KYTC contract 26-5406 bid tabulation

BRIDGE REPLACEMENT VARIOUS BRIDGES IN DISTRICT 12. Let by Kentucky Transportation Cabinet on February 19, 2026. 4 bids received; low bid $1,943,260 by Bush & Burchett Inc, -29% against the engineer's estimate of $2,719,556.

Owner
Kentucky Transportation Cabinet
Letting
19 FEB 2026
Pay items
98
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Bush & Burchett Inc$1,943,260Low-29%
2Central Bridge Co LLC$2,251,587+16%-17%
3Orders Construction Company Inc$2,557,157+32%-6.0%
4Hinkle Construction Services LLC$2,578,176+33%-5.0%
KYTC contract 26-5406: bids by rank

Engineer's estimate: $2,719,556.

Bid tabulation

LinePay itemUnitQuantity1. Bush & Burchett Inc2. Central Bridge Co LLC3. Orders Construction Company Inc4. Hinkle Construction Services LLC
0010Dga baseTON A A224$99.50$85.00$110.00$105.00
0020Asphalt seal aggregateTON A A5$470.00$470.00$540.00$495.00
0030Asphalt seal coatTON A A1$1,605.00$1,605.00$1,800.00$1,690.00
0040CL2 asph base 1.00D PG64-22TON A A145$340.15$340.15$390.00$355.00
0050CL2 asph surf 0.38D PG64-22TON A A29$364.10$364.10$410.00$380.00
0060Asphalt material for tackTON A A0.27$1,000.00$1,000.00$1,100.00$1,050.00
0070Delineator for guardrail BI directional whiteEACH A A13$12.00$15.24$13.00$9.30
0080Delineator for barrier wall-B/WEACH A A3$20.00$16.53$54.00$25.00
0090Barricade-type IIIEACH A A2$200.00$250.00$190.00$150.00
0100Embankment in placeCUYD A A53$100.00$150.00$150.00$110.00
0110Structure granular backfillCUYD A A317$85.00$95.00$160.00$150.00
0120Guardrail-steel W beam-S faceLF A A100$40.00$43.34$43.00$41.00
0130Guardrail terminal section no 1EACH A A2$85.00$81.18$92.00$81.00
0140Guardrail end treatment type 1EACH A A3$4,000.00$3,533.81$4,300.00$3,887.00
0150Guardrail end treatment type 7EACH A A3$2,000.00$2,011.51$2,200.00$1,905.00
0160Remove guardrailLF A A334$3.00$4.33$3.30$4.25
0170Temp guardrailLF A A300$25.00$11.54$27.00$32.00
0180Clearing and grubbingLS A A1$30,000$10,000$50,000$12,140
0190Temporary signsSQFT A A300$20.00$20.00$17.00$17.85
0200Edge keyLF A A87$55.50$55.50$63.00$58.00
0210Maintain & control trafficLS A A1$15,000$10,000$28,000$5,775.00
0220Diversions (by-pass detours)LS A A1$20,000$25,000$28,000$31,613
0230Portable changeable message signEACH A A4$1,000.00$2,800.00$9,100.00$3,615.00
0235Mobilization for mill & textLS A A1$1.00$6,520.00$5,400.00$1,575.00
0240Asphalt pave milling & texturingTON A A22$310.00$310.00$350.00$325.00
0250StakingLS A A1$5,000.00$5,000.00$45,000$6,270.00
0260Remove structureLS A A1$100,000$65,000$59,000$60,100
0270Conc barrier wall type 9TLF A A80$40.00$70.00$210.00$215.00
0280Armored edge for concreteLF A A68$125.00$90.00$390.00$85.00
0290Temp signal multi phaseEACH A A3$1.00$10,500$25,000$10,045
0300SBM alum sheet signs .080 inSQFT A A22.20$45.00$42.21$49.00$41.00
0310Steel post type 1LF A A33$35.00$35.32$38.00$25.00
0320Pave striping-temp paint-6 inLF A A464$5.00$5.00$5.40$5.25
0330Pave striping-thermo-6 in WLF A A155$10.00$10.00$11.00$10.50
0340Pave striping-thermo-6 in YLF A A114$10.00$10.00$11.00$10.50
0350Pave striping-dur TY 1-6 in WLF A A172$12.00$12.00$13.00$12.65
0360Pave striping-dur TY 1-6 in YLF A A172$12.00$12.00$13.00$12.65
0370Foundation preparationLS A A1$31,000$50,000$63,000$34,900
0380Cyclopean stone rip rapTON A A837$55.00$68.00$64.00$78.00
0390Test pilesLF A A67$200.00$175.00$220.00$115.00
0400Pre-drilling for pilesLF A A240$450.00$430.00$470.00$540.00
0410Piles-steel HP12X53LF A A343$100.00$135.00$170.00$145.00
0420Pile points-12 inEACH A A24$1.00$175.00$270.00$0.01
0430Concrete-class ACUYD A A162.60$1,250.00$1,030.00$1,400.00$1,150.00
