KYTC contract 26-2165 bid tabulation
ASPHALT RESURFACING LAGRANGE ROAD (KY 146). Let by Kentucky Transportation Cabinet on March 26, 2026. 6 bids received; low bid $911,500 by Louisville Paving Company Inc, -24% against the engineer's estimate of $1,206,443.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 31
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Louisville Paving Company Inc | $911,500 | Low | -24% |
| 2 | Hall Contracting of Kentucky Inc | $927,000 | +2.0% | -23% |
| 3 | E & B Paving LLC | $962,131 | +6.0% | -20% |
| 4 | Hinkle Contracting Company LLC | $1,014,597 | +11% | -16% |
| 5 | Mac Construction & Excavating Inc | $1,027,452 | +13% | -15% |
| 6 | Flynn Brothers Contracting Inc | $1,062,724 | +17% | -12% |
Engineer's estimate: $1,206,443.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Louisville Paving Company Inc | 2. Hall Contracting of Kentucky Inc | 3. E & B Paving LLC | 4. Hinkle Contracting Company LLC | 5. Mac Construction & Excavating Inc | 6. Flynn Brothers Contracting Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Leveling & wedging PG64-22 | TON A A | 1,040 | $82.00 | $76.00 | $76.00 | $92.25 | $87.00 | $79.45 |
| 0020 | CL3 asph surf 0.38B PG64-22 | TON A A | 6,715 | $78.00 | $71.00 | $76.00 | $92.25 | $80.00 | $79.45 |
| 0030 | Adjust manhole frame to grade | EACH A A | 1 | $600.00 | $200.00 | $1,500.00 | $530.00 | $125.00 | $300.00 |
| 0040 | Temporary signs | SQFT A A | 710 | $4.00 | $4.00 | $7.00 | $0.01 | $7.42 | $4.60 |
| 0050 | Maintain & control traffic | LS A A | 1 | $61,500 | $41,996 | $76,317 | $11,000 | $25,000 | $84,235 |
| 0060 | Portable changeable message sign | EACH A A | 2 | $600.00 | $600.00 | $742.00 | $550.00 | $742.00 | $636.00 |
| 0070 | Mobilization for mill & text | LS A A | 1 | $2,500.00 | $16,500 | $30,000 | $3,500.00 | $2,500.00 | $1,335.00 |
| 0080 | Asphalt pave milling & texturing | TON A A | 6,715 | $7.00 | $13.00 | $12.00 | $10.50 | $18.71 | $19.80 |
| 0090 | Edgeline rumble strips | LF A A | 48,500 | $0.17 | $0.27 | $0.27 | $0.18 | $0.16 | $0.16 |
| 0100 | Arrow panel | EACH A A | 2 | $400.00 | $400.00 | $100.00 | $505.00 | $504.00 | $424.00 |
| 0110 | Base failure repair | SQYD A A | 1,000 | $37.00 | $71.00 | $40.00 | $67.00 | $69.00 | $69.00 |
| 0120 | Pave striping-temp paint-4 in | LF A A | 90,000 | $0.18 | $0.12 | $0.01 | $0.12 | $0.21 | $0.21 |
| 0130 | Pave striping-perm paint-6 in | LF A A | 110,600 | $0.26 | $0.21 | $0.21 | $0.21 | $0.24 | $0.24 |
| 0140 | Pave striping-thermo-12 in W | LF A A | 425 | $2.25 | $2.50 | $2.50 | $2.50 | $3.00 | $3.00 |
| 0150 | Pave striping-thermo-12 in Y | LF A A | 110 | $2.25 | $3.00 | $3.00 | $3.00 | $5.00 | $5.00 |
| 0160 | Pave marking-thermo R 6 FT | EACH A A | 8 | $125.00 | $165.00 | $165.00 | $165.00 | $85.00 | $85.00 |
| 0170 | Pave marking-R/R xbucks 16 in | LF A A | 176 | $8.00 | $11.00 | $11.00 | $11.00 | $12.00 | $12.00 |
| 0180 | Pave marking-thermo X-walk-6 in | LF A A | 472 | $3.25 | $3.00 | $3.00 | $3.00 | $3.50 | $3.50 |
| 0190 | Pave marking-thermo stop bar-24IN | LF A A | 396 | $9.25 | $10.00 | $10.00 | $10.00 | $12.95 | $12.95 |
| 0200 | Pave marking-thermo cross-hatch | SQFT A A | 1,105 | $6.50 | $10.00 | $10.00 | $10.00 | $4.95 | $4.95 |
| 0210 | Pave marking-thermo curv arrow | EACH A A | 49 | $95.00 | $100.00 | $100.00 | $100.00 | $120.00 | $120.00 |
| 0220 | Remove pavement marker type V | EACH A A | 150 | $6.75 | $6.75 | $6.75 | $8.22 | $6.75 | $5.00 |
| 0230 | Fuel adjustment | DOLL A A | 10,452 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0240 | Asphalt adjustment | DOLL A A | 26,253 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0250 | Law enforcement officer | HOUR A A | 140 | $85.00 | $95.00 | $80.00 | $80.00 | $90.00 | $85.00 |
| 0260 | Pave mark thermo cone cap-solid yellow | SQFT A A | 200 | $5.85 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 0270 | Pave marking-thermo dotted lane exten | LF A A | 100 | $6.25 | $4.00 | $4.00 | $5.00 | $3.50 | $3.50 |
| 0280 | Asphalt material for tack non-tracking | TON A A | 43 | $0.01 | $0.01 | $1.00 | $10.00 | $0.01 | $0.01 |
| 0290 | Install radar presence detector type A | EACH A A | 8 | $904.00 | $904.00 | $904.00 | $904.00 | $904.00 | $904.00 |
| 0300 | Install radar advance detector type B | EACH A A | 3 | $904.00 | $904.00 | $904.00 | $904.00 | $904.00 | $904.00 |
| 0310 | Demobilization | LS A A | 1 | $13,801 | $13,906 | $14,200 | $14,801 | $32,186 | $16,776 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.