RankBidderTotal bidAgainst the low bid
1Ti-Zack Concrete, LLC$1,471,013Low
2Sprouls Construction, Inc.$1,499,832+2.0%
3Hunter Chase & Associates, Inc.$1,642,000+12%
MoDOT contract 260515-G01: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ti-Zack Concrete, LLC2. Sprouls Construction, Inc.3. Hunter Chase & Associates, Inc.
0010Removal of improvements (2022010)LS1$66,000$50,000$8,163.25
0020Class 3 excavation (2063000)CY39$129.78$50.00$51.41
0030Misc.linear grading for ADA facilities (2079909)STA73$693.37$1,200.00$2,474.92
0040Type 1 aggregate for base (4 in. thick) (3040143)SY4,989$10.15$20.00$15.03
0050Gravel (A) or crushed stone (B) (3105003)SY47$21.54$18.00$18.42
0060Concrete curb ramp (6081010)SY906.70$187.00$175.00$152.38
0070Truncated domes (6081012)SF1,538$26.25$55.00$30.15
0080Paved approach, 8 in. (6085008)SY2,242$175.78$125.00$101.57
0090Concrete sidewalk, 4 in. (6086004)SY1,778.70$95.66$90.00$71.03
0100Concrete sidewalk, 8 in. (6086008)SY61$175.78$140.00$123.60
0110Curb and gutter type B (6091052)LF584$67.76$60.00$40.06
0120Misc.concrete curb and gutter type B (6099903)LF1,709$67.76$65.00$50.40
0130Furnishing and placing bituminous material for class C partial depth pavement repair (6133020)TON7$330.00$1,000.00$868.16
0140Misc.lump sum temporary traffic control (6169901)LS1$21,311$5,000.00$28,201
0150Misc.misc. {temporary traffic barrier, ADA compliant movable barricade} (6169902)EACH77$132.00$150.00$37.03
0160Mobilization (6181000)LS1$24,554$90,000$332,672
0170Contractor furnished surveying and staking (6274000)LS1$10,610$4,500.00$22,218
018012 in. pipe group C (7250412)LF78$132.00$75.00$92.26
019015 in. pipe group C (7250415)LF8$192.50$100.00$199.81
0200Misc.seeding & mulching (8059901)LS1$3,850.00$5,000.00$17,275
0210Silt fence (8061019)LF1,557$1.10$6.00$4.19
0220Misc.inlet check (8069902)EACH43$1.10$400.00$166.04
0230Removal of improvements (2022010)LS1$33,000$18,000$29,685
0240Class 3 excavation (2063000)CY28$108.46$30.00$53.87
0250Misc.linear grading for ADA facilities (2079909)STA19.40$782.72$1,200.00$2,466.27
0260Type 1 aggregate for base (4 in. thick) (3040143)SY859$11.78$20.00$15.12
0270Gravel (A) or crushed stone (B) (3105003)SY8$126.54$25.00$73.77
0280Concrete curb ramp (6081010)SY166.50$187.00$250.00$187.77
0290Truncated domes (6081012)SF298$26.25$60.00$40.99
0300Paved approach, 8 in. (6085008)SY201.80$175.78$140.00$120.61
0310Concrete sidewalk, 4 in. (6086004)SY486.10$121.89$100.00$70.77
0320Concrete sidewalk, 8 in. (6086008)SY4.70$200.46$150.00$168.64
0330Misc.concrete curb and gutter type B (6099903)LF115$67.76$65.00$61.30
0340Furnishing and placing bituminous material for class C partial depth pavement repair (6133020)TON0.70$385.00$1,000.00$4,353.00
0350Misc.lump sum temporary traffic control (6169901)LS1$10,610$2,000.00$12,432
0360Misc.misc. {temporary traffic barrier, ADA compliant movable barricade} (6169902)EACH15$132.00$250.00$37.03
0370Mobilization (6181000)LS1$24,554$40,000$45,947
0380Contractor furnished surveying and staking (6274000)LS1$16,500$2,500.00$10,580
039012 in. pipe group C (7250412)LF47$165.00$80.00$60.70
0400Misc.8 in. unperforated smooth wall PVC underdrain pipe (7259902)EACH24$27.50$50.00$62.65
0410Misc.seeding & mulching (8059901)LS1$2,750.00$2,000.00$5,221.21
0420Silt fence (8061019)LF616$1.10$6.00$4.19
0430Misc.inlet check (8069902)EACH3$165.00$500.00$166.02
MoDOT contract 260515-G01: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy