KYTC contract 26-5403 bid tabulation
BRIDGE REPLACEMENT US 60 EB OVER CLEAR CREEK. Let by Kentucky Transportation Cabinet on January 29, 2026. 5 bids received; low bid $2,979,490 by E & B Paving LLC, -7.4% against the engineer's estimate of $3,217,998.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 29 JAN 2026
- Pay items
- 72
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E & B Paving LLC | $2,979,490 | Low | -7.0% |
| 2 | Hinkle Construction Services LLC | $3,099,854 | +4.0% | -4.0% |
| 3 | Hall Contracting of Kentucky Inc | $3,450,000 | +16% | +7.0% |
| 4 | Orders Construction Company Inc | $4,093,280 | +37% | +27% |
| 5 | Haydon Bridge Company Inc | $4,499,869 | +51% | +40% |
Engineer's estimate: $3,217,998.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Hinkle Construction Services LLC | 3. Hall Contracting of Kentucky Inc | 4. Orders Construction Company Inc | 5. Haydon Bridge Company Inc |
|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 953 | $75.00 | $65.00 | $70.00 | $68.00 | $85.00 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A A | 543 | $100.00 | $123.00 | $120.00 | $130.00 | $132.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 108 | $259.00 | $175.00 | $300.00 | $190.00 | $264.00 |
| 0040 | JPC pavement-9 in | SQYD A A | 310 | $171.35 | $217.00 | $160.00 | $260.00 | $175.00 |
| 0050 | Standard curb and gutter mod | LF A A | 640 | $55.42 | $58.00 | $75.00 | $130.00 | $90.00 |
| 0060 | Delineator for guardrail mono directional white | EACH A A | 2 | $16.64 | $10.50 | $17.00 | $19.00 | $20.00 |
| 0070 | Delineator for guardrail mono directional yello | EACH A A | 2 | $16.64 | $10.50 | $17.00 | $19.00 | $20.00 |
| 0080 | Delineator for barrier - white | EACH A A | 2 | $20.35 | $15.80 | $21.00 | $23.00 | $25.00 |
| 0090 | Delineator for barrier - yellow | EACH A A | 2 | $20.35 | $15.80 | $21.00 | $23.00 | $25.00 |
| 0100 | Barricade-type III | EACH A A | 12 | $185.50 | $150.00 | $110.00 | $200.00 | $200.00 |
| 0110 | Cem conc ent pavement-8 in | SQYD A A | 404 | $129.27 | $136.00 | $120.00 | $240.00 | $175.00 |
| 0120 | Roadway excavation | CUYD A A | 649 | $156.00 | $76.00 | $60.00 | $85.00 | $88.00 |
| 0130 | Granular embankment | CUYD A A | 95 | $145.00 | $170.00 | $110.00 | $225.00 | $105.00 |
| 0140 | Guardrail-steel W beam-S face | LF A A | 62.50 | $62.13 | $74.00 | $70.00 | $80.00 | $71.00 |
| 0150 | Guardrail terminal section no 1 | EACH A A | 2 | $101.57 | $105.00 | $102.00 | $130.00 | $115.00 |
| 0160 | Right-of-way monument type 1 | EACH A A | 8 | $190.11 | $160.00 | $200.00 | $110.00 | $265.00 |
| 0170 | Witness post | EACH A A | 8 | $171.56 | $127.00 | $172.00 | $190.00 | $265.00 |
| 0180 | Channel lining class II | TON A A | 26 | $110.00 | $110.00 | $85.00 | $180.00 | $100.00 |
