NJDOT contract 25105 bid tabulation
Re-advertisement of Route 15, Bridge over Paulins Kill. Let by New Jersey DOT on April 10, 2025, Sussex, N1. 3 bids received; low bid $4,648,000 by Colonnelli Brothers, Inc..
- Owner
- New Jersey DOT
- Letting
- 10 APR 2025
- Pay items
- 114
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Colonnelli Brothers, Inc. | $4,648,000 | Low |
| 2 | Ritacco Construction, Inc. | $5,262,000 | +13% |
| 3 | New Prince Concrete Construction Co., Inc. | $6,184,338 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Colonnelli Brothers, Inc. | 2. Ritacco Construction, Inc. | 3. New Prince Concrete Construction Co., Inc. |
|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $35,000 | $35,000 | $40,000 |
| 0002 | Progress schedule (153003P) | LS | 1 | $5,000.00 | $7,500.00 | $15,000 |
| 0003 | Progress schedule update (153005M) | U | 12 | $750.00 | $100.00 | $2,000.00 |
| 0004 | Trainees (153011M) | HR | 1,440 | $5.00 | $1.00 | $1.00 |
| 0005 | Mobilization (154003P) | LS | 1 | $325,000 | $526,200 | $750,000 |
| 0006 | Field office type F set UP (155018M) | U | 1 | $20,000 | $20,000 | $75,000 |
| 0007 | Field office type F maintenance (155036M) | MO | 27 | $1,500.00 | $2,750.00 | $4,000.00 |
| 0008 | Nuclear density gauge (156015M) | U | 1 | $2,500.00 | $9,500.00 | $15,000 |
| 0009 | Concrete compression testing equipment (156021M) | U | 1 | $3,500.00 | $9,500.00 | $10,000 |
| 0010 | Heavy duty silt fence, orange (158009M) | LF | 910 | $8.00 | $8.00 | $10.00 |
| 0011 | Inlet filter type 2, 4' X 4' (158033M) | U | 2 | $150.00 | $200.00 | $150.00 |
| 0012 | Temporary inlet sediment trap (158036M) | U | 2 | $300.00 | $500.00 | $150.00 |
| 0013 | Floating turbidity barrier, type 2 (158045M) | LF | 200 | $35.00 | $30.00 | $100.00 |
| 0014 | Dewatering basin (158051M) | U | 2 | $5,000.00 | $1,000.00 | $1.00 |
| 0015 | Concrete washout system (158063P) | LS | 1 | $4,000.00 | $9,500.00 | $5,000.00 |
| 0016 | Oil only emergency spill kit, type 1 (158072M) | U | 2 | $850.00 | $600.00 | $2,500.00 |
| 0017 | Erosion control sediment removal (158084M) | CY | 20 | $35.00 | $10.00 | $1.00 |
| 0018 | Biological surveys (158085P) | LS | 1 | $15,000 | $9,500.00 | $40,000 |
| 0019 | Breakaway barricade (159003M) | U | 30 | $45.00 | $20.00 | $150.00 |
| 0020 | Drum (159006M) | U | 200 | $40.00 | $10.00 | $100.00 |
| 0021 | Traffic cone (159009M) | U | 200 | $22.00 | $1.00 | $25.00 |
| 0022 | Construction signs (159012M) | SF | 889 | $17.00 | $20.00 | $25.00 |
| 0023 | Construction identification sign, 4' X 8' (159015M) | U | 2 | $1,000.00 | $1,500.00 | $2,500.00 |
| 0024 | Construction barrier curb (159021P) | LF | 600 | $55.00 | $10.00 | $120.00 |
| 0025 | Arrow board, 4' X 8' (159027M) | U | 2 | $1,000.00 | $500.00 | $7,500.00 |
| 0026 | Portable variable message sign (159030M) | U | 2 | $25,000 | $1,500.00 | $25,000 |
| 0027 | Traffic control truck with mounted crash cushion (159108M) | U | 2 | $20,000 | $2,500.00 | $30,000 |
| 0028 | Temporary pavement markings (159132M) | SF | 60 | $8.00 | $15.00 | $10.00 |
| 0029 | Temporary crash cushion, low maintenance compressive barrier, type 2, width narrow (159236M) | U | 10 | $7,500.00 | $100.00 | $1.00 |
| 0030 | Traffic stripes, latex, 4" (159300M) | LF | 4,000 | $1.00 | $1.00 | $1.00 |
| 0031 | Traffic markings lines, latex, 24" (159314M) | LF | 60 | $10.00 | $3.00 | $5.00 |
| 0032 | Fuel price adjustment (160004M) | DOL | 1 | $1,900.00 | $1,900.00 | $1,900.00 |
| 0033 | Asphalt price adjustment (160007M) | DOL | 1 | $3,100.00 | $3,100.00 | $3,100.00 |
