GRADE & DRAIN WITH ASPHALT SURFACE AA HIGHWAY (KY 9). Let by Kentucky Transportation Cabinet on January 23, 2025, Lewis, District 9. 3 bids received; low bid $695,225 by Rame Contracting LLC, -24% against the engineer's estimate of $919,632.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 JAN 2025
- Pay items
- 52
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Rame Contracting LLC | $695,225 | Low | -24% |
| 2 | Walker Construction & Materials LLC | $808,889 | +16% | -12% |
| 3 | Eaton Asphalt Paving Co Inc | $882,488 | +27% | -4.0% |
Engineer's estimate: $919,632.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rame Contracting LLC | 2. Walker Construction & Materials LLC | 3. Eaton Asphalt Paving Co Inc |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 2,031 | $42.00 | $45.00 | $45.00 |
| 0020 | Leveling & wedging PG64-22 | TON A | 36 | $95.00 | $95.00 | $190.00 |
| 0030 | CL3 asph base 1.00D PG64-22 | TON A | 1,737 | $112.00 | $115.00 | $110.00 |
| 0040 | CL3 asph surf 0.38B PG64-22 | TON A | 851 | $92.00 | $95.00 | $150.00 |
| 0050 | Edge key | LF A | 122 | $18.00 | $18.00 | $36.00 |
| 0055 | Mobilization for mill & text | LS A | 1 | $2,500.00 | $2,500.00 | $3,850.00 |
| 0060 | Asphalt pave milling & texturing | TON A | 115 | $29.00 | $29.00 | $48.00 |
| 0070 | Sawcut pavement | LF A | 3,693 | $0.05 | $0.50 | $3.00 |
| 0080 | Shoulder milling/trenching | SQYD A | 3,455 | $9.90 | $11.00 | $17.60 |
| 0090 | Longitudinal edge key | LF A | 3,693 | $1.40 | $0.50 | $2.00 |
| 0100 | Asphalt material for tack non-tracking | TON A | 4.58 | $800.00 | $800.00 | $1.00 |
| 0110 | Temp ditch | LF A | 987 | $0.05 | $0.25 | $2.00 |
| 0120 | Clean temp ditch | LF A | 494 | $0.05 | $0.10 | $1.00 |
| 0130 | Embankment in place | CUYD A | 8,189 | $21.50 | $24.00 | $25.00 |
| 0140 | Water | MGAL A | 19 | $0.01 | $1.00 | $10.00 |
| 0150 | Maintain & control traffic | LS A | 1 | $9,500.00 | $70,111 | $61,040 |
| 0160 | Portable changeable message sign | EACH A | 2 | $1,550.00 | $2,000.00 | $1,250.00 |
| 0170 | Shoulder rumble strips | LF A | 3,292 | $1.05 | $1.15 | $1.05 |
| 0180 | Temp silt fence | LF A | 987 | $3.00 | $4.00 | $3.00 |
| 0190 | Silt trap type A | EACH A | 4 | $200.00 | $125.00 | $200.00 |
| 0200 | Silt trap type B | EACH A | 4 | $200.00 | $125.00 | $200.00 |
| 0210 | Silt trap type C | EACH A | 4 | $250.00 | $125.00 | $200.00 |
| 0220 | Clean silt trap type A | EACH A | 4 | $5.00 | $25.00 | $100.00 |
| 0230 | Clean silt trap type B | EACH A | 4 | $5.00 | $25.00 | $100.00 |
| 0240 | Clean silt trap type C | EACH A | 4 | $5.00 | $25.00 | $100.00 |
| 0250 | Staking | LS A | 1 | $5,000.00 | $8,500.00 | $15,000 |
| 0260 | Temp mulch | SQYD A | 6,636 | $0.39 | $0.39 | $0.41 |
| 0270 | Temp seeding and protection | SQYD A | 4,977 | $0.44 | $0.44 | $0.45 |
| 0280 | Initial fertilizer | TON A | 0.51 | $1,800.00 | $1,800.00 | $1,550.00 |
| 0290 | Maintenance fertilizer | TON A | 0.31 | $1,800.00 | $1,800.00 | $1,550.00 |
| 0300 | Seeding and protection | SQYD A | 9,954 | $1.50 | $1.50 | $0.49 |
| 0310 | Agricultural limestone | TON A | 6.20 | $85.00 | $85.00 | $100.00 |
| 0320 | Pave striping-temp paint-6 in | LF A | 14,931 | $0.26 | $0.26 | $0.26 |
| 0330 | Pave striping-thermo-6 in W | LF A | 4,336 | $1.25 | $1.25 | $1.25 |
| 0340 | Pave striping-thermo-6 in Y | LF A | 6,098 | $1.25 | $1.25 | $1.25 |
| 0350 | Pave striping-thermo-12 in Y | LF A | 19 | $3.00 | $3.00 | $3.00 |
| 0360 | Pave marking-thermo stop bar-24IN | LF A | 24 | $18.00 | $18.00 | $18.00 |
| 0370 | Pave marking-thermo cross-hatch | SQFT A | 1,138 | $3.00 | $3.00 | $3.00 |
| 0380 | Pave marking-thermo STR arrow | EACH A | 4 | $105.00 | $105.00 | $105.00 |
| 0390 | Pave marking-thermo curv arrow | EACH A | 10 | $125.00 | $125.00 | $125.00 |
| 0400 | Inlaid pavement marker-MW | EACH A | 18 | $38.00 | $38.00 | $38.00 |
| 0410 | Inlaid pavement marker-by | EACH A | 76 | $38.00 | $38.00 | $38.00 |
| 0420 | Centerline rumble strips | LF A | 2,573 | $1.15 | $1.15 | $1.20 |
| 0430 | Water blasting existing stripe | LF A | 7,973 | $0.65 | $0.65 | $0.65 |
| 0440 | Entrance pipe-15 in | LF A | 5 | $300.00 | $500.00 | $375.00 |
| 0450 | Culvert pipe-18 in | LF A | 23 | $245.00 | $280.00 | $400.00 |
| 0460 | Sloped box outlet type 1-18 in | EACH A | 1 | $3,900.00 | $6,000.00 | $3,500.00 |
| 0470 | Remove headwall | EACH A | 1 | $150.00 | $900.00 | $500.00 |
| 0480 | Erosion control blanket | SQYD A | 46 | $12.75 | $12.75 | $2.00 |
| 0490 | Temporary signs | SQFT A | 169 | $4.90 | $15.00 | $5.00 |
| 0500 | Remove sign | EACH A | 16 | $50.00 | $250.00 | $77.00 |
| 0510 | Demobilization | LS A | 1 | $10,275 | $12,201 | $13,240 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.