NJDOT contract 25415 bid tabulation
Bridge Preventive MTN and Painting 2025-1. Let by New Jersey DOT on April 10, 2025, Bergen, Hudson, Passaic, H4. 5 bids received; low bid $8,398,000 by Joseph M. Sanzari, Inc..
- Owner
- New Jersey DOT
- Letting
- 10 APR 2025
- Pay items
- 58
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Joseph M. Sanzari, Inc. | $8,398,000 | Low |
| 2 | Power Concrete Co., Inc. | $10,724,469 | +28% |
| 3 | Colonnelli Brothers, Inc. | $12,361,538 | +47% |
| 4 | Berto Construction, Inc. | $13,227,973 | +58% |
| 5 | Iew Construction Group, Inc. | $14,174,641 | +69% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Joseph M. Sanzari, Inc. | 2. Power Concrete Co., Inc. | 3. Colonnelli Brothers, Inc. | 4. Berto Construction, Inc. | 5. Iew Construction Group, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0002 | Trainees (153011M) | HR | 2,210 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 |
| 0003 | Mobilization (154003P) | LS | 1 | $405,000 | $422,000 | $615,000 | $660,000 | $700,000 |
| 0004 | Testing, IF and where directed (MMG086M) | DOL | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Breakaway barricade (159003M) | U | 104 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 |
| 0006 | Drum (159006M) | U | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 |
| 0007 | Traffic cone (159009M) | U | 3,000 | $1.00 | $0.50 | $1.00 | $1.00 | $0.01 |
| 0008 | Construction signs (159012M) | SF | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $0.01 |
| 0009 | Arrow board, 4' X 8' (159027M) | U | 8 | $500.00 | $100.00 | $1.00 | $1.00 | $0.01 |
| 0010 | Portable variable message sign W/remote communication (159029M) | U | 8 | $500.00 | $500.00 | $1.00 | $1.00 | $1,000.00 |
| 0011 | Traffic control truck with mounted crash cushion (159108M) | U | 8 | $500.00 | $500.00 | $1.00 | $1.00 | $1,000.00 |
| 0012 | Traffic director, flagger (159141M) | HR | 1,000 | $100.00 | $110.00 | $125.00 | $0.01 | $100.00 |
| 0013 | Traffic stripes, latex, 4" (159300M) | LF | 1,000 | $1.00 | $2.00 | $1.00 | $5.00 | $2.46 |
| 0014 | Clearing site (201003P) | LS | 1 | $26,864 | $20,000 | $20,000 | $38,000 | $5,000.00 |
| 0015 | Traffic stripes, 4" (610003M) | LF | 15,000 | $1.00 | $2.00 | $1.00 | $2.00 | $1.47 |
| 0016 | Traffic markings symbols (610060M) | SF | 2,000 | $5.00 | $8.50 | $8.00 | $10.00 | $12.28 |
| 0017 | Railroad protective liability insurance (152012P) | DOL | 25,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Pollution liability insurance (152015P) | DOL | 22,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0019 | Concrete deck repair, type C (551009M) | SF | 350 | $100.00 | $150.00 | $350.00 | $300.00 | $300.00 |
| 0020 | Railroad services (MMB188M) | DOL | 70,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0021 | Chain-link fence, aluminum- coated steel, 6' high (605009P) | LF | 500 | $40.00 | $60.00 | $150.00 | $75.00 | $72.44 |
| 0022 | Field office type F set UP (155018M) | U | 1 | $29,000 | $50,405 | $20,000 | $30,000 | $52,803 |
| 0023 | Field office type F maintenance (155036M) | MO | 15 | $4,000.00 | $3,000.00 | $3,000.00 | $5,000.00 | $5,485.11 |
| 0024 | HMA patch (159138M) | T | 225 | $120.00 | $200.00 | $250.00 | $1,000.00 | $306.97 |
| 0025 | Epoxy waterproofing (504036P) | SY | 3,700 | $45.00 | $60.00 | $45.00 | $55.00 | $80.63 |
| 0026 | Lubricate bearing (506013P) | U | 1,025 | $80.00 | $30.00 | $80.00 | $70.00 | $119.08 |
| 0027 | Clean existing scuppers and pipes (508005M) | U | 65 | $150.00 | $100.00 | $250.00 | $75.00 | $442.69 |
| 0028 | Concrete deck repair, type B (551006M) | SF | 7,200 | $82.00 | $130.00 | $332.00 | $150.00 | $141.51 |
| 0029 | Pressure injection, concrete cracks (552003M) | LF | 1,000 | $20.00 | $20.00 | $40.00 | $100.00 | $125.00 |
| 0030 | Substructure concrete repair (555003M) | SF | 5,000 | $135.00 | $185.00 | $300.00 | $350.00 | $460.91 |
| 0031 | Concrete sidewalk, 4" thick (606012P) | SY | 250 | $150.00 | $110.00 | $100.00 | $150.00 | $320.12 |
| 0032 | Bridge header repair (MMB070M) | LF | 2,000 | $250.00 | $120.00 | $200.00 | $250.00 | $271.55 |
| 0033 | Repair concrete curb (MMB077M) | LF | 100 | $70.00 | $100.00 | $80.00 | $250.00 | $226.94 |
| 0034 | Deck corrosion inhibitor (MMB086M) | SY | 97,000 | $13.00 | $10.00 | $12.00 | $19.00 | $10.00 |
| 0035 | Bridge deck power washing this includes superstructure and substructure (MMB201M) | SY | 70,000 | $3.00 | $2.00 | $3.75 | $9.00 | $3.68 |
| 0036 | Deck joint reseal (silicon) (MMB087M) | LF | 13,000 | $12.00 | $120.00 | $71.00 | $75.00 | $100.00 |
| 0037 | Bridge deck crack sealing (MMB088M) | LF | 1,000 | $6.00 | $5.00 | $10.00 | $20.00 | $32.77 |
| 0038 | Deck joint repair (MMB089M) | LF | 12,700 | $112.00 | $120.00 | $125.00 | $125.00 | $100.00 |
| 0039 | Deck joint reseal (rubber asphalt) (MMB090M) | LF | 6,400 | $5.00 | $3.00 | $3.00 | $20.00 | $40.00 |
| 0040 | Methacrylate flood coat (MMB203M) | SY | 9,700 | $63.00 | $75.00 | $50.00 | $75.00 | $63.83 |
| 0041 | Sandblasting (MMG023M) | SF | 12,000 | $4.00 | $6.00 | $5.00 | $12.00 | $2.46 |
| 0042 | Flexible delineators, parapet mounted (MMB215M) | U | 600 | $20.00 | $40.00 | $30.00 | $25.00 | $31.21 |
| 0043 | Concrete parapet repair (MMG047M) | SF | 104 | $43.00 | $100.00 | $250.00 | $350.00 | $229.95 |
| 0044 | Containment system , 0211-153 (MMG082M) | LS | 1 | $105,600 | $100,000 | $218,000 | $130,000 | $443,507 |
| 0045 | SSPC, blast/prime , 0211-153 (MMG083M) | LS | 1 | $264,000 | $480,000 | $250,000 | $130,000 | $526,000 |
| 0046 | SSPC, stripe/intermediate , 0211-153 (MMG084M) | LS | 1 | $95,000 | $80,000 | $90,000 | $130,000 | $117,682 |
| 0047 | SSPC, finish , 0211-153 (MMG085M) | LS | 1 | $79,000 | $100,000 | $75,000 | $130,000 | $98,068 |
| 0048 | Final cleanup , 0211-153 (161003P) | LS | 1 | $16,600 | $10,000 | $10,000 | $130,000 | $13,076 |
| 0049 | Containment system , 0211-154 (MMG082M) | LS | 1 | $105,600 | $100,000 | $218,000 | $130,000 | $443,507 |
| 0050 | SSPC, blast/prime , 0211-154 (MMG083M) | LS | 1 | $264,000 | $480,000 | $250,000 | $130,000 | $526,000 |
| 0051 | SSPC, stripe/intermediate , 0211-154 (MMG084M) | LS | 1 | $95,000 | $80,000 | $90,000 | $130,000 | $117,682 |
| 0052 | SSPC, finish , 0211-154 (MMG085M) | LS | 1 | $80,000 | $100,000 | $75,000 | $130,000 | $98,068 |
| 0053 | Final cleanup , 0211-154 (161003P) | LS | 1 | $10,600 | $10,000 | $10,000 | $130,000 | $13,076 |
| 0054 | Containment system , 0211-155 (MMG082M) | LS | 1 | $105,600 | $90,000 | $218,000 | $130,000 | $365,320 |
| 0055 | SSPC, blast/prime , 0211-155 (MMG083M) | LS | 1 | $264,000 | $450,000 | $250,000 | $130,000 | $526,000 |
| 0056 | SSPC, stripe/intermediate , 0211-155 (MMG084M) | LS | 1 | $79,000 | $80,000 | $75,000 | $130,000 | $98,068 |
| 0057 | SSPC, finish , 0211-155 (MMG085M) | LS | 1 | $58,000 | $80,000 | $55,000 | $130,000 | $71,917 |
| 0058 | Final cleanup , 0211-155 (161003P) | LS | 1 | $10,600 | $10,000 | $10,000 | $130,000 | $13,076 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.