| 0034 | Final cleanup (161003P) | LS | 1 | $12,500 | $10,500 | $10,000 |
| 0035 | Clearing site (201003P) | LS | 1 | $250,000 | $50,000 | $50,000 |
| 0036 | Stripping (202003P) | ACRE | 0.20 | $50,000 | $1.00 | $1,000.00 |
| 0037 | Excavation, unclassified (202009P) | CY | 1,166 | $60.00 | $90.00 | $65.00 |
| 0038 | I-9 soil aggregate (203009P) | CY | 128 | $55.00 | $70.00 | $230.00 |
| 0039 | Subbase (301006P) | CY | 172 | $55.00 | $70.00 | $170.00 |
| 0040 | Dense-graded aggregate base course, 6" thick (302036P) | SY | 725 | $12.00 | $20.00 | $40.00 |
| 0041 | Dense-graded aggregate base course, 8" thick (302042P) | SY | 413 | $16.00 | $25.00 | $40.00 |
| 0042 | HMA milling, 3" or less (401009P) | SY | 3,252 | $15.00 | $12.00 | $10.00 |
| 0043 | Polymerized joint adhesive (401027M) | LF | 400 | $3.00 | $2.00 | $12.00 |
| 0044 | Tack coat (401030M) | GAL | 500 | $5.00 | $2.00 | $0.01 |
| 0045 | Prime coat (401036M) | GAL | 400 | $5.00 | $0.01 | $0.01 |
| 0046 | Hot mix asphalt 12.5 M 64 surface course (401054M) | T | 543 | $165.00 | $235.00 | $120.00 |
| 0047 | Hot mix asphalt 12.5 M 64 intermediate course (401072M) | T | 318 | $165.00 | $205.00 | $120.00 |
| 0048 | Hot mix asphalt 25 M 64 base course (401099M) | T | 650 | $170.00 | $175.00 | $125.00 |
| 0049 | Core samples, hot mix asphalt (401108M) | U | 10 | $1,000.00 | $150.00 | $1.00 |
| 0050 | Temporary sheeting (501003P) | SF | 368 | $125.00 | $10.00 | $250.00 |
| 0051 | Retaining wall, location no. ___ 1 (513003P) | SF | 240 | $225.00 | $70.00 | $200.00 |
| 0052 | Stone facing 1 (515004P) | SF | 100 | $135.00 | $70.00 | $200.00 |
| 0053 | 15" reinforced concrete pipe (601122P) | LF | 52 | $100.00 | $125.00 | $150.00 |
| 0054 | Subbase outlet drain (601404P) | LF | 42 | $50.00 | $40.00 | $100.00 |
| 0055 | Inlet, type B (602012M) | U | 2 | $5,200.00 | $10,500 | $5,000.00 |
| 0056 | Concrete sidewalk, 4" thick (606012P) | SY | 260 | $65.00 | $50.00 | $130.00 |
| 0057 | Concrete driveway, 6" thick (606051P) | SY | 21 | $100.00 | $150.00 | $150.00 |
| 0058 | Concrete steps (606112P) | LS | 1 | $8,500.00 | $5,500.00 | $8,000.00 |
| 0059 | 9" X 18" concrete vertical curb (607021P) | LF | 399 | $45.00 | $35.00 | $80.00 |
| 0060 | Nonvegetative surface, porous hot mix asphalt, 6" thick (608005P) | SY | 36 | $75.00 | $70.00 | $60.00 |
| 0061 | Beam guide rail (609003M) | LF | 163 | $75.00 | $70.00 | $90.00 |
| 0062 | Tangent guide rail terminal (609027M) | U | 6 | $6,000.00 | $4,500.00 | $5,400.00 |
| 0063 | Beam guide rail anchorage (609039M) | U | 1 | $6,000.00 | $2,500.00 | $3,000.00 |
| 0064 | Approach guide rail transition TL-2 (609058M) | U | 1 | $6,000.00 | $2,500.00 | $3,000.00 |
| 0065 | Removal of beam guide rail (609075M) | LF | 688 | $10.00 | $1.00 | $1.00 |
| 0066 | Traffic stripes, 4" (610003M) | LF | 4,900 | $1.00 | $1.00 | $1.25 |
| 0067 | Traffic markings (610009M) | SF | 30 | $30.00 | $30.00 | $40.00 |
| 0068 | RPM, mono-directional, white lens (610012M) | U | 10 | $80.00 | $75.00 | $100.00 |
| 0069 | RPM, mono-directional, amber lens (610018M) | U | 10 | $80.00 | $75.00 | $100.00 |
| 0070 | Removal of RPM (610024M) | U | 5 | $50.00 | $25.00 | $100.00 |
| 0071 | Rumble strip (610033M) | LF | 450 | $25.00 | $10.00 | $32.00 |
| 0072 | Crash cushion, compressive barrier, type 2, width narrow (611300M) | U | 2 | $30,000 | $35,000 | $35,000 |
| 0073 | Specialized sign (612033P) | U | 1 | $2,000.00 | $8,500.00 | $10,000 |
| 0074 | Temporary traffic signal system, location no. ___ 1 (702054M) | LS | 1 | $165,000 | $285,000 | $380,000 |
| 0075 | Temporary highway lighting system (703033P) | LS | 1 | $50,000 | $135,000 | $110,000 |