0440Concrete-class AACUYD A A51.70$2,000.00$1,700.00$2,000.00$1,965.00
0450Steel reinforcement-epoxy coatedLB A A18,074$2.00$2.60$2.70$2.50
0460Precast PC box beam CB17-48LF A A516$450.00$470.00$390.00$440.00
0470Temporary bridgeEACH A A1$50,000$235,000$110,000$295,000
0480Object marker TY 3EACH A A3$100.00$29.45$110.00$375.00
0490Remove-store and reinstall signEACH A A2$300.00$819.91$1,100.00$565.00
0500Erosion controlLS A A1$10,000$6,200.00$18,000$5,850.00
0510Pave mark temp paint stop bar-24 inLF A A24$10.00$10.00$11.00$10.50
0520Concrete sealingSQFT A A4,650$2.00$2.10$6.20$1.90
0530Barcode sign inventoryEACH A A3$30.00$36.21$33.00$29.00
0540Rail system side mounted MGSLF A A173$215.00$213.94$250.00$240.00
0550Mobilization for concrete surf treatmentLS A A1$50.00$2,500.00$10,000$1,500.00
0560Dga baseTON A A74$99.50$85.00$110.00$105.00
0570Asphalt seal aggregateTON A A4$470.00$470.00$540.00$495.00
0580Asphalt seal coatTON A A0.50$1,605.00$1,605.00$1,800.00$1,690.00
0590CL2 asph base 1.00D PG64-22TON A A43$340.15$340.15$390.00$355.00
0600CL2 asph surf 0.38D PG64-22TON A A19$364.10$364.10$410.00$380.00
0610Asphalt material for tackTON A A0.27$640.00$640.00$730.00$675.00
0620Delineator for guardrail BI directional whiteEACH A A8$12.00$15.24$13.00$9.30
0630Barricade-type IIIEACH A A2$200.00$250.00$190.00$150.00
0640Structure granular backfillCUYD A A155.20$85.00$110.00$220.00$155.00
0650Guardrail-steel W beam-S faceLF A A171.50$40.00$45.06$43.00$41.00
0660Guardrail terminal section no 1EACH A A6$85.00$81.18$92.00$81.00
0670Guardrail end treatment type 2MEACH A A1$1,500.00$1,882.38$1,600.00$2,146.00
0680Guardrail end treatment type 7EACH A A1$2,000.00$2,011.51$2,200.00$1,905.00
0690Temp guardrailLF A A162.50$25.00$29.71$27.00$32.00
0700Clearing and grubbingLS A A1$25,000$15,000$32,000$18,200
0710Temporary signsSQFT A A100$20.00$20.00$17.00$17.85
0720Edge keyLF A A108$55.50$55.50$63.00$58.00
0730Retaining wall-gabionCUYD A A36$250.00$490.00$650.00$830.00
0740Maintain & control trafficLS A A1$7,000.00$25,000$21,000$5,550.00
0750Diversions (by-pass detours)LS A A1$20,000$20,000$5,900.00$13,500
0760StakingLS A A1$5,000.00$4,000.00$32,000$4,200.00
0770Remove structureLS A A1$25,000$27,000$54,000$24,450
0780Armored edge for concreteLF A A32$125.00$140.00$410.00$85.00
0790SBM alum sheet signs .080 inSQFT A A11$45.00$49.45$49.00$42.00
0800Steel post type 1LF A A12$35.00$42.57$38.00$26.00
0810Pave striping-perm paint-4 inLF A A85$5.00$5.00$5.40$5.25
0820Foundation preparationLS A A1$50,000$24,000$21,000$29,280
0830Cyclopean stone rip rapTON A A265$60.00$70.00$69.00$80.00
0840Test pilesLF A A63$200.00$160.00$200.00$120.00
0850Piles-steel HP12X53LF A A212$100.00$135.00$140.00$135.00
0860Pile points-12 inEACH A A10$150.00$175.00$290.00$170.00
0870Concrete-class ACUYD A A39.40$1,500.00$1,385.00$1,500.00$1,880.00
0880Concrete-class AACUYD A A22.20$2,500.00$2,135.00$3,100.00$2,990.00
0890Steel reinforcement-epoxy coatedLB A A5,515$2.00$2.75$2.70$2.50
0900Precast PC box beam CB17-48LF A A184$500.00$490.00$440.00$940.00
0910Temporary bridgeEACH A A1$35,000$143,500$82,000$198,000
0920Erosion controlLS A A1$5,000.00$5,200.00$8,900.00$3,300.00
0930Concrete sealingSQFT A A990$2.00$3.00$13.00$4.05
0940Rail system side mounted MGSLF A A92$215.00$213.94$250.00$240.00
0950Mobilization for concrete surf treatmentLS A A1$50.00$2,000.00$10,000$1,500.00
0960MobilizationLS A A1$90,000$105,705$100,000$120,825
0970DemobilizationLS A A1$27,800$31,715$40,000$36,400
KYTC contract 26-5406: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of February 19, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy