Colonnelli Brothers, Inc.: NJDOT bid record
Colonnelli Brothers, Inc. submitted 37 bids on New Jersey DOT contracts in the data, from 01 OCT 2020 to 09 APR 2026, and was the low bidder on 12 of them (32%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- New Jersey DOT
- Low bid volume
- $41,630,355
- Latest bid
- 09 APR 2026
- Data through
- 16 APR 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 3 | 0 | 0% |
| 2021 | 5 | 0 | 0% |
| 2022 | 4 | 3 | 75% |
| 2023 | 5 | 1 | 20% |
| 2024 | 5 | 3 | 60% |
| 2025 | 12 | 3 | 25% |
| 2026 | 3 | 2 | 67% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| H4 | 10 | 4 | 40% |
| C4 | 9 | 2 | 22% |
| N4 | 7 | 3 | 43% |
| S4 | 4 | 1 | 25% |
| N1 | 4 | 2 | 50% |
| C1 | 3 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Overtime differential (OD) | MMG025M | DOL | 16 | 16 (100%) | $1.00 | $1.00 |
| Solid waste disposal | MMB173M | DOL | 16 | 16 (100%) | $1.00 | $1.00 |
| Crew coordinator | MMB092M | HR | 16 | 16 (100%) | $125.00 | $135.00 |
| Disposal of regulated material, hazardous | MMG064M | DOL | 16 | 16 (100%) | $1.00 | $1.00 |
| Telephone service | MMG010M | DOL | 11 | 11 (100%) | $1.00 | $1.00 |
| Excavation, unclassified | 202009P | CY | 13 | 8 (62%) | $60.00 | $78.60 |
| Construction signs | 159012M | SF | 10 | 8 (80%) | $15.00 | $15.00 |
| Force account | 109006M | DOL | 8 | 8 (100%) | $1.00 | $1.00 |
| Disposal of regulated material | MMG027M | DOL | 8 | 8 (100%) | $1.00 | $1.00 |
| I-9 soil aggregate | 203009P | CY | 7 | 7 (100%) | $60.00 | $85.00 |
| Disposal of regulated material | 202024M | T | 10 | 6 (60%) | $50.00 | $50.00 |
| Adjustment factor , (force account) | MMG095M | PCT | 8 | 6 (75%) | $1.00 | $1.10 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Iew Construction Group, Inc. | 32 | 13 of 32 |
| Joseph M. Sanzari, Inc. | 24 | 12 of 24 |
| Mount Construction Co., Inc. | 11 | 7 of 11 |
| Ferreira Construction Co., Inc. | 8 | 2 of 8 |
| Konkus Corporation | 8 | 4 of 8 |
| Berto Construction, Inc. | 6 | 2 of 6 |
| Sparwick Contracting, Inc. | 6 | 4 of 6 |
| Ritacco Construction, Inc. | 6 | 2 of 6 |
| Railroad Construction Company, Inc. | 5 | 1 of 5 |
| Diaco Contracting, Inc. DBA Grade Construction | 5 | 3 of 5 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 09 APR 2026 | 26451 | N4 | MTN JOC Infrastructure North 2026 | 1 of 2 | $968,182 | Low, 46% under the second |
| 24 MAR 2026 | 26438 | C4 | MTN Infrastructure Repair Central - 2026 | 1 of 4 | $6,869,518 | Low, 7.0% under the second |
| 12 FEB 2026 | 25139 | C1 | Route 36, Bridge over Troutman's Creek | 2 of 9 | $8,335,105 | +5.0% |
| 23 DEC 2025 | 26433 | S4 | MTN STORMWATER FACILITY RES SOUTH 2026 | 1 of 2 | $5,177,752 | Low, 3.0% under the second |
| 20 NOV 2025 | 25422 | H4 | MTN JOC Basin Restoration Contract, Statewide 2025 | 1 of 3 | $2,575,250 | Low, 30% under the second |
| 28 OCT 2025 | 25468 | N4 | Re-Advertisement Drainage Restoration Contract, North-2025 | 2 of 3 | $11,861,988 | +6.0% |
| 14 OCT 2025 | 26426 | C4 | MTN CONCRETE STRUC. REP. CENTRAL - 2026 | 2 of 4 | $7,373,572 | +5.0% |
| 09 OCT 2025 | 26425 | N4 | MTN CONCRETE STRUC. REP. NORTH - 2026 | 2 of 3 | $12,541,172 | +2.0% |
| 29 MAY 2025 | 25108 | C1 | ROUTE 78 WB, BRIDGE OVER TRIBUTARY OF DEAD RIVER | 6 of 8 | $8,492,700 | +38% |
| 15 APR 2025 | 25418 | H4 | Bridge Preventive MTN and Painting 2025-2 | 4 of 4 | $8,556,888 | +23% |
| 10 APR 2025 | 25105 | N1 | Re-advertisement of Route 15, Bridge over Paulins Kill | 1 of 3 | $4,648,000 | Low, 13% under the second |
| 10 APR 2025 | 25415 | H4 | Bridge Preventive MTN and Painting 2025-1 | 3 of 5 | $12,361,538 | +47% |
| 20 MAR 2025 | 25439 | S4 | MTN Infrastructure Repair South - 2025 | 3 of 4 | $4,621,818 | +13% |
| 18 MAR 2025 | 25438 | C4 | MTN Infrastructure Repair Central - 2025 | 3 of 7 | $6,293,783 | +5.0% |
| 28 JAN 2025 | 24153 | C1 | GROVE AVENUE, BRIDGE OVER PORT READING RAILROAD | 2 of 11 | $10,400,000 | +4.0% |
| 19 DEC 2024 | 24440 | H4 | MTN JOC Basin Restoration Contract, Statewide 2024 | 1 of 4 | $3,257,000 | Low, 4.0% under the second |
| 21 NOV 2024 | 25432 | C4 | MTN STORMWATER FACILITY RES CENTRAL 2025 | 2 of 2 | $9,876,342 | +4.0% |
| 07 NOV 2024 | 25429 | C4 | MTN STEEL & ALUMINUM REP. CENTRAL- 2025 | 2 of 3 | $9,450,252 | +5.0% |
| 17 SEP 2024 | 25455 | C4 | MTN ORPHAN BRIDGE REP. CENTRAL-2025 | 1 of 5 | $1,907,822 | Low, 2.0% under the second |
| 30 MAY 2024 | 24451 | N4 | MTN JOC Infrastructure Repairs, North-2024 | 1 of 4 | $3,329,400 | Low, 2.0% under the second |
| 31 OCT 2023 | 23157 | N1 | Rt. 80, Exit 55, Culvert | 5 of 5 | $2,498,000 | +69% |
| 12 OCT 2023 | 23132 | N1 | Route 23 NB Bridge Over Pequannock River Bridge Improvements | 2 of 5 | $7,443,141 | +1.0% |
| 10 AUG 2023 | 23457 | H4 | MTN JOC Basin Restoration Contract, Statewide 2023 | 3 of 4 | $3,072,000 | +3.0% |
| 23 MAY 2023 | 23466 | C4 | MTN ORPHAN BRIDGE REP. CENTRAL-2023 | 2 of 6 | $1,681,164 | +3.0% |
| 18 MAY 2023 | 23465 | N4 | MTN ORPHAN BRIDGE REP. NORTH-2023 | 1 of 7 | $1,464,164 | Low, 9.0% under the second |
How this record was read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Every bid counted here matched its published total to within one dollar; NJDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.