KYTC contract 26-5408 bid tabulation
BRIDGE REPLACEMENT KY 79. Let by Kentucky Transportation Cabinet on March 26, 2026. 3 bids received.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 26 MAR 2026
- Pay items
- 77
- Data through
- 22 OCT 2026
2 of the 3 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 2 | E & B Paving LLC | $2,557,471 | +1.0% | +7.0% |
| 3 | Jave LLC | $2,704,802 | +6.0% | +13% |
Engineer's estimate: $2,386,366.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Jave LLC |
|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 612 | $100.00 | $72.54 |
| 0020 | Asphalt seal aggregate | TON A A | 12 | $775.00 | $623.15 |
| 0030 | Asphalt seal coat | TON A A | 2 | $1,970.00 | $1,297.80 |
| 0040 | Leveling & wedging PG64-22 | TON A A | 25 | $172.00 | $128.49 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A A | 675 | $118.00 | $113.30 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A A | 184 | $199.00 | $121.95 |
| 0070 | Asphalt material for tack | TON A A | 2.30 | $0.10 | $556.20 |
| 0080 | Asphalt pave milling & texturing | TON A A | 101 | $102.00 | $114.28 |
| 0090 | Delineator for guardrail BI directional white | EACH A A | 8 | $15.15 | $15.60 |
| 0100 | Delineator for barrier wall-B/W | EACH A A | 18 | $55.00 | $29.25 |
| 0110 | Relocate temp conc barrier | LF A A | 80 | $58.00 | $40.66 |
| 0120 | Barricade-type III | EACH A A | 3 | $159.00 | $103.00 |
| 0130 | Roadway excavation | CUYD A A | 708 | $125.00 | $59.23 |
| 0140 | Fence-woven wire type 1 | LF A A | 214 | $25.16 | $25.91 |
| 0150 | Guardrail-steel W beam-S face | LF A A | 412.50 | $31.82 | $32.77 |
| 0160 | Guardrail terminal section no 1 | EACH A A | 1 | $88.51 | $91.17 |
| 0170 | Guardrail end treatment type 1 | EACH A A | 1 | $3,466.23 | $3,570.22 |
| 0180 | Guardrail end treatment type 4A | EACH A A | 2 | $3,789.40 | $3,903.08 |
| 0190 | Clearing and grubbing | LS A A | 1 | $10,000 | $13,010 |
| 0200 | Temporary signs | SQFT A A | 318 | $8.48 | $6.18 |
| 0210 | Edge key | LF A A | 149 | $16.10 | $17.15 |
| 0220 | Maintain & control traffic | LS A A | 1 | $7,800.00 | $46,129 |
| 0230 | Portable changeable message sign | EACH A A | 4 | $3,710.00 | $4,585.56 |
| 0240 | Mobilization for mill & text | LS A A | 1 | $3,800.00 | $6,143.95 |
| 0250 | Edgeline rumble strips | LF A A | 697 | $7.50 | $7.73 |
| 0260 | Staking | LS A A | 1 | $42,049 | $7,605.00 |
| 0270 | Remove structure | LS A A | 1 | $294,640 | $217,357 |
| 0280 | Relocate crash cushion | EACH A A | 4 | $3,575.65 | $4,183.51 |
| 0290 | Conc barrier wall type 9T | LF A A | 183 | $100.00 | $122.85 |
| 0300 | Temp signal multi phase | EACH A A | 3 | $10,335 | $37,080 |
| 0310 | Erosion control blanket | SQYD A A | 513 | $3.07 | $3.16 |
| 0320 | SBM alum sheet signs .080 in | SQFT A A | 21 | $52.12 | $53.74 |
| 0330 | Steel post type 1 | LF A A | 25 | $34.15 | $35.17 |
| 0340 | Pave striping-thermo-6 in W | LF A A | 1,333 | $1.35 | $1.39 |
| 0350 | Pave striping-thermo-6 in Y | LF A A | 1,520 | $1.35 | $1.39 |
| 0360 | Pave striping-dur TY 1-6 in W | LF A A | 420 | $9.00 | $9.27 |
