KYTC contract 26-5409 bid tabulation
BRIDGE SUPERSTRUCTURE REHAB KY 89. Let by Kentucky Transportation Cabinet on June 25, 2026. 3 bids received; low bid $1,627,280 by Kay & Kay Contracting LLC, -5.1% against the engineer's estimate of $1,714,484.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 25 JUN 2026
- Pay items
- 33
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kay & Kay Contracting LLC | $1,627,280 | Low | -5.0% |
| 2 | Bush & Burchett Inc | $1,669,120 | +3.0% | -3.0% |
| 3 | Haydon Bridge Company Inc | $1,996,159 | +23% | +16% |
Engineer's estimate: $1,714,484.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kay & Kay Contracting LLC | 2. Bush & Burchett Inc | 3. Haydon Bridge Company Inc |
|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 8 | $644.60 | $350.00 | $450.00 |
| 0020 | CL2 asph base 1.00D PG64-22 | TON A A | 7 | $500.00 | $500.00 | $545.00 |
| 0030 | CL2 asph surf 0.38D PG64-22 | TON A A | 7 | $500.00 | $600.00 | $545.00 |
| 0035 | Asphalt material for tack | TON A A | 1 | $1,250.00 | $1,250.00 | $1,400.00 |
| 0040 | Barricade-type III | EACH A A | 4 | $159.00 | $200.00 | $400.00 |
| 0050 | G/R end treatment type 7 | EACH A A | 4 | $1,800.00 | $1,800.00 | $2,000.00 |
| 0060 | Clearing and grubbing | LS A A | 1 | $139,600 | $100,000 | $430,000 |
| 0070 | Temporary signs | SQFT A A | 36 | $19.08 | $25.00 | $60.00 |
| 0080 | Maintain & control traffic | LS A A | 1 | $120,000 | $30,000 | $50,000 |
| 0090 | Portable changeable message sign | EACH A A | 2 | $3,100.00 | $3,000.00 | $5,000.00 |
| 0095 | Mobilization for mill & text | LS A A | 1 | $2,850.00 | $2,850.00 | $3,200.00 |
| 0100 | Staking | LS A A | 1 | $9,210.00 | $20,000 | $20,000 |
| 0110 | Erosion control | LS A A | 1 | $96,750 | $16,000 | $9,500.00 |
| 0120 | G/R-W beam-S face TL-3 | LF A A | 100 | $27.00 | $27.00 | $58.00 |
| 0130 | Asphalt milling and texturing | SQYD A A | 78 | $45.00 | $45.00 | $50.00 |
| 0140 | Structure granular backfill | CUYD A A | 27 | $251.20 | $150.00 | $150.00 |
| 0150 | Armored edge for concrete | LF A A | 28 | $259.00 | $150.00 | $230.00 |
| 0160 | Cyclopean stone rip rap | TON A A | 74 | $215.80 | $100.00 | $140.00 |
| 0170 | Concrete-class A | CUYD A A | 4 | $7,416.00 | $5,000.00 | $10,000 |
| 0180 | Concrete-class AA | CUYD A A | 97 | $2,050.00 | $2,200.00 | $3,400.00 |
| 0190 | Steel reinforcement | LB A A | 650 | $24.50 | $5.00 | $5.00 |
| 0200 | Steel reinforcement-epoxy coated | LB A A | 29,150 | $1.96 | $2.25 | $3.25 |
| 0210 | Structural steel | LS A A | 1 | $603,200 | $675,000 | $535,000 |
| 0220 | Shear connectors | LS A A | 1 | $10,600 | $10,000 | $15,000 |
| 0230 | Remove superstructure | LS A A | 1 | $120,000 | $300,000 | $160,000 |
| 0240 | Concrete patching repair | SQFT A A | 30 | $428.20 | $100.00 | $495.00 |
| 0250 | Concrete sealing | SQFT A A | 4,180 | $2.00 | $3.00 | $2.25 |
| 0260 | Bearing pads | EACH A A | 12 | $2,319.00 | $3,000.00 | $2,000.00 |
| 0270 | Rail system side mounted MGS | LF A A | 400 | $189.00 | $189.00 | $250.00 |
| 0280 | Historic bronze plaque | EACH A A | 1 | $3,564.00 | $3,000.00 | $3,200.00 |
| 0290 | Install historic bronze plaque | EACH A A | 1 | $225.00 | $3,000.00 | $2,500.00 |
| 0300 | Painting | SQFT A A | 3,182 | $2.10 | $2.10 | $18.00 |
| 0310 | Demobilization | LS A A | 1 | $24,048 | $24,700 | $29,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of June 25, 2026. Compiled by Mirage Metrics.