MoDOT contract 261016-D14 bid tabulation
JST0017C - ROUTE B - COOPER COUNTY. Let by Missouri DOT on October 16, 2026, Cooper, Central. 6 bids received; low bid $1,351,479 by Capital Paving & Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 16 OCT 2026
- Pay items
- 69
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Capital Paving & Construction, LLC | $1,351,479 | Low |
| 2 | Gene Haile Excavating, Inc. | $1,518,104 | +12% |
| 3 | Stockman Construction Corp. | $1,671,274 | +24% |
| 4 | Sam Gaines Construction, Inc. | $1,922,508 | +42% |
| 5 | Hardy Construction, LLC | $2,020,692 | +50% |
| 6 | Emery Sapp & Sons, Inc. | $2,289,054 | +69% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital Paving & Construction, LLC | 2. Gene Haile Excavating, Inc. | 3. Stockman Construction Corp. | 4. Sam Gaines Construction, Inc. | 5. Hardy Construction, LLC | 6. Emery Sapp & Sons, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $63,672 | $80,000 | $150,000 | $100,000 | $110,000 | $120,000 |
| 0020 | Unclassified excavation (2035000) | CY | 2,898 | $11.94 | $15.00 | $45.00 | $40.00 | $101.00 | $55.00 |
| 0030 | Compacting embankment (2036000) | CY | 940 | $12.31 | $6.00 | $13.00 | $30.00 | $13.00 | $9.50 |
| 0040 | Compacting in cut (2037075) | STA | 5 | $996.16 | $1,000.00 | $1,500.00 | $5,000.00 | $2,570.00 | $8,900.00 |
| 0050 | Class 3 excavation (2063000) | CY | 165 | $29.21 | $40.00 | $30.00 | $45.00 | $45.50 | $40.00 |
| 0060 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 2,434 | $13.07 | $11.00 | $10.25 | $15.00 | $17.00 | $17.00 |
| 0070 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 4,808 | $13.59 | $12.50 | $13.25 | $19.00 | $26.00 | $27.00 |
| 0080 | Type A2 shoulder (4010150) | SY | 316.30 | $76.22 | $75.00 | $136.00 | $90.00 | $153.00 | $172.00 |
| 0090 | Bituminous pavement mixture PG64-22, (BP-2) (4011211) | TON | 990 | $180.00 | $205.00 | $151.00 | $147.55 | $180.00 | $180.00 |
| 0100 | Concrete pavement (9 1/2 in. non-reinforced, 15 FT. joints) (5021333) | SY | 4,272 | $96.88 | $112.00 | $110.00 | $131.00 | $110.00 | $153.00 |
| 0110 | Misc.8 in. tinted concrete truck apron (5029905) | SY | 394.80 | $108.70 | $175.00 | $130.00 | $145.00 | $120.00 | $180.00 |
| 0120 | Concrete curb ramp (6081010) | SY | 108.40 | $232.88 | $115.00 | $115.00 | $75.00 | $168.00 | $265.00 |
| 0130 | Truncated domes (6081012) | SF | 210 | $36.96 | $37.50 | $28.00 | $40.00 | $32.00 | $30.00 |
| 0140 | Paved approach, 8 in. (6085008) | SY | 191.60 | $119.43 | $180.00 | $120.00 | $120.00 | $101.00 | $125.00 |
| 0150 | Concrete sidewalk, 4 in. (6086004) | SY | 209.70 | $75.40 | $122.00 | $90.00 | $75.00 | $98.50 | $180.00 |
| 0160 | Misc.3 in. tinted concrete median strip (6089905) | SY | 86.60 | $179.11 | $95.00 | $135.00 | $95.00 | $150.00 | $260.00 |
| 0170 | Misc.6 in. tinted concrete median strip (6089905) | SY | 241.40 | $127.25 | $98.00 | $155.00 | $145.00 | $160.00 | $333.00 |
| 0180 | Concrete curb (over 6 in. height) type S (6091011) | LF | 223 | $52.52 | $70.00 | $70.00 | $100.00 | $83.00 | $105.00 |