| 0370 | Pave striping-dur TY 1-6 in Y | LF A A | 210 | $9.00 | $9.27 |
| 0380 | Pave marking-thermo cross-hatch | SQFT A A | 575 | $7.00 | $7.21 |
| 0390 | Pave marking-paint symbol | EACH A A | 2 | $100.00 | $103.00 |
| 0400 | Crash cushion TY 6 class B TL3 | EACH A A | 2 | $43,447 | $56,098 |
| 0410 | Object marker TY 3 | EACH A A | 3 | $27.31 | $28.13 |
| 0420 | Pave marking thermo-bike | EACH A A | 2 | $300.00 | $309.00 |
| 0430 | Longitudinal edge key | LF A A | 274 | $36.05 | $17.87 |
| 0440 | Erosion control | LS A A | 1 | $15,000 | $15,210 |
| 0450 | Pave mark temp paint stop bar-24 in | LF A A | 24 | $20.00 | $20.60 |
| 0460 | Barcode sign inventory | EACH A A | 3 | $46.47 | $47.39 |
| 0470 | Rail system single slope - 40 in | LF A A | 100 | $288.00 | $476.19 |
| 0480 | Thrie beam guardrail transition TL-3 | EACH A A | 4 | $3,385.44 | $3,487.00 |
| 0490 | Electronic delivery MGMT system - agg | LS A A | 1 | $2,500.00 | $1.03 |
| 0500 | Removable bollard | EACH A A | 4 | $892.95 | $1,044.75 |
| 0510 | Structure granular backfill | CUYD A A | 264 | $140.00 | $107.64 |
| 0520 | Concrete-class B | CUYD A A | 6.30 | $1,057.61 | $248.04 |
| 0530 | Armored edge for concrete | LF A A | 84 | $100.00 | $133.38 |
| 0540 | PVC pipe-8 in | LF A A | 326 | $40.00 | $87.75 |
| 0550 | Structure excav-solid rock | CUYD A A | 56 | $800.00 | $232.83 |
| 0560 | Foundation preparation | LS A A | 1 | $15,935 | $15,350 |
| 0570 | Test piles | LF A A | 34 | $294.93 | $278.46 |
| 0580 | Pre-drilling for piles | LF A A | 140 | $640.00 | $548.72 |
| 0590 | Piles-steel HP12X53 | LF A A | 144 | $255.00 | $278.46 |
| 0600 | Pile points-12 in | EACH A A | 14 | $196.00 | $161.46 |
| 0610 | Concrete-class A | CUYD A A | 44 | $1,500.00 | $2,743.65 |
| 0620 | Concrete-class AA | CUYD A A | 194.60 | $1,550.00 | $1,625.13 |
| 0630 | Mechanical reinf coupler #5 epoxy coated | EACH A A | 432 | $35.00 | $56.16 |
| 0640 | Steel reinforcement-epoxy coated | LB A A | 41,842 | $2.20 | $2.42 |
| 0650 | Concrete sealing | SQFT A A | 9,300 | $1.55 | $3.51 |
| 0660 | Mechanical reinf coupler #8-epoxy coated | EACH A A | 20 | $60.00 | $121.68 |
| 0670 | PPC I-beam HN 48-49 | LF A A | 515 | $745.00 | $959.40 |
| 0680 | Rail system single slope - 40 in | LF A A | 316 | $210.00 | $347.49 |
| 0690 | Aluminum handrail | LF A A | 211 | $80.00 | $104.13 |
| 0700 | Mobilization for concrete surf treatment | LS A A | 1 | $1,500.00 | $5,335.20 |
| 0710 | W encasement steel open cut range 3 | LF A A | 103 | $835.00 | $463.32 |
| 0720 | W pipe DCTL iron RSTRND joint 06 in | LF A A | 232 | $505.00 | $298.35 |
| 0730 | W plug existing main | EACH A A | 2 | $1,950.00 | $5,337.54 |
| 0740 | W tie-in 06 inch | EACH A A | 2 | $4,300.00 | $3,616.47 |
| 0750 | W valve cut-in 06 inch | EACH A A | 2 | $3,250.00 | $9,004.32 |
| 0760 | Mobilization | LS A A | 1 | $120,068 | $126,017 |
| 0770 | Demobilization | LS A A | 1 | $36,021 | $38,110 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of March 26, 2026. Compiled by Mirage Metrics.