MoDOT contract 260515-G01 bid tabulation
J7P3518, J7S3399 - VARIOUS ROUTES - HENRY, ST. CLAIR, VERNON COUNTIES. Let by Missouri DOT on May 15, 2026, Vernon, Southwest. 3 bids received; low bid $1,471,013 by Ti-Zack Concrete, LLC.
- Owner
- Missouri DOT
- Letting
- 15 MAY 2026
- Pay items
- 43
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $1,471,013 | Low |
| 2 | Sprouls Construction, Inc. | $1,499,832 | +2.0% |
| 3 | Hunter Chase & Associates, Inc. | $1,642,000 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ti-Zack Concrete, LLC | 2. Sprouls Construction, Inc. | 3. Hunter Chase & Associates, Inc. |
|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $66,000 | $50,000 | $8,163.25 |
| 0020 | Class 3 excavation (2063000) | CY | 39 | $129.78 | $50.00 | $51.41 |
| 0030 | Misc.linear grading for ADA facilities (2079909) | STA | 73 | $693.37 | $1,200.00 | $2,474.92 |
| 0040 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 4,989 | $10.15 | $20.00 | $15.03 |
| 0050 | Gravel (A) or crushed stone (B) (3105003) | SY | 47 | $21.54 | $18.00 | $18.42 |
| 0060 | Concrete curb ramp (6081010) | SY | 906.70 | $187.00 | $175.00 | $152.38 |
| 0070 | Truncated domes (6081012) | SF | 1,538 | $26.25 | $55.00 | $30.15 |
| 0080 | Paved approach, 8 in. (6085008) | SY | 2,242 | $175.78 | $125.00 | $101.57 |
| 0090 | Concrete sidewalk, 4 in. (6086004) | SY | 1,778.70 | $95.66 | $90.00 | $71.03 |
| 0100 | Concrete sidewalk, 8 in. (6086008) | SY | 61 | $175.78 | $140.00 | $123.60 |
| 0110 | Curb and gutter type B (6091052) | LF | 584 | $67.76 | $60.00 | $40.06 |
| 0120 | Misc.concrete curb and gutter type B (6099903) | LF | 1,709 | $67.76 | $65.00 | $50.40 |
| 0130 | Furnishing and placing bituminous material for class C partial depth pavement repair (6133020) | TON | 7 | $330.00 | $1,000.00 | $868.16 |
| 0140 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $21,311 | $5,000.00 | $28,201 |
| 0150 | Misc.misc. {temporary traffic barrier, ADA compliant movable barricade} (6169902) | EACH | 77 | $132.00 | $150.00 | $37.03 |
| 0160 | Mobilization (6181000) | LS | 1 | $24,554 | $90,000 | $332,672 |
| 0170 | Contractor furnished surveying and staking (6274000) | LS | 1 | $10,610 | $4,500.00 | $22,218 |
| 0180 | 12 in. pipe group C (7250412) | LF | 78 | $132.00 | $75.00 | $92.26 |
| 0190 | 15 in. pipe group C (7250415) | LF | 8 | $192.50 | $100.00 | $199.81 |
| 0200 | Misc.seeding & mulching (8059901) | LS | 1 | $3,850.00 | $5,000.00 | $17,275 |
| 0210 | Silt fence (8061019) | LF | 1,557 | $1.10 | $6.00 | $4.19 |
| 0220 | Misc.inlet check (8069902) | EACH | 43 | $1.10 | $400.00 | $166.04 |
| 0230 | Removal of improvements (2022010) | LS | 1 | $33,000 | $18,000 | $29,685 |
| 0240 | Class 3 excavation (2063000) | CY | 28 | $108.46 | $30.00 | $53.87 |
| 0250 | Misc.linear grading for ADA facilities (2079909) | STA | 19.40 | $782.72 | $1,200.00 | $2,466.27 |
| 0260 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 859 | $11.78 | $20.00 | $15.12 |
| 0270 | Gravel (A) or crushed stone (B) (3105003) | SY | 8 | $126.54 | $25.00 | $73.77 |
| 0280 | Concrete curb ramp (6081010) | SY | 166.50 | $187.00 | $250.00 | $187.77 |
| 0290 | Truncated domes (6081012) | SF | 298 | $26.25 | $60.00 | $40.99 |
| 0300 | Paved approach, 8 in. (6085008) | SY | 201.80 | $175.78 | $140.00 | $120.61 |
| 0310 | Concrete sidewalk, 4 in. (6086004) | SY | 486.10 | $121.89 | $100.00 | $70.77 |
| 0320 | Concrete sidewalk, 8 in. (6086008) | SY | 4.70 | $200.46 | $150.00 | $168.64 |
| 0330 | Misc.concrete curb and gutter type B (6099903) | LF | 115 | $67.76 | $65.00 | $61.30 |
| 0340 | Furnishing and placing bituminous material for class C partial depth pavement repair (6133020) | TON | 0.70 | $385.00 | $1,000.00 | $4,353.00 |
| 0350 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $10,610 | $2,000.00 | $12,432 |
| 0360 | Misc.misc. {temporary traffic barrier, ADA compliant movable barricade} (6169902) | EACH | 15 | $132.00 | $250.00 | $37.03 |
| 0370 | Mobilization (6181000) | LS | 1 | $24,554 | $40,000 | $45,947 |
| 0380 | Contractor furnished surveying and staking (6274000) | LS | 1 | $16,500 | $2,500.00 | $10,580 |
| 0390 | 12 in. pipe group C (7250412) | LF | 47 | $165.00 | $80.00 | $60.70 |
| 0400 | Misc.8 in. unperforated smooth wall PVC underdrain pipe (7259902) | EACH | 24 | $27.50 | $50.00 | $62.65 |
| 0410 | Misc.seeding & mulching (8059901) | LS | 1 | $2,750.00 | $2,000.00 | $5,221.21 |
| 0420 | Silt fence (8061019) | LF | 616 | $1.10 | $6.00 | $4.19 |
| 0430 | Misc.inlet check (8069902) | EACH | 3 | $165.00 | $500.00 | $166.02 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.