KYTC contract 25-2981 bid tabulation
BRIDGE SUPERSTRUCTURE REPLACEMENT SOUTH PROPERTY ROAD (KY 573). Let by Kentucky Transportation Cabinet on August 21, 2025. 5 bids received; low bid $326,000 by Hall Contracting of Kentucky Inc, -19% against the engineer's estimate of $403,429.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 36
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hall Contracting of Kentucky Inc | $326,000 | Low | -19% |
| 2 | M & M Services Co Inc | $370,095 | +14% | -8.0% |
| 3 | Judy C Harp Company Inc | $371,776 | +14% | -8.0% |
| 4 | Jave LLC | $417,470 | +28% | +3.0% |
| 5 | Hinkle Construction Services LLC | $456,826 | +40% | +13% |
Engineer's estimate: $403,429.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hall Contracting of Kentucky Inc | 2. M & M Services Co Inc | 3. Judy C Harp Company Inc | 4. Jave LLC | 5. Hinkle Construction Services LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Asphalt seal aggregate | TON A A | 2 | $2,100.00 | $1,450.00 | $2,625.00 | $2,677.50 | $2,760.00 |
| 0020 | Asphalt seal coat | TON A A | 0.30 | $6,700.00 | $3,000.00 | $7,215.00 | $7,359.30 | $7,600.00 |
| 0030 | CL3 asph base 1.00D PG64-22 | TON A A | 17 | $625.00 | $155.00 | $305.59 | $311.70 | $322.00 |
| 0040 | CL3 asph surf 0.38D PG64-22 | TON A A | 30 | $350.00 | $155.00 | $380.45 | $388.06 | $400.00 |
| 0050 | Asphalt material for tack | TON A A | 0.20 | $1.00 | $2,200.00 | $32.75 | $33.41 | $34.50 |
| 0060 | Edge key | LF A A | 40 | $51.00 | $15.00 | $81.85 | $83.49 | $86.00 |
| 0070 | Longitudinal edge key | LF A A | 150 | $51.00 | $15.00 | $68.60 | $69.97 | $72.00 |
| 0080 | Crushed stone base | TON A A | 161 | $40.00 | $65.00 | $58.65 | $59.82 | $62.00 |
| 0090 | Cement stabilized roadbed | SQYD A A | 159 | $180.00 | $145.00 | $75.00 | $167.28 | $153.00 |
| 0100 | Barricade-type III | EACH A A | 2 | $100.00 | $200.00 | $1,000.00 | $102.00 | $155.00 |
| 0110 | Roadway excavation | CUYD A A | 84 | $37.00 | $145.00 | $75.00 | $76.80 | $52.00 |
| 0120 | Guardrail-steel W beam-S face | LF A A | 25 | $48.00 | $50.00 | $46.94 | $47.88 | $79.00 |
| 0130 | Guardrail end treatment type 1 | EACH A A | 4 | $4,600.00 | $4,800.00 | $4,568.81 | $4,659.68 | $5,260.00 |
| 0140 | Temporary signs | SQFT A A | 290 | $5.00 | $11.00 | $10.00 | $5.10 | $9.00 |
| 0150 | Ditching and shouldering | LF A A | 180 | $13.00 | $15.00 | $65.00 | $24.00 | $15.00 |
| 0160 | Maintain & control traffic | LS A A | 1 | $20,000 | $19,000 | $15,000 | $4,156.50 | $39,850 |
| 0170 | Staking | LS A A | 1 | $15,000 | $12,000 | $2,000.00 | $4,200.00 | $3,690.00 |
| 0180 | Cyclopean stone rip rap | TON A A | 44 | $70.00 | $70.00 | $91.00 | $92.40 | $90.00 |
| 0190 | Object marker TY 3 | EACH A A | 4 | $51.00 | $65.00 | $50.70 | $51.71 | $105.00 |
| 0200 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $4,130.00 | $4,000.00 | $3,479.76 | $3,549.36 | $4,735.00 |
| 0210 | Remove concrete masonry | CUYD A A | 0.50 | $3,500.00 | $4,500.00 | $8,000.00 | $17,280 | $6,560.00 |
| 0220 | Masonry coating | SQYD A A | 91 | $25.00 | $9.00 | $12.00 | $31.20 | $71.00 |
| 0230 | Armored edge for concrete | LF A A | 45.90 | $70.00 | $85.00 | $250.00 | $106.80 | $100.00 |
| 0240 | Foundation preparation | LS A A | 1 | $10,000 | $28,000 | $5,500.00 | $39,762 | $25,050 |
| 0250 | Concrete-class A | CUYD A A | 3.60 | $4,500.00 | $2,500.00 | $5,556.00 | $6,420.00 | $5,510.00 |
| 0260 | Concrete-class AA | CUYD A A | 24.10 | $2,000.00 | $1,850.00 | $3,500.00 | $2,541.60 | $4,250.00 |
| 0270 | Steel reinforcement | LB A A | 1,295 | $2.00 | $2.00 | $4.00 | $11.52 | $1.90 |
| 0280 | Steel reinforcement-epoxy coated | LB A A | 5,554 | $2.50 | $2.15 | $3.00 | $2.84 | $2.05 |
| 0290 | Structural steel | LS A A | 1 | $50,000 | $68,000 | $25,000 | $38,298 | $44,150 |
| 0300 | Shear connectors | LS A A | 1 | $1.00 | $4,200.00 | $2,000.00 | $12,000 | $4,000.00 |
| 0310 | Remove superstructure | LS A A | 1 | $3,000.00 | $28,000 | $20,000 | $24,000 | $18,565 |
| 0320 | Concrete sealing | SQFT A A | 1,194 | $2.10 | $3.00 | $2.50 | $2.82 | $5.00 |
| 0330 | Deck drain | EACH A A | 2 | $450.00 | $450.00 | $1,750.00 | $1,455.60 | $1,440.00 |
| 0340 | Rail system single slope - 40 in | LF A A | 59 | $200.00 | $285.00 | $400.00 | $397.20 | $405.00 |
| 0350 | Mobilization for concrete surf treatment | LS A A | 1 | $1,000.00 | $2,500.00 | $4,500.00 | $2,400.00 | $1,385.00 |
| 0360 | Demobilization | LS A A | 1 | $5,091.40 | $5,856.82 | $5,495.00 | $6,169.51 | $6,800.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.