KYTC contract 25-5386 bid tabulation
BRIDGE REPLACEMENT CS 1041. Let by Kentucky Transportation Cabinet on August 21, 2025. 3 bids received; low bid $2,436,560 by Irvine Contracting Limited Liability Company, -29% against the engineer's estimate of $3,453,566.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 21 AUG 2025
- Pay items
- 49
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Irvine Contracting Limited Liability Company | $2,436,560 | Low | -29% |
| 2 | Bush & Burchett Inc | $2,883,780 | +18% | -16% |
| 3 | Jave LLC | $2,995,675 | +23% | -13% |
Engineer's estimate: $3,453,566.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Irvine Contracting Limited Liability Company | 2. Bush & Burchett Inc | 3. Jave LLC |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 329 | $53.70 | $53.70 | $54.24 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A A | 252 | $229.85 | $229.85 | $232.15 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 47 | $265.75 | $265.75 | $268.41 |
| 0040 | Asphalt material for tack non-tracking | TON A A | 0.23 | $10.00 | $10.00 | $10.10 |
| 0050 | Standard header curb | LF A A | 142 | $37.00 | $50.00 | $61.74 |
| 0060 | Delineator for guardrail BI directional white | EACH A A | 4 | $21.38 | $21.38 | $21.59 |
| 0070 | Barricade-type III | EACH A A | 4 | $50.00 | $200.00 | $101.00 |
| 0080 | Remove pavement | SQYD A A | 922 | $2.00 | $10.00 | $10.10 |
| 0090 | Embankment in place | CUYD A A | 494 | $26.00 | $50.00 | $55.55 |
| 0100 | Guardrail-steel W beam-S face | LF A A | 237.50 | $46.16 | $46.16 | $46.62 |
| 0110 | Guardrail terminal section no 1 | EACH A A | 4 | $104.42 | $104.42 | $105.46 |
| 0120 | Remove guardrail | LF A A | 148 | $7.23 | $7.23 | $7.30 |
| 0130 | Right-of-way monument type 1 | EACH A A | 7 | $200.00 | $219.93 | $222.13 |
| 0140 | Right-of-way monument type 1A | EACH A A | 3 | $200.00 | $219.93 | $222.13 |
| 0150 | Witness post | EACH A A | 2 | $200.00 | $198.08 | $200.06 |
| 0160 | Clearing and grubbing | LS A A | 1 | $22,000 | $60,000 | $36,879 |
| 0170 | Temporary signs | SQFT A A | 70 | $18.00 | $17.00 | $10.10 |
| 0180 | Edge key | LF A A | 110 | $42.15 | $42.15 | $42.57 |
| 0190 | Maintain & control traffic | LS A A | 1 | $8,400.00 | $35,000 | $9,292.00 |
| 0200 | Portable changeable message sign | EACH A A | 2 | $3,710.00 | $1,000.00 | $7,494.20 |
| 0210 | Sidewalk-4 in concrete | SQYD A A | 246 | $75.00 | $65.00 | $72.96 |
| 0220 | Staking | LS A A | 1 | $4,000.00 | $10,000 | $17,399 |
| 0230 | Remove structure | LS A A | 1 | $50,000 | $75,000 | $64,943 |
| 0240 | Pave striping-thermo-4 in Y | LF A A | 604 | $4.50 | $5.00 | $5.89 |
| 0250 | Foundation preparation | LS A A | 1 | $100,000 | $200,000 | $218,888 |
| 0260 | Erosion control | LS A A | 1 | $8,000.00 | $10,000 | $5,050.00 |
| 0270 | Thrie beam guardrail transition TL-2 | EACH A A | 4 | $2,530.27 | $2,530.27 | $2,555.57 |
| 0280 | Culvert pipe-15 in | LF A A | 21 | $35.00 | $100.00 | $95.95 |
| 0290 | Pipe culvert headwall-15 in | EACH A A | 1 | $1,200.00 | $3,500.00 | $3,535.00 |
| 0300 | Curb box inlet type B | EACH A A | 1 | $8,500.00 | $8,000.00 | $6,060.00 |
| 0310 | Fabric-geotextile class 2 for pipe | SQYD A A | 27 | $2.00 | $2.00 | $2.00 |
| 0320 | Erosion control blanket | SQYD A A | 43 | $10.34 | $10.34 | $10.44 |
| 0330 | Structure granular backfill | CUYD A A | 185 | $80.00 | $100.00 | $114.50 |
| 0340 | Armored edge for concrete | LF A A | 69 | $75.00 | $100.00 | $124.60 |
| 0350 | Structure excav-solid rock | CUYD A A | 78 | $300.00 | $100.00 | $205.42 |
| 0360 | Cyclopean stone rip rap | TON A A | 525 | $50.00 | $60.00 | $80.82 |
| 0370 | Test piles | LF A A | 61 | $127.00 | $200.00 | $212.15 |
| 0380 | Piles-steel HP12X53 | LF A A | 306 | $127.00 | $90.00 | $212.15 |
| 0390 | Pile points-12 in | EACH A A | 14 | $155.00 | $150.00 | $148.73 |
| 0400 | Concrete-class A | CUYD A A | 242 | $1,000.00 | $1,250.00 | $1,380.68 |
| 0410 | Concrete-class AA | CUYD A A | 390 | $1,100.00 | $1,350.00 | $1,070.87 |
| 0420 | Steel reinforcement | LB A A | 34,500 | $2.00 | $1.75 | $2.44 |
| 0430 | Steel reinforcement-epoxy coated | LB A A | 120,000 | $1.90 | $1.75 | $2.05 |
| 0440 | Precast PC I beam type 4 | LF A A | 1,198 | $574.14 | $550.00 | $554.52 |
| 0450 | Concrete sealing | SQFT A A | 25,500 | $1.25 | $1.50 | $2.65 |
| 0460 | Rail system type C411 | LF A A | 607 | $249.00 | $375.00 | $418.16 |
| 0470 | Mobilization | LS A A | 1 | $69,000 | $125,000 | $139,569 |
| 0480 | Demobilization | LS A A | 1 | $37,219 | $41,000 | $42,208 |
| 0490 | Mobilization for concrete surf treatment | LS A A | 1 | $2,000.00 | $1,000.00 | $11,225 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of August 21, 2025. Compiled by Mirage Metrics.