KYTC contract 25-5394 bid tabulation
BRIDGE REPLACEMENT VAN CLEAVE ROAD. Let by Kentucky Transportation Cabinet on November 20, 2025. 4 bids received; low bid $646,520 by Jim Smith Contracting Company LLC, -26% against the engineer's estimate of $877,339.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 20 NOV 2025
- Pay items
- 36
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jim Smith Contracting Company LLC | $646,520 | Low | -26% |
| 2 | Youngblood Excavating & Contracting LLC | $697,580 | +8.0% | -20% |
| 3 | Jave LLC | $700,640 | +8.0% | -20% |
| 4 | Hal Coffey Contracting LLC | $965,233 | +49% | +10% |
Engineer's estimate: $877,339.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jim Smith Contracting Company LLC | 2. Youngblood Excavating & Contracting LLC | 3. Jave LLC | 4. Hal Coffey Contracting LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 634 | $39.93 | $50.00 | $63.63 | $45.00 |
| 0020 | Asphalt seal aggregate | TON A A | 4 | $506.45 | $1,500.00 | $1,767.50 | $975.00 |
| 0030 | Asphalt seal coat | TON A A | 1 | $1,116.57 | $875.00 | $3,535.00 | $2,500.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 252 | $150.00 | $165.00 | $176.75 | $200.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 38 | $250.00 | $200.00 | $277.75 | $200.00 |
| 0060 | Asphalt material for tack | TON A A | 1 | $850.00 | $1,000.00 | $883.75 | $950.00 |
| 0070 | Delineator for guardrail BI directional white | EACH A A | 10 | $16.61 | $15.00 | $16.78 | $16.61 |
| 0080 | Barricade-type III | EACH A A | 8 | $431.97 | $200.00 | $80.80 | $500.00 |
| 0090 | Granular embankment | CUYD A A | 45 | $76.37 | $58.00 | $152.51 | $125.00 |
| 0100 | Embankment in place | CUYD A A | 178 | $91.89 | $35.00 | $103.02 | $130.00 |
| 0110 | Guardrail-steel W beam-S face | LF A A | 212.50 | $33.39 | $125.00 | $33.72 | $33.39 |
| 0120 | Guardrail end treatment type 1 | EACH A A | 4 | $3,608.29 | $6,000.00 | $3,644.28 | $3,608.29 |
| 0130 | Clearing and grubbing | LS A A | 1 | $6,640.37 | $4,500.00 | $21,119 | $55,000 |
| 0140 | Temporary signs | SQFT A A | 216 | $16.31 | $25.00 | $9.09 | $24.00 |
| 0150 | Edge key | LF A A | 38 | $100.00 | $150.00 | $126.25 | $250.00 |
| 0160 | Maintain & control traffic | LS A A | 1 | $4,750.88 | $3,500.00 | $2,020.00 | $25,000 |
| 0170 | Portable changeable message sign | EACH A A | 2 | $7.39 | $2,400.00 | $2,783.56 | $6,500.00 |
| 0180 | Staking | LS A A | 1 | $1,500.00 | $6,500.00 | $5,050.00 | $8,000.00 |
| 0190 | Erosion control | LS A A | 1 | $3,000.00 | $4,500.00 | $7,676.00 | $14,000 |
| 0200 | G/R steel W beam-S face (7 FT post) | LF A A | 62.50 | $35.43 | $130.00 | $35.78 | $35.43 |
| 0210 | Structure granular backfill | CUYD A A | 79 | $76.27 | $63.00 | $112.11 | $200.00 |
| 0220 | Remove structure | LS A A | 1 | $39,780 | $12,000 | $26,018 | $55,000 |
| 0230 | Armored edge for concrete | LF A A | 49 | $58.18 | $90.00 | $122.21 | $150.00 |
| 0240 | Foundation preparation | LS A A | 1 | $20,476 | $7,500.00 | $5,130.80 | $25,000 |
| 0250 | Cyclopean stone rip rap | TON A A | 400 | $39.05 | $52.00 | $69.39 | $65.00 |
| 0260 | Test piles | LF A A | 208 | $212.28 | $135.00 | $91.91 | $325.00 |
| 0270 | Piles-steel HP12X53 | LF A A | 752 | $72.98 | $130.00 | $130.00 | $135.00 |
| 0280 | Concrete-class A | CUYD A A | 32 | $1,017.36 | $1,300.00 | $1,158.47 | $1,900.00 |
| 0290 | Concrete-class AA | CUYD A A | 30 | $2,945.46 | $2,700.00 | $1,419.05 | $1,900.00 |
| 0300 | Steel reinforcement | LB A A | 2,950 | $1.74 | $3.00 | $2.94 | $4.50 |
| 0310 | Steel reinforcement-epoxy coated | LB A A | 2,800 | $2.33 | $3.70 | $2.25 | $4.50 |
| 0320 | Precast PC box beam CB21-48 | LF A A | 336 | $422.00 | $390.00 | $485.00 | $525.00 |
| 0330 | Concrete sealing | SQFT A A | 2,190 | $2.50 | $3.00 | $1.55 | $5.00 |
| 0340 | Rail system side mounted MGS | LF A A | 112 | $220.96 | $275.00 | $254.70 | $350.00 |
| 0350 | Mobilization for concrete surf treatment | LS A A | 1 | $1,591.36 | $8,500.00 | $5,050.00 | $1,500.00 |
| 0360 | Demobilization | LS A A | 1 | $9,555.00 | $10,400 | $10,354 | $15,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of November 20, 2025. Compiled by Mirage Metrics.