cushion | EACH A A | 2 | $1,900.00 | $2,500.00 | $4,500.00 | $3,000.00 | $4,000.00 | $5,000.00 |
| 0080 | Conc barrier wall type 9T | LF A A | 1,070 | $20.00 | $135.00 | $42.00 | $40.00 | $100.00 | $40.00 |
| 0090 | Expan joint replace 3 in | LF A A | 183 | $555.00 | $900.00 | $1,050.00 | $800.00 | $1,100.00 | $1,800.00 |
| 0100 | Expan joint replace 4 in | LF A A | 176 | $585.00 | $975.00 | $1,250.00 | $900.00 | $1,650.00 | $2,300.00 |
| 0110 | Armored edge for concrete | LF A A | 183 | $105.00 | $125.00 | $250.00 | $300.00 | $130.00 | $150.00 |
| 0120 | Bridge overlay approach pavement | SQYD A A | 1,453 | $39.00 | $63.00 | $58.00 | $70.00 | $62.00 | $60.00 |
| 0130 | Temp relocation of signal head | EACH A A | 12 | $6,800.00 | $1,000.00 | $250.00 | $500.00 | $4,382.00 | $4,400.00 |
| 0140 | Pave striping-temp paint-4 in | LF A A | 7,065 | $0.45 | $0.25 | $0.75 | $0.25 | $1.00 | $0.25 |
| 0150 | Pave striping-perm paint-4 in | LF A A | 10,650 | $0.30 | $0.40 | $0.85 | $0.40 | $0.50 | $0.40 |
| 0160 | Pave striping-temp rem tape-W | LF A A | 7,520 | $1.55 | $1.50 | $1.50 | $2.00 | $2.30 | $3.25 |
| 0170 | Pave striping-temp rem tape-Y | LF A A | 5,833 | $1.55 | $1.50 | $1.50 | $2.00 | $2.30 | $3.25 |
| 0180 | Concrete-class M 1 | CUYD A A | 11 | $1,250.00 | $19,000 | $11,500 | $2,500.00 | $25,000 | $30,000 |
| 0190 | Steel reinforcement-epoxy coated | LB A A | 1,810 | $2.35 | $1.00 | $3.50 | $3.00 | $4.00 | $3.00 |
| 0200 | Epoxy sand slurry | SQYD A A | 800 | $45.00 | $30.00 | $42.00 | $35.00 | $35.00 | $40.00 |
| 0210 | Conc class M full depth patch | CUYD A A | 25 | $1,150.00 | $1,750.00 | $250.00 | $2,000.00 | $2,000.00 | $1,000.00 |
| 0220 | Concrete overlay-latex | CUYD A A | 190 | $1,200.00 | $3,000.00 | $1,850.00 | $2,000.00 | $2,180.00 | $2,600.00 |
| 0230 | Blast cleaning | SQYD A A | 5,356 | $9.00 | $12.00 | $12.00 | $10.00 | $10.00 | $20.00 |
| 0240 | Machine prep of slab | SQYD A A | 4,556 | $14.00 | $32.00 | $32.00 | $50.00 | $100.00 | $50.00 |
| 0250 | Temp crash cushion | EACH A A | 4 | $4,500.00 | $5,000.00 | $8,500.00 | $4,000.00 | $13,000 | $7,500.00 |
| 0260 | Concrete patching repair | SQFT A A | 892 | $525.00 | $250.00 | $550.00 | $250.00 | $325.00 | $350.00 |
| 0270 | Water blasting existing stripe | LF A A | 21,225 | $0.40 | $0.65 | $0.75 | $0.30 | $1.00 | $0.65 |
| 0280 | Partial depth patching | CUYD A A | 80 | $1,250.00 | $1,275.00 | $2,775.00 | $1,000.00 | $1,230.00 | $1,500.00 |
| 0290 | Railroad coordination | LS A A | 1 | $185,000 | $50,000 | $150,000 | $250,000 | $150,000 | $165,000 |
| 0300 | Steel repair | EACH A A | 2 | $18,000 | $9,000.00 | $15,000 | $25,000 | $20,000 | $25,000 |
| 0310 | Bridge cleaning | LS A A | 1 | $72,000 | $17,000 | $55,000 | $20,000 | $30,000 | $245,000 |
| 0320 | Concrete coating | LS A A | 1 | $32,000 | $37,000 | $65,000 | $50,000 | $30,000 | $15,000 |
| 0330 | Bearing lubrication | EACH A A | 22 | $500.00 | $500.00 | $800.00 | $1,000.00 | $3,500.00 | $1,200.00 |
| 0340 | Bearing lubrication | EACH A A | 44 | $600.00 | $500.00 | $1,200.00 | $1,000.00 | $4,600.00 | $1,200.00 |
| 0350 | FRP wrap | SQFT A A | 1,943 | $115.00 | $45.00 | $42.00 | $60.00 | $60.00 | $60.00 |
| 0360 | Mobilization | LS A A | 1 | $50,000 | $134,674 | $55,000 | $140,000 | $160,253 | $180,000 |
| 0370 | Demobilization | LS A A | 1 | $37,500 | $40,402 | $42,532 | $42,600 | $52,706 | $56,300 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.