KYTC contract 25-2985 bid tabulation
BRIDGE REPLACEMENT STATE HWY 687 (KY 687). Let by Kentucky Transportation Cabinet on April 24, 2025, Clay, District 11. 4 bids received; low bid $825,463 by Kay & Kay Contracting LLC, -20% against the engineer's estimate of $1,038,013.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 APR 2025
- Pay items
- 38
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kay & Kay Contracting LLC | $825,463 | Low | -20% |
| 2 | Irvine Contracting Limited Liability Company | $905,869 | +10% | -13% |
| 3 | M & M Services Co Inc | $1,061,051 | +29% | +2.0% |
| 4 | Jave LLC | $1,093,954 | +33% | +5.0% |
Engineer's estimate: $1,038,013.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kay & Kay Contracting LLC | 2. Irvine Contracting Limited Liability Company | 3. M & M Services Co Inc | 4. Jave LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Delineator for guardrail BI directional white | EACH A | 10 | $14.30 | $14.30 | $15.00 | $15.02 |
| 0020 | Embankment in place | CUYD A | 390 | $54.50 | $51.00 | $134.00 | $72.80 |
| 0030 | Guardrail terminal section no 1 | EACH A | 1 | $75.43 | $75.43 | $80.00 | $79.20 |
| 0040 | Guardrail end treatment type 7 | EACH A | 3 | $1,913.69 | $1,913.69 | $2,400.00 | $2,009.37 |
| 0050 | Right-of-way monument type 1 | EACH A | 7 | $250.00 | $150.00 | $150.00 | $152.49 |
| 0060 | Channel lining class II | TON A | 100 | $62.50 | $61.00 | $65.00 | $96.20 |
| 0070 | Temporary signs | SQFT A | 200 | $16.96 | $16.00 | $15.00 | $16.80 |
| 0080 | Edge key | LF A | 51 | $60.00 | $60.00 | $10.00 | $63.00 |
| 0090 | Maintain & control traffic | LS A | 1 | $17,650 | $8,500.00 | $50,000 | $2,625.00 |
| 0100 | Staking | LS A | 1 | $4,300.00 | $5,000.00 | $15,000 | $4,550.00 |
| 0110 | Conc barrier wall type 9T | LF A | 300 | $90.00 | $60.00 | $25.00 | $122.20 |
| 0120 | Bridge overlay approach pavement | SQYD A | 875 | $50.00 | $60.00 | $125.00 | $55.17 |
| 0130 | Temp signal multi phase | EACH A | 1 | $18,603 | $25,000 | $19,000 | $25,200 |
| 0140 | Sawcut pavement | LF A | 193 | $10.80 | $6.00 | $6.00 | $9.75 |
| 0150 | Longitudinal edge key | LF A | 193 | $30.00 | $30.00 | $15.00 | $39.00 |
| 0160 | Erosion control | LS A | 1 | $3,200.00 | $8,000.00 | $14,500 | $10,725 |
| 0170 | G/R steel W beam-S face (7 FT post) | LF A | 225 | $32.45 | $32.45 | $35.00 | $34.07 |
| 0180 | Pave mark temp paint stop bar-24 in | LF A | 36 | $22.43 | $25.00 | $25.00 | $43.05 |
| 0190 | Structure granular backfill | CUYD A | 453 | $73.50 | $100.00 | $70.00 | $117.00 |
| 0200 | Guardrail-steel W beam-S face A | LF A | 100 | $53.31 | $53.31 | $48.00 | $55.98 |
| 0210 | Armored edge for concrete | LF A | 56 | $96.00 | $100.00 | $105.00 | $140.40 |
| 0220 | Foundation preparation | LS A | 1 | $51,900 | $51,400 | $39,000 | $40,495 |
| 0230 | Cyclopean stone rip rap | TON A | 348 | $61.50 | $59.00 | $98.00 | $75.40 |
| 0240 | Test piles | LF A | 42 | $153.50 | $150.00 | $425.00 | $260.00 |
| 0250 | Pre-drilling for piles | LF A | 156 | $320.00 | $558.00 | $350.00 | $603.20 |
| 0260 | Piles-steel HP14X89 | LF A | 241 | $171.50 | $119.00 | $225.00 | $247.00 |
| 0270 | Concrete-class A | CUYD A | 99.20 | $982.00 | $1,000.00 | $1,250.00 | $1,758.90 |
| 0280 | Concrete-class AA | CUYD A | 37.80 | $1,540.00 | $1,800.00 | $1,580.00 | $2,319.20 |
| 0290 | Mechanical reinf coupler #5 epoxy coated | EACH A | 56 | $112.00 | $52.00 | $145.00 | $57.20 |
| 0300 | Steel reinforcement-epoxy coated | LB A | 14,238 | $2.00 | $2.35 | $2.25 | $2.59 |
| 0310 | Remove superstructure | LS A | 1 | $31,900 | $40,000 | $58,000 | $22,890 |
| 0320 | Precast PC box beam CB21-48 | LF A | 392 | $306.50 | $363.00 | $335.00 | $387.40 |
| 0330 | Concrete sealing | SQFT A | 2,445 | $2.00 | $2.50 | $3.50 | $2.60 |
| 0340 | Mechanical reinf coupler #8-epoxy coated | EACH A | 48 | $181.00 | $125.00 | $178.00 | $130.00 |
| 0350 | Rail system type T631 | LF A | 54 | $250.32 | $250.32 | $265.00 | $291.72 |
| 0360 | Deep beam bridge guardrail | LF A | 100 | $556.34 | $556.34 | $580.00 | $700.38 |
| 0370 | Mobilization for concrete surf treatment | LS A | 1 | $956.50 | $3,000.00 | $1,400.00 | $6,110.00 |
| 0380 | Demobilization | LS A | 1 | $12,199 | $14,099 | $15,918 | $16,167 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.