| 0076 | Topsoil spreading __" thick 4 inch (804000P) | SY | 705 | $10.00 | $3.00 | $24.00 |
| 0077 | Topsoil spreading __" thick 6 inch (804000P) | SY | 450 | $10.00 | $4.00 | $22.00 |
| 0078 | Plant pit soil (804014P) | CY | 26 | $50.00 | $90.00 | $108.00 |
| 0079 | Borrow topsoil (804015P) | CY | 117 | $50.00 | $50.00 | $102.00 |
| 0080 | Fertilizing and seeding, type A (806003P) | SY | 705 | $3.00 | $2.00 | $4.00 |
| 0081 | Fertilizing and seeding, type F (806018P) | SY | 100 | $3.00 | $4.00 | $10.00 |
| 0082 | Straw mulching (809003M) | SY | 705 | $3.00 | $1.50 | $4.00 |
| 0083 | Stone mulching (809009M) | SY | 120 | $35.00 | $50.00 | $45.00 |
| 0084 | Wood mulching, 2" thick (809021M) | SY | 450 | $10.00 | $4.00 | $9.00 |
| 0085 | Large deciduous tree, 2-2 1/2" caliper, B&B (811006M) | U | 1 | $750.00 | $800.00 | $930.00 |
| 0086 | Small deciduous tree, 2-2 1/2" caliper, B&B (811024M) | U | 8 | $100.00 | $700.00 | $810.00 |
| 0087 | Small deciduous tree, 6-7' high B&B (811029M) | U | 7 | $100.00 | $500.00 | $690.00 |
| 0088 | Deciduous shrub, 18-24" high, #3 container (811063M) | U | 70 | $100.00 | $60.00 | $78.00 |
| 0089 | Deciduous shrub, 24-36" high, container comus sericea (811067M) | U | 26 | $50.00 | $90.00 | $114.00 |
| 0090 | Deciduous shrub, 24-36" high, container lindera benzoin (811067M) | U | 28 | $50.00 | $90.00 | $114.00 |
| 0091 | Evergreen shrub, 18-24" high, #3 container lles glabra "shamrock" 3 - 4' (811078M) | U | 37 | $50.00 | $60.00 | $78.00 |
| 0092 | Perennial, 2" plug (811120M) | U | 325 | $5.00 | $6.00 | $6.00 |
| 0093 | Plant establishment and maintenance period (811138M) | LS | 1 | $12,500 | $1,500.00 | $15,000 |
| 0094 | Watering (811165M) | MG | 8 | $550.00 | $150.00 | $600.00 |
| 0095 | Steel edging (812006P) | LF | 185 | $40.00 | $40.00 | $46.00 |
| 0096 | Vibration monitoring (162006P) | LS | 1 | $25,000 | $55,000 | $45,000 |
| 0097 | Clearing site, bridge (___) 1922-150 (201006P) | LS | 1 | $250,000 | $150,000 | $150,000 |
| 0098 | Temporary shielding (201039P) | LS | 1 | $35,000 | $150,000 | $150,000 |
| 0099 | Excavation, unclassified (202009P) | CY | 1,640 | $50.00 | $50.00 | $65.00 |
| 0100 | Rock dowel (202013M) | U | 59 | $100.00 | $200.00 | $50.00 |
| 0101 | I-9 soil aggregate (203009P) | CY | 530 | $55.00 | $70.00 | $85.00 |
| 0102 | Temporary cofferdam (501009P) | LS | 1 | $492,500 | $771,061 | $300,000 |
| 0103 | Reinforcement steel, epoxy- coated (504006P) | LB | 46,000 | $3.00 | $2.00 | $2.85 |
| 0104 | Concrete footing (504015P) | CY | 325 | $650.00 | $800.00 | $1,800.00 |
| 0105 | Concrete wing wall (504018P) | CY | 50 | $1,500.00 | $2,000.00 | $3,500.00 |
| 0106 | Precast concrete culvert (505057P) | LF | 55 | $7,500.00 | $8,000.00 | $7,500.00 |
| 0107 | Concrete bridge deck, HPC (507024P) | CY | 85 | $1,450.00 | $1,250.00 | $3,500.00 |
| 0108 | Date panel (507027M) | U | 2 | $2,000.00 | $2,000.00 | $10,000 |
| 0109 | Concrete bridge sidewalk, HPC (507033P) | CY | 10 | $2,000.00 | $1,500.00 | $1,800.00 |
| 0110 | Concrete bridge parapet, HPC (507039P) | LF | 105 | $500.00 | $500.00 | $1,020.00 |
| 0111 | Concrete bridge approach (507051P) | CY | 140 | $700.00 | $900.00 | $1,740.00 |
| 0112 | Temporary structure, two- way (514006P) | LS | 1 | $534,649 | $750,000 | $500,000 |
| 0113 | 8" perforated high density polyethylene pipe (601419P) | LF | 175 | $50.00 | $60.00 | $65.00 |
| 0114 | 3" rigid metallic conduit (701021P) | LF | 200 | $50.00 | $60.00 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of April 10, 2025. Compiled by Mirage Metrics.