MoDOT contract 251114-F07 bid tabulation
JSLM0087 - ROUTE D - FRANKLIN COUNTY. Let by Missouri DOT on November 14, 2025, Franklin, St. Louis. 4 bids received; low bid $414,687 by Plattin Creek Excavating, LLC dba PCX Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 14 NOV 2025
- Pay items
- 20
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Plattin Creek Excavating, LLC dba PCX Construction, LLC | $414,687 | Low |
| 2 | Concrete Strategies, LLC | $428,816 | +3.0% |
| 3 | N.B. West Contracting Company | $605,000 | +46% |
| 4 | Olympus Painting Contractors, Inc. | $625,778 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Plattin Creek Excavating, LLC dba PCX Construction, LLC | 2. Concrete Strategies, LLC | 3. N.B. West Contracting Company | 4. Olympus Painting Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $20,000 | $1,500.00 | $20,000 | $5,000.00 |
| 0020 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $2,800.00 | $2,650.00 | $2,800.00 | $2,800.00 |
| 0030 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $135,000 | $60,500 | $82,408 | $145,000 |
| 0040 | Misc.maintenance of commission-owned traffic control devices (6169901) | LS | 1 | $1.00 | $1,600.00 | $1.00 | $5,000.00 |
| 0050 | Mobilization (6181000) | LS | 1 | $40,000 | $90,500 | $167,287 | $60,000 |
| 0060 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 4 | $300.00 | $385.00 | $300.00 | $420.00 |
| 0070 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 716 | $3.00 | $2.20 | $3.00 | $5.00 |
| 0080 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 1,084 | $2.00 | $3.30 | $2.00 | $5.00 |
| 0090 | Pavement marking removal (6207001) | LF | 1,106 | $3.00 | $6.60 | $3.00 | $8.00 |
| 0100 | Pavement marking removal (symbols) (6207002) | EACH | 2 | $100.00 | $220.00 | $100.00 | $400.00 |
| 0110 | Contractor furnished surveying and staking (6274000) | LS | 1 | $2,500.00 | $1,722.64 | $5,000.00 | $10,000 |
| 0120 | Misc.removal of diaphragm (2169902) | EACH | 2 | $13,000 | $1,800.00 | $1,500.00 | $2,000.00 |
| 0130 | Fabricated structural carbon steel (misc) (7121000) | LB | 710 | $9.55 | $16.50 | $12.00 | $35.00 |
| 0140 | Surface preparation for recoating structural steel (7125100) | LS | 1 | $75,000 | $110,200 | $100,000 | $150,000 |
| 0150 | Field application of inorganic zinc primer (7125110) | LS | 1 | $11,250 | $11,000 | $10,000 | $35,000 |
| 0160 | Intermediate field coat (system G) (7125111) | LS | 1 | $7,500.00 | $11,000 | $10,000 | $35,000 |
| 0170 | Misc.grind surface deformities (7129901) | LS | 1 | $3,000.00 | $1,450.00 | $650.00 | $4,000.00 |
| 0180 | Misc.heat straightening of existing steel beam (7129901) | LS | 1 | $65,250 | $95,500 | $177,000 | $78,000 |
| 0190 | Misc.bolt replacement (7129902) | EACH | 52 | $22.52 | $48.00 | $50.00 | $500.00 |
| 0200 | Misc.crack reapirs (7129902) | EACH | 6 | $1,100.00 | $1,050.00 | $650.00 | $3,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of November 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.