| 0190 | Integral curb (over 6 in. height) type A (6092021) | LF | 795 | $28.47 | $25.00 | $45.00 | $45.00 | $30.00 | $7.00 |
| 0200 | Rock lining (6097000) | CY | 4 | $157.70 | $250.00 | $370.00 | $175.00 | $160.00 | $225.00 |
| 0210 | Misc.apwa type CG-1 dry curb (6099903) | LF | 220 | $72.36 | $50.00 | $70.00 | $85.00 | $81.00 | $110.00 |
| 0220 | Misc.apwa type CG-2 dry curb (6099903) | LF | 375 | $63.22 | $55.00 | $70.00 | $75.00 | $69.00 | $105.00 |
| 0230 | Manhole frame and cover, type 3 (6143013) | EACH | 1 | $538.20 | $500.00 | $450.00 | $1,500.00 | $600.00 | $750.00 |
| 0240 | Construction signs (6161005) | SF | 447 | $8.00 | $9.00 | $7.70 | $7.50 | $7.50 | $9.50 |
| 0250 | Relocated signs (6161010) | SF | 32 | $8.00 | $9.00 | $9.25 | $9.00 | $9.00 | $9.50 |
| 0260 | Channelizer (trim-line) (6161025) | EACH | 75 | $31.00 | $35.00 | $16.45 | $16.00 | $16.00 | $36.00 |
| 0270 | Type 3 moveable barricade (6161030) | EACH | 10 | $170.00 | $190.00 | $103.00 | $100.00 | $100.00 | $200.00 |
| 0280 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $5,000.00 | $5,250.00 | $7,712.00 | $7,500.00 | $7,500.00 | $6,000.00 |
| 0290 | Mobilization (6181000) | LS | 1 | $81,135 | $116,665 | $102,000 | $150,000 | $208,000 | $250,000 |
| 0300 | Additional mobilization for seeding (6181020) | EACH | 2 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0310 | Preformed thermoplastic pavement marking, 6 in. white (6200009) | LF | 180 | $7.00 | $8.00 | $10.30 | $10.00 | $10.00 | $8.00 |
| 0320 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 236 | $21.00 | $24.00 | $28.28 | $27.50 | $27.50 | $25.00 |
| 0330 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 147 | $21.00 | $24.00 | $18.00 | $17.50 | $17.50 | $25.00 |
| 0340 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 2 | $250.00 | $275.00 | $411.00 | $400.00 | $400.00 | $290.00 |
| 0350 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 55 | $65.00 | $70.00 | $31.00 | $30.00 | $30.00 | $75.00 |
| 0360 | Preformed thermoplastic pavement marking, combination STR/LT/RT fish hook arrow (6200051) | EACH | 4 | $300.00 | $350.00 | $1,285.00 | $1,250.00 | $1,250.00 | $350.00 |
| 0370 | Temporary removable marking tape, 24 in., white (6205309) | LF | 128 | $3.00 | $4.00 | $28.30 | $27.50 | $27.50 | $3.50 |
| 0380 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 1,345 | $0.85 | $1.00 | $1.40 | $1.35 | $1.35 | $1.00 |
| 0390 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 486 | $0.85 | $1.00 | $1.40 | $1.35 | $1.35 | $1.00 |
| 0400 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 200 | $0.50 | $1.00 | $1.20 | $1.15 | $1.15 | $0.60 |
| 0410 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 1,491 | $0.50 | $1.00 | $1.20 | $1.15 | $1.15 | $0.60 |
| 0420 | Pavement marking removal (6207001) | LF | 5,241 | $0.85 | $1.00 | $1.20 | $1.15 | $1.15 | $1.00 |
| 0430 | 4 in temporary pavement marking paint (6208076) | LF | 15,831 | $0.50 | $1.00 | $1.20 | $1.15 | $1.15 | $0.60 |
| 0440 | Contractor furnished surveying and staking (6274000) | LS | 1 | $7,500.00 | $17,500 | $21,000 | $60,000 | $15,000 | $45,000 |