| 0190 | Clearing and grubbing | LS A A | 1 | $59,590 | $95,070 | $50,000 | $55,000 | $265,000 |
| 0200 | Temporary signs | SQFT A A | 378 | $7.42 | $8.00 | $7.00 | $7.90 | $12.00 |
| 0210 | Edge key | LF A A | 38 | $160.00 | $27.50 | $60.00 | $29.00 | $75.00 |
| 0220 | Fabric-geotextile class 1 | SQYD A A | 49 | $10.00 | $6.00 | $5.00 | $24.00 | $5.00 |
| 0230 | Maintain & control traffic | LS A A | 1 | $23,000 | $16,700 | $100,000 | $55,000 | $75,000 |
| 0240 | Portable changeable message sign | EACH A A | 10 | $2,650.00 | $4,330.00 | $5,100.00 | $7,100.00 | $7,500.00 |
| 0250 | Sidewalk-4 in concrete | SQYD A A | 197 | $80.15 | $85.00 | $100.00 | $240.00 | $125.00 |
| 0260 | Staking | LS A A | 1 | $55,000 | $10,130 | $30,000 | $88,000 | $40,000 |
| 0270 | Remove structure | LS A A | 1 | $155,800 | $127,635 | $230,000 | $200,000 | $235,000 |
| 0280 | Tubular markers | EACH A A | 96 | $80.00 | $70.00 | $40.00 | $43.00 | $125.00 |
| 0290 | Pave striping-perm paint-6 in | LF A A | 427 | $1.00 | $1.05 | $1.00 | $1.10 | $1.05 |
| 0300 | Pave striping-thermo-6 in W | LF A A | 2,822 | $2.00 | $2.10 | $2.00 | $2.30 | $2.25 |
| 0310 | Pave striping-thermo-6 in Y | LF A A | 637 | $2.00 | $2.10 | $2.00 | $2.30 | $2.05 |
| 0320 | Pave striping-dur TY 1-6 in W | LF A A | 3,943 | $7.25 | $7.60 | $5.00 | $8.20 | $9.50 |
| 0330 | Pave striping-dur TY 1-6 in Y | LF A A | 3,315 | $7.25 | $7.60 | $5.00 | $8.20 | $9.50 |
| 0340 | Pave striping-dur TY 1-12 in W | LF A A | 458 | $14.00 | $14.75 | $10.00 | $16.00 | $17.50 |
| 0350 | Pave marking-thermo stop bar-24IN | LF A A | 43 | $14.00 | $14.75 | $1.00 | $16.00 | $17.50 |
| 0360 | Remove-store and reinstall sign | EACH A A | 8 | $681.66 | $575.00 | $700.00 | $130.00 | $700.00 |
| 0370 | Erosion control | LS A A | 1 | $50,000 | $6,785.00 | $30,000 | $35,000 | $35,000 |
| 0380 | Wood plank fence | LF A A | 290 | $132.00 | $94.00 | $60.00 | $150.00 | $150.00 |
| 0390 | Detectable warnings | SQFT A A | 79 | $48.91 | $52.00 | $75.00 | $14.00 | $65.00 |
| 0400 | Pave mark TY 1 tape X-walk-6 in | LF A A | 124 | $8.00 | $8.40 | $5.00 | $9.00 | $9.00 |
| 0410 | Pave mark TY 1 tape -only | EACH A A | 3 | $1,200.00 | $1,263.00 | $500.00 | $1,400.00 | $1,250.00 |
| 0420 | Pave mark TY 1 tape stop bar-24 in | LF A A | 89 | $28.00 | $29.50 | $20.00 | $32.00 | $50.00 |
| 0430 | Pave mark TY 1 tape-curv arrow | EACH A A | 9 | $775.00 | $815.00 | $350.00 | $870.00 | $900.00 |
| 0440 | Yellow paint for median safety nose | SQFT A A | 48 | $5.00 | $5.25 | $5.00 | $5.60 | $6.00 |
| 0450 | Thrie beam guardrail transition TL-2 | EACH A A | 2 | $2,002.77 | $3,150.00 | $3,000.00 | $2,600.00 | $4,000.00 |
