KYTC contract 25-4202 bid tabulation
GRADE & DRAIN WITH ASPHALT SURFACE US HIGHWAY 68 (US 68). Let by Kentucky Transportation Cabinet on March 20, 2025, Mccracken, Marshall, District 1. 2 bids received; low bid $1,196,089 by Jim Smith Contracting Company LLC, -12% against the engineer's estimate of $1,361,726.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 MAR 2025
- Pay items
- 47
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jim Smith Contracting Company LLC | $1,196,089 | Low | -12% |
| 2 | Hal Coffey Contracting LLC | $1,370,223 | +15% | +1.0% |
Engineer's estimate: $1,361,726.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jim Smith Contracting Company LLC | 2. Hal Coffey Contracting LLC |
|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A | 39 | $206.13 | $185.00 |
| 0020 | CL2 asph surf 0.38D PG64-22 | TON A | 119 | $206.06 | $185.00 |
| 0030 | Asphalt material for tack | TON A | 0.81 | $1,169.63 | $1,000.00 |
| 0040 | Mobilization for mill & text | LS A | 1 | $2,210.95 | $2,000.00 |
| 0050 | Asphalt pave milling & texturing | TON A | 45 | $274.10 | $225.00 |
| 0060 | Delineator for guardrail BI directional white | EACH A | 9 | $16.45 | $16.45 |
| 0070 | Temp ditch | LF A | 6,480 | $0.40 | $0.75 |
| 0080 | Clean temp ditch | LF A | 3,240 | $0.40 | $0.75 |
| 0090 | Guardrail-steel W beam-S face | LF A | 437.50 | $35.58 | $35.58 |
| 0100 | Guardrail end treatment type 1 | EACH A | 2 | $3,757.46 | $3,757.46 |
| 0110 | Remove trees or stumps | EACH A | 48 | $3,149.05 | $1,670.00 |
| 0120 | Maintain & control traffic | LS A | 1 | $83,845 | $255,000 |
| 0130 | Maintain & control traffic | LS A | 1 | $7,322.08 | $95,000 |
| 0140 | Portable changeable message sign | EACH A | 2 | $2,987.22 | $5,500.00 |
| 0150 | Edgeline rumble strips | LF A | 1,300 | $3.60 | $3.50 |
| 0160 | Temp silt fence | LF A | 6,480 | $2.75 | $1.50 |
| 0170 | Silt trap type A | EACH A | 6 | $238.22 | $300.00 |
| 0180 | Silt trap type B | EACH A | 6 | $241.74 | $300.00 |
| 0190 | Silt trap type C | EACH A | 6 | $241.74 | $75.00 |
| 0200 | Clean silt trap type A | EACH A | 6 | $96.01 | $50.00 |
| 0210 | Clean silt trap type B | EACH A | 6 | $96.01 | $50.00 |
| 0220 | Clean silt trap type C | EACH A | 6 | $96.01 | $50.00 |
| 0230 | Staking | LS A | 1 | $20,700 | $55,000 |
| 0240 | Staking | LS A | 1 | $8,163.31 | $24,000 |
| 0250 | Arrow panel | EACH A | 2 | $4,197.42 | $1,500.00 |
| 0260 | Trim & remove trees & brush | LF A | 26,505 | $15.85 | $11.35 |
| 0270 | Erosion control blanket | SQYD A | 60 | $4.25 | $5.00 |
| 0280 | Temp mulch | SQYD A | 17,747 | $0.45 | $0.10 |
| 0290 | Temp seeding and protection | SQYD A | 13,310 | $0.65 | $0.15 |
| 0300 | Initial fertilizer | TON A | 1.40 | $1,200.00 | $250.00 |
| 0310 | Maintenance fertilizer | TON A | 0.80 | $1,200.00 | $800.00 |
| 0320 | Seeding and protection | SQYD A | 26,620 | $0.65 | $0.75 |
| 0330 | Agricultural limestone | TON A | 16.50 | $900.00 | $115.00 |
| 0340 | Pave striping-perm paint-4 in | LF A | 2,600 | $0.75 | $0.75 |
| 0350 | Roadside regrading | LF A | 630 | $50.17 | $155.00 |
| 0360 | Culvert pipe-18 in | LF A | 18 | $459.98 | $700.00 |
| 0370 | Culvert pipe-24 in | LF A | 25 | $375.37 | $750.00 |
| 0380 | Fittings | EACH A | 4 | $1,886.52 | $4,500.00 |
| 0390 | Sloped and mitered headwall-18 in | EACH A | 2 | $8,723.96 | $10,000 |
| 0400 | Sloped and mitered headwall-24 in | EACH A | 2 | $8,723.96 | $10,000 |
| 0410 | Temporary signs | SQFT A | 300 | $31.00 | $12.00 |
| 0420 | SBM alum sheet signs .080 in | SQFT A | 1,303.30 | $47.28 | $47.28 |
| 0430 | SBM alum sheet signs .125 in | SQFT A | 201.24 | $73.69 | $73.69 |
| 0440 | Steel post type 1 | LF A | 3,185 | $27.49 | $27.49 |
| 0450 | Remove sign | EACH A | 232 | $140.38 | $140.38 |
| 0460 | Barcode sign inventory | EACH A | 380 | $46.79 | $46.79 |
| 0470 | Demobilization | LS A | 1 | $17,700 | $20,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.