| 0450 | 15 in. pipe group A (7261015) | LF | 75 | $91.80 | $70.00 | $101.00 | $125.00 | $173.00 | $108.00 |
| 0460 | 18 in. pipe group A (7261018) | LF | 286 | $103.34 | $80.00 | $115.00 | $175.00 | $130.00 | $132.00 |
| 0470 | Precast concrete drop inlet 5 FT X 3 FT (7311053) | FT | 5 | $906.58 | $1,000.00 | $1,400.00 | $7,500.00 | $2,200.00 | $1,200.00 |
| 0480 | 15 in. or allowed substitute group A flared end section (7320615A) | EACH | 2 | $1,528.86 | $500.00 | $1,560.00 | $1,800.00 | $1,650.00 | $1,700.00 |
| 0490 | 18 in. or allowed substitute group A flared end section (7320618A) | EACH | 3 | $1,014.86 | $625.00 | $1,850.00 | $2,500.00 | $2,350.00 | $950.00 |
| 0500 | Mulching (8025006) | ACRE | 0.70 | $500.00 | $500.00 | $515.00 | $3,000.00 | $700.00 | $580.00 |
| 0510 | Turf type tall fescue sodding (8031000A) | SY | 3,965 | $11.25 | $12.30 | $11.60 | $15.00 | $12.00 | $13.00 |
| 0520 | Sediment trap excavation (8061003) | CY | 10 | $50.00 | $50.00 | $90.00 | $100.00 | $37.50 | $75.00 |
| 0530 | Sediment trap rock (8061004) | CY | 10 | $30.00 | $50.00 | $152.00 | $500.00 | $100.00 | $230.00 |
| 0540 | Alternate ditch check (8061006) | LF | 168 | $3.00 | $3.50 | $3.10 | $32.00 | $4.00 | $3.50 |
| 0550 | Curb inlet check (8061007A) | EACH | 6 | $50.00 | $55.00 | $156.00 | $100.00 | $64.00 | $60.00 |
| 0560 | Temporary seeding (8061017) | ACRE | 0.70 | $500.00 | $550.00 | $515.00 | $5,000.00 | $650.00 | $580.00 |
| 0570 | Silt fence (8061019) | LF | 281 | $3.00 | $3.50 | $4.00 | $4.00 | $4.00 | $3.50 |
| 0580 | Type 3B erosion control blanket (8064140) | SY | 11 | $10.00 | $11.00 | $10.30 | $30.00 | $12.50 | $12.00 |
| 0590 | Conduit, 4 in. rigid, in trench (9013004) | LF | 122 | $30.00 | $33.00 | $30.85 | $30.00 | $30.00 | $35.00 |
| 0600 | Pull box, preformed class 1 (9016110) | EACH | 2 | $2,100.00 | $2,300.00 | $2,160.00 | $2,100.00 | $2,100.00 | $2,450.00 |
| 0610 | Misc.conduit, 1.5 in. rigid, in trench (9019903) | LF | 617 | $20.00 | $22.00 | $20.60 | $20.00 | $20.00 | $24.00 |
| 0620 | Concrete footings, embedded (9031010) | CY | 0.40 | $600.00 | $660.00 | $1,030.00 | $1,000.00 | $1,000.00 | $700.00 |
| 0630 | Pipe posts (9031220) | LB | 190 | $12.00 | $13.50 | $15.40 | $15.00 | $15.00 | $14.00 |
| 0640 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 18 | $220.00 | $240.00 | $360.00 | $350.00 | $350.00 | $255.00 |
| 0650 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 384 | $20.00 | $22.00 | $20.60 | $20.00 | $20.00 | $24.00 |
| 0660 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 16 | $125.00 | $140.00 | $257.00 | $250.00 | $250.00 | $145.00 |
| 0670 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 18 | $250.00 | $20.00 | $309.00 | $300.00 | $300.00 | $290.00 |
| 0680 | SH-flat sheet (9035004A) | SF | 115 | $30.00 | $33.00 | $20.60 | $20.00 | $20.00 | $35.00 |
| 0690 | SHF-flat sheet fluorescent (9035069A) | SF | 146 | $40.00 | $44.00 | $20.60 | $20.00 | $20.00 | $47.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.