| 0460 | Storm sewer pipe-15 in | LF A A | 102 | $400.00 | $86.00 | $140.00 | $180.00 | $395.00 |
| 0470 | Storm sewer pipe-18 in | LF A A | 26 | $350.00 | $114.00 | $150.00 | $210.00 | $295.00 |
| 0480 | Pipe culvert headwall-15 in | EACH A A | 2 | $3,800.00 | $1,620.00 | $2,000.00 | $5,800.00 | $2,200.00 |
| 0490 | Pipe culvert headwall-18 in | EACH A A | 1 | $3,900.00 | $1,625.00 | $2,100.00 | $5,800.00 | $2,400.00 |
| 0500 | Curb box inlet type B | EACH A A | 3 | $12,000 | $7,300.97 | $6,200.00 | $7,300.00 | $14,000 |
| 0510 | Junction box-15 in | EACH A A | 1 | $4,200.00 | $2,250.00 | $2,500.00 | $3,900.00 | $4,680.00 |
| 0520 | Junction box-18 in | EACH A A | 1 | $4,300.00 | $2,330.00 | $2,600.00 | $3,900.00 | $6,450.00 |
| 0530 | Structure granular backfill | CUYD A A | 170 | $95.00 | $172.00 | $105.00 | $240.00 | $85.00 |
| 0540 | Armored edge for concrete | LF A A | 76 | $90.00 | $89.00 | $80.00 | $440.00 | $125.00 |
| 0550 | Foundation preparation | LS A A | 1 | $103,000 | $114,500 | $160,000 | $170,000 | $390,000 |
| 0560 | Cyclopean stone rip rap | TON A A | 760 | $78.00 | $81.00 | $110.00 | $68.00 | $80.00 |
| 0570 | Test piles | LF A A | 160 | $245.00 | $110.00 | $160.00 | $200.00 | $250.00 |
| 0580 | Pre-drilling for piles | LF A A | 529 | $217.00 | $240.00 | $425.00 | $290.00 | $250.00 |
| 0590 | Piles-steel HP12X53 | LF A A | 354 | $130.00 | $140.00 | $155.00 | $220.00 | $120.00 |
| 0600 | Piles-steel HP14X89 | LF A A | 812 | $115.00 | $150.00 | $175.00 | $180.00 | $160.00 |
| 0610 | Pile points-12 in | EACH A A | 18 | $200.00 | $150.00 | $160.00 | $440.00 | $225.00 |
| 0620 | Pile points-14 in | EACH A A | 24 | $225.00 | $185.00 | $180.00 | $500.00 | $250.00 |
| 0630 | Concrete-class A | CUYD A A | 237 | $1,400.00 | $1,360.00 | $1,600.00 | $1,600.00 | $1,750.00 |
| 0640 | Concrete-class AA | CUYD A A | 324 | $950.00 | $1,350.00 | $1,300.00 | $1,600.00 | $1,700.00 |
| 0650 | Steel reinforcement | LB A A | 17,170 | $2.00 | $1.55 | $1.50 | $2.50 | $2.00 |
| 0660 | Steel reinforcement-epoxy coated | LB A A | 63,550 | $1.85 | $1.65 | $1.60 | $2.50 | $2.00 |
| 0670 | Precast PC box beam SB27 | LF A A | 1,159 | $305.00 | $375.00 | $335.00 | $350.00 | $455.00 |
| 0680 | Concrete sealing | SQFT A A | 18,000 | $0.90 | $1.50 | $1.05 | $3.80 | $2.75 |
| 0690 | Bridge rail | LF A A | 296 | $282.00 | $470.00 | $515.00 | $810.00 | $689.00 |
| 0700 | Mobilization for concrete surf treatment | LS A A | 1 | $2,000.00 | $1,350.00 | $1,000.00 | $12,000 | $1,000.00 |
| 0710 | Mobilization | LS A A | 1 | $139,880 | $145,000 | $161,698 | $190,000 | $210,000 |
| 0720 | Demobilization | LS A A | 1 | $41,965 | $44,000 | $48,596 | $70,000 | $63,815 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 29, 2026. Compiled by Mirage Metrics.