MoDOT contract 260320-G01 bid tabulation
J7P3397, JSR0165 - ROUTE 32, 39, 123 - CEDAR, GREENE COUNTIES. Let by Missouri DOT on March 20, 2026, Greene, Southwest. 5 bids received; low bid $773,704 by Branco Enterprises, Inc..
- Owner
- Missouri DOT
- Letting
- 20 MAR 2026
- Pay items
- 90
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Branco Enterprises, Inc. | $773,704 | Low |
| 2 | Hunter Chase & Associates, Inc. | $777,000 | 0.0% |
| 3 | Ti-Zack Concrete, LLC | $883,932 | +14% |
| 4 | Sprouls Construction, Inc. | $899,372 | +16% |
| 5 | Radmacher Brothers Excavating Co., Inc. | $1,006,863 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Branco Enterprises, Inc. | 2. Hunter Chase & Associates, Inc. | 3. Ti-Zack Concrete, LLC | 4. Sprouls Construction, Inc. | 5. Radmacher Brothers Excavating Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $21,733 | $9,185.36 | $11,000 | $7,500.00 | $7,550.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $49,557 | $25,848 | $22,800 | $72,000 | $29,300 |
| 0030 | Class 3 excavation (2063000) | CY | 642 | $43.00 | $31.00 | $62.15 | $30.00 | $56.50 |
| 0040 | Linear grading class 1 (2071000) | STA | 3 | $1,237.00 | $2,257.07 | $2,660.00 | $1,500.00 | $1,870.00 |
| 0050 | Misc.linear grading for ADA facilities (2079903) | LF | 1,974.80 | $13.00 | $12.34 | $4.04 | $5.00 | $19.50 |
| 0060 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 1,876 | $13.00 | $10.37 | $4.25 | $15.00 | $15.90 |
| 0070 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 403 | $20.00 | $10.50 | $19.80 | $18.00 | $14.10 |
| 0080 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 63 | $322.00 | $204.80 | $275.00 | $225.00 | $419.00 |
| 0090 | Bituminous pavement mixture PG64-22 (base) (4013000) | TON | 37.20 | $483.00 | $251.37 | $385.00 | $275.00 | $457.00 |
| 0100 | Tack coat (4071005) | GAL | 113 | $4.00 | $3.02 | $5.50 | $3.00 | $4.35 |
| 0110 | Concrete curb ramp (6081010) | SY | 370.40 | $107.00 | $193.41 | $172.80 | $195.00 | $173.50 |
| 0120 | Truncated domes (6081012) | SF | 200 | $44.00 | $25.66 | $47.50 | $50.00 | $44.75 |
| 0130 | Hand-railing for steps without balusters (6082023) | LF | 6 | $252.00 | $266.72 | $236.50 | $325.00 | $260.00 |
| 0140 | 4 in. concrete median strip (6083004) | SY | 9.70 | $51.00 | $337.54 | $114.80 | $200.00 | $146.00 |
| 0150 | Sidewalk hand-railing with balusters (6084024) | LF | 40 | $186.00 | $196.86 | $236.50 | $240.00 | $200.00 |
| 0160 | Paved approach, 8 in. (6085008) | SY | 571.20 | $97.00 | $108.95 | $185.49 | $120.00 | $117.00 |
| 0170 | Concrete sidewalk, 4 in. (6086004) | SY | 865 | $59.00 | $69.82 | $89.97 | $90.00 | $77.00 |
| 0180 | Concrete sidewalk, 8 in. (6086008) | SY | 11.10 | $146.00 | $230.43 | $185.49 | $120.00 | $88.25 |
| 0190 | Concrete curb (6 in. height and under) type S (6091010) | LF | 11 | $124.00 | $359.78 | $99.52 | $50.00 | $106.00 |
| 0200 | Concrete gutter type A (6091041) | LF | 15 | $108.00 | $121.38 | $99.52 | $70.00 | $107.00 |
| 0210 | Curb and gutter type A (6091051) | LF | 252 | $46.00 | $48.11 | $67.27 | $50.00 | $57.00 |
| 0220 | Rock lining (6097000) | CY | 33 | $226.00 | $130.47 | $126.50 | $70.00 | $189.00 |
| 0230 | Misc.2 FT concrete curb & gutter (6099903) | LF | 482 | $44.00 | $46.94 | $80.43 | $40.00 | $49.00 |
| 0240 | Misc.modified S-curb (6099903) | LF | 328 | $61.00 | $101.39 | $80.43 | $60.00 | $112.00 |
| 0250 | Manhole frame and cover, type 3 (6143013) | EACH | 2 | $967.00 | $1,158.98 | $753.75 | $1,000.00 | $966.00 |
| 0260 | Manhole frame and cover, type 4 (6143014) | EACH | 2 | $1,014.00 | $817.62 | $1,222.50 | $1,200.00 | $1,020.00 |
| 0270 | Construction signs (6161005) | SF | 262 | $6.00 | $6.88 | $7.70 | $7.00 | $6.30 |
| 0280 | Channelizer (trim-line) (6161025) | EACH | 50 | $19.00 | $21.17 | $22.00 | $23.00 | $20.00 |
| 0290 | Direction indicator barricade (6161033) | EACH | 6 | $55.00 | $95.26 | $88.00 | $66.00 | $57.75 |
| 0300 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 3 | $3,500.00 | $2,645.99 | $3,080.00 | $4,200.00 | $3,680.00 |
| 0310 | Misc.ADA compliant moveable barricade (6169902) | EACH | 23 | $100.00 | $116.42 | $148.50 | $120.00 | $105.00 |
| 0320 | Mobilization (6181000) | LS | 1 | $75,681 | $62,046 | $63,776 | $150,000 | $193,500 |
| 0330 | Additional mobilization for seeding (6181020) | EACH | 1 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0340 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 240 | $22.50 | $26.46 | $25.30 | $27.00 | $23.70 |
| 0350 | Pavement marking removal (6207001) | LF | 216 | $1.50 | $19.95 | $1.10 | $2.00 | $1.60 |
| 0360 | Pavement marking removal (symbols) (6207002) | EACH | 25 | $50.00 | $115.19 | $165.00 | $60.00 | $52.50 |
| 0370 | Flowable backfill (6214600A) | CY | 6 | $352.00 | $602.38 | $1,045.00 | $200.00 | $266.00 |
| 0380 | Coldmilling bituminous pavement for removal of surfacing (greater than 3 in. thick) (6221003) | SY | 27 | $73.50 | $54.67 | $38.50 | $60.00 | $127.00 |
| 0390 | Modified coldmilling (depth transitions) (6224010) | SY | 945 | $15.75 | $15.03 | $13.20 | $16.00 | $20.60 |
| 0400 | Contractor furnished surveying and staking (6274000) | LS | 1 | $7,040.00 | $7,451.12 | $20,900 | $8,500.00 | $10,000 |
| 0410 | Class B-1 concrete (7034001) | CY | 0.40 | $6,631.00 | $7,597.75 | $2,100.00 | $2,500.00 | $5,660.00 |
| 0420 | Reinforcing steel (7061000) | LB | 20 | $6.00 | $40.09 | $1.68 | $4.00 | $49.75 |
| 0430 | 15 in. pipe group A (7261015) | LF | 133 | $112.00 | $93.27 | $140.40 | $42.00 | $113.00 |
| 0440 | 30 in. pipe group A (7261030) | LF | 283 | $172.00 | $130.36 | $180.00 | $100.00 | $150.00 |
| 0450 | 42 in. pipe group A (7261042) | LF | 32 | $308.00 | $232.51 | $312.00 | $170.00 | $231.00 |
| 0460 | Misc.29 in X 45 in elliptical reinforced concrete pipe (7269903) | LF | 7 | $346.00 | $274.94 | $628.80 | $250.00 | $252.00 |
| 0470 | Misc.5 FT X 5 FT junction box (7319902) | EACH | 1 | $7,844.00 | $7,381.75 | $10,412 | $9,000.00 | $6,850.00 |
| 0480 | Misc.6 FT X 6 FT junction box (7319902) | EACH | 1 | $8,764.00 | $7,447.43 | $16,440 | $10,000 | $7,770.00 |
| 0490 | Misc.modified type T drop inlet 5 FT X 3 FT (7319903) | LF | 10 | $1,243.00 | $753.12 | $2,400.00 | $1,200.00 | $837.00 |
| 0500 | 42 in. or allowed substitute group A flared end section (7320642A) | EACH | 1 | $2,319.00 | $3,091.75 | $2,400.00 | $3,000.00 | $2,550.00 |
| 0510 | Mulching (8025006) | ACRE | 0.40 | $3,539.00 | $3,745.68 | $3,740.00 | $3,500.00 | $3,570.00 |
| 0520 | Turf type tall fescue sodding (8031000A) | SY | 995 | $7.27 | $7.69 | $13.20 | $10.00 | $27.75 |
| 0530 | Seeding - cool season grasses (8051000A) | ACRE | 0.20 | $4,719.05 | $4,994.65 | $8,250.00 | $6,000.00 | $7,880.00 |
| 0540 | Sediment trap excavation (8061003) | CY | 20 | $40.00 | $173.10 | $55.00 | $45.00 | $56.50 |
| 0550 | Sediment trap rock (8061004) | CY | 20 | $100.00 | $112.07 | $55.00 | $75.00 | $62.50 |
| 0560 | Alternate ditch check (8061006) | LF | 42 | $5.18 | $5.48 | $4.40 | $10.00 | $4.20 |
| 0570 | Curb inlet check (8061007A) | EACH | 5 | $180.32 | $190.85 | $55.00 | $100.00 | $52.50 |
| 0580 | Sediment removal (8061016) | CY | 76 | $18.00 | $30.06 | $55.00 | $40.00 | $37.75 |
| 0590 | Temporary seeding (8061017) | ACRE | 0.20 | $4,717.85 | $4,993.35 | $8,250.00 | $3,200.00 | $6,300.00 |
| 0600 | Silt fence (8061019) | LF | 2,489 | $3.85 | $4.07 | $2.20 | $3.00 | $2.10 |
| 0610 | Type 3B erosion control blanket (8064140) | SY | 738 | $3.20 | $3.39 | $2.20 | $3.00 | $2.10 |
| 0620 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 192 | $11.75 | $12.44 | $22.00 | $16.00 | $15.00 |
| 0630 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 12 | $366.00 | $387.37 | $247.50 | $475.00 | $375.00 |
| 0640 | SHF-flat sheet fluorescent (9035069A) | SF | 13 | $20.50 | $21.70 | $44.00 | $27.00 | $25.00 |
| 0650 | Removal of improvements (2022010) | LS | 1 | $7,740.00 | $16,801 | $1,100.00 | $5,000.00 | $22,000 |
| 0660 | Culvert cleanout (2063500) | EACH | 2 | $2,008.00 | $507.86 | $2,926.00 | $4,000.00 | $1,990.00 |
| 0670 | Linear grading class 1 (2071000) | STA | 1.30 | $1,237.00 | $1,650.94 | $2,750.00 | $1,500.00 | $1,870.00 |
| 0680 | Misc.linear grading for ADA facilities (2079903) | LF | 51 | $10.00 | $49.59 | $6.60 | $10.00 | $19.50 |
| 0690 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 34 | $12.00 | $52.57 | $6.60 | $15.00 | $15.90 |
| 0700 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 82 | $14.00 | $23.61 | $6.60 | $18.00 | $15.90 |
| 0710 | Concrete pavement ( 8 in. non-reinf) (5021108) | SY | 82 | $91.00 | $100.65 | $185.49 | $130.00 | $122.00 |
| 0720 | Concrete curb ramp (6081010) | SY | 23 | $123.00 | $224.02 | $181.90 | $220.00 | $167.00 |
| 0730 | Truncated domes (6081012) | SF | 22 | $51.00 | $74.20 | $47.50 | $50.00 | $44.75 |
| 0740 | Concrete sidewalk, 8 in. (6086008) | SY | 11 | $123.00 | $232.53 | $249.14 | $120.00 | $88.50 |
| 0750 | Misc.ADA compliant manhole frame and cover (6089902) | EACH | 2 | $1,635.00 | $1,539.09 | $961.44 | $6,500.00 | $4,840.00 |
| 0760 | Misc.curved vane grate, frame, and cover 5'X2' (6149902) | EACH | 1 | $2,074.00 | $1,931.60 | $1,875.00 | $4,500.00 | $551.00 |
| 0770 | Construction signs (6161005) | SF | 344 | $6.00 | $6.88 | $7.70 | $7.00 | $6.30 |
| 0780 | Channelizer (trim-line) (6161025) | EACH | 50 | $13.00 | $21.17 | $22.00 | $16.00 | $13.65 |
| 0790 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $1,125.00 | $2,646.00 | $3,080.00 | $1,350.00 | $1,180.00 |
| 0800 | Misc.ADA compliant moveable barricade (6169902) | EACH | 8 | $50.00 | $116.42 | $148.50 | $60.00 | $52.50 |
| 0810 | Mobilization (6181000) | LS | 1 | $16,400 | $27,500 | $11,370 | $28,000 | $22,000 |
| 0820 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 216 | $27.25 | $26.46 | $29.70 | $33.00 | $28.50 |
| 0830 | Contractor furnished surveying and staking (6274000) | LS | 1 | $7,040.00 | $7,451.12 | $1,100.00 | $6,000.00 | $10,000 |
| 0840 | Alternate ditch check (8061006) | LF | 65 | $5.17 | $5.47 | $4.40 | $5.00 | $4.20 |
| 0850 | Curb inlet check (8061007A) | EACH | 5 | $180.32 | $190.85 | $55.00 | $70.00 | $52.50 |
| 0860 | Sediment removal (8061016) | CY | 6 | $18.00 | $30.08 | $55.00 | $40.00 | $37.75 |
| 0870 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 2 | $160.00 | $169.35 | $275.00 | $208.00 | $175.00 |
| 0880 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 32 | $11.75 | $12.44 | $22.00 | $16.00 | $15.00 |
| 0890 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 2 | $367.00 | $388.43 | $247.50 | $475.00 | $375.00 |
| 0900 | SHF-flat sheet fluorescent (9035069A) | SF | 25.50 | $20.50 | $21.70 | $44.00 | $27.00 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of March 20, 2026. Compiled by Mirage Metrics.