KYTC contract 26-5414 bid tabulation

BRIDGE REPLACEMENT CR 1086. Let by Kentucky Transportation Cabinet on May 21, 2026. 3 bids received; low bid $719,612 by Kay & Kay Contracting LLC, -8.8% against the engineer's estimate of $789,479.

Owner
Kentucky Transportation Cabinet
Letting
21 MAY 2026
Pay items
40
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kay & Kay Contracting LLC$719,612Low-9.0%
2Hinkle Construction Services LLC$729,513+1.0%-8.0%
3Jave LLC$771,219+7.0%-2.0%
KYTC contract 26-5414: bids by rank

Engineer's estimate: $789,479.

Bid tabulation

LinePay itemUnitQuantity1. Kay & Kay Contracting LLC2. Hinkle Construction Services LLC3. Jave LLC
0010Dga baseTON A A104$85.00$64.00$84.68
0020Asphalt seal aggregateTON A A2$250.00$410.00$262.50
0030Asphalt seal coatTON A A0.22$2,500.00$34,000$2,625.00
0040CL2 asph base 1.00D PG64-22TON A A37$400.00$420.00$420.00
0050CL2 asph surf 0.38D PG64-22TON A A13$700.00$730.00$735.00
0060Asphalt material for tackTON A A0.14$10.00$10.50$10.50
0070Delineator for G/R BI directional whiteEACH A A8$13.00$10.00$13.65
0080Barricade-type IIIEACH A A2$162.00$150.00$116.00
0090Roadway excavationCUYD A A48$200.00$30.00$69.60
0100G/R terminal section no 1EACH A A1$85.00$78.00$89.25
0110G/R end treatment type 7EACH A A3$1,875.00$2,170.00$1,968.75
0120Right-of-way monument type 1EACH A A8$179.50$155.00$730.80
0130Witness postEACH A A2$146.00$124.00$661.20
0140Channel lining class IITON A A200$75.50$41.00$78.88
0150Clearing and grubbingLS A A1$31,350$10,830$46,261
0160Temporary signsSQFT A A200$19.50$20.00$7.35
0170Edge keyLF A A16$156.25$165.00$164.06
0180Fabric-geotextile class 1SQYD A A200$6.70$2.50$3.69
0190Maintain & control trafficLS A A1$27,000$28,500$3,459.12
0200Portable changeable message signEACH A A2$2,250.00$2,515.00$2,582.16
0210StakingLS A A1$6,500.00$5,400.00$2,900.00
0220Remove structureLS A A1$27,000$29,310$24,425
0230Erosion controlLS A A1$28,600$5,000.00$8,120.00
0240G/R steel W beam-S face (7 FT post)LF A A137.50$29.00$41.00$30.45
0250Mobilization for concrete surf treatmentLS A A1$1,500.00$1,350.00$5,800.00
0260Structure granular backfillCUYD A A261.70$91.10$128.00$89.32
0270Armored edge for concreteLF A A47$145.00$70.00$99.76
0280Foundation preparationLS A A1$27,000$45,210$18,436
0290Cyclopean stone rip rapTON A A399.90$58.50$68.00$64.39
0300Test pilesLF A A40$136.50$142.00$167.41
0310Pre-drilling for pilesLF A A160$271.00$368.00$426.98
0320Piles-steel HP12X53LF A A210$117.50$190.00$165.09
0330Pile points-12 inEACH A A16$160.00$0.01$1.16
0340Concrete-class ACUYD A A71.90$1,150.00$1,060.00$1,313.12
0350Concrete-class AACUYD A A43.50$1,150.00$1,750.00$1,947.64
0360Steel reinforcement-epoxy coatedLB A A8,706$2.86$2.00$2.53
0370Precast PC box beam CB27-48LF A A330$450.00$435.00$475.97
0380Concrete sealingSQFT A A3,200$2.00$1.60$2.02
0390Deep beam bridge G/RLF A A132$263.85$230.00$306.05
0400DemobilizationLS A A1$10,635$10,800$11,397
KYTC contract 26-5414: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of May 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy