NJDOT contract 25108 bid tabulation
ROUTE 78 WB, BRIDGE OVER TRIBUTARY OF DEAD RIVER. Let by New Jersey DOT on May 29, 2025, Somerset, C1. 8 bids received; low bid $6,136,000 by Ritacco Construction, Inc..
- Owner
- New Jersey DOT
- Letting
- 29 MAY 2025
- Pay items
- 95
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ritacco Construction, Inc. | $6,136,000 | Low |
| 2 | Joseph M. Sanzari, Inc. | $6,998,613 | +14% |
| 3 | Iew Construction Group, Inc. | $7,198,811 | +17% |
| 4 | Union Paving & Construction Co., Inc. | $7,962,994 | +30% |
| 5 | Konkus Corporation | $8,323,923 | +36% |
| 6 | Colonnelli Brothers, Inc. | $8,492,700 | +38% |
| 7 | Ferreira Construction Co., Inc. | $8,899,472 | +45% |
| 8 | Carbro Constructors Corp. | $9,882,288 | +61% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ritacco Construction, Inc. | 2. Joseph M. Sanzari, Inc. | 3. Iew Construction Group, Inc. | 4. Union Paving & Construction Co., Inc. | 5. Konkus Corporation | 6. Colonnelli Brothers, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $35,000 | $57,000 | $36,444 | $35,000 | $100,000 | $45,000 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $25,000 | $10,000 | $0.01 | $10,000 | $15,000 | $10,000 |
| 0003 | Progress schedule (153003P) | LS | 1 | $8,000.00 | $3,500.00 | $0.01 | $8,000.00 | $5,500.00 | $10,000 |
| 0004 | Progress schedule update (153005M) | U | 10 | $250.00 | $400.00 | $0.01 | $1,000.00 | $0.01 | $2,500.00 |
| 0005 | Trainees (153011M) | HR | 1 | $1.00 | $300.00 | $0.01 | $0.01 | $0.01 | $5.00 |
| 0006 | Mobilization (154003P) | LS | 1 | $613,600 | $625,000 | $750,000 | $1,170,000 | $600,000 | $850,000 |
| 0007 | Field office type F set UP (155018M) | U | 1 | $20,000 | $50,000 | $48,916 | $45,000 | $30,000 | $35,000 |
| 0008 | Field office type F maintenance (155036M) | MO | 21 | $2,700.00 | $4,500.00 | $5,283.21 | $4,500.00 | $3,000.00 | $2,500.00 |
| 0009 | Materials field laboratory set-UP (156003M) | U | 1 | $35,000 | $50,000 | $56,351 | $35,000 | $0.01 | $25,000 |
| 0010 | Materials field laboratory maintenance (156006M) | MO | 21 | $3,000.00 | $3,500.00 | $4,397.59 | $3,500.00 | $0.01 | $1,500.00 |
| 0011 | Nuclear density gauge (156015M) | U | 1 | $10,000 | $10,000 | $12,216 | $10,000 | $0.01 | $2,500.00 |
| 0012 | Heavy duty silt fence, orange (158009M) | LF | 2,110 | $9.00 | $20.00 | $11.45 | $8.00 | $6.50 | $8.00 |
| 0013 | Inlet filter type 2, 2' X 4' (158030M) | U | 4 | $400.00 | $530.00 | $377.39 | $300.00 | $0.01 | $150.00 |
| 0014 | Construction driveway (158060M) | T | 683 | $40.00 | $190.00 | $65.90 | $110.00 | $0.01 | $55.00 |
| 0015 | Concrete washout system (158063P) | LS | 1 | $10,000 | $5,900.00 | $30,539 | $7,000.00 | $20,000 | $5,000.00 |
| 0016 | Oil only emergency spill kit, type 1 (158072M) | U | 2 | $500.00 | $1,620.00 | $1,343.71 | $1,000.00 | $0.01 | $850.00 |
| 0017 | Erosion control sediment removal (158084M) | CY | 21 | $20.00 | $1,130.00 | $113.57 | $0.01 | $0.01 | $35.00 |
| 0018 | Breakaway barricade (159003M) | U | 80 | $10.00 | $100.00 | $183.23 | $135.00 | $0.01 | $50.00 |
| 0019 | Drum (159006M) | U | 180 | $5.00 | $40.00 | $73.29 | $75.00 | $0.01 | $65.00 |
| 0020 | Traffic cone (159009M) | U | 180 | $1.00 | $12.00 | $24.98 | $30.00 | $0.01 | $25.00 |
| 0021 | Construction signs (159012M) | SF | 1,344 | $16.00 | $25.00 | $21.38 | $22.00 | $17.25 | $16.00 |
| 0022 | Construction identification sign, 6' X 12' (159018M) | U | 1 | $1,250.00 | $1,575.00 | $2,137.71 | $3,000.00 | $1,610.00 | $1,500.00 |
| 0023 | Construction barrier curb (159021P) | LF | 1,980 | $120.00 | $314.00 | $124.85 | $160.00 | $45.00 | $95.00 |
| 0024 | Portable variable message sign (159030M) | U | 4 | $1,000.00 | $15,000 | $11,767 | $13,000 | $0.01 | $15,000 |
| 0025 | Traffic control truck with mounted crash cushion (159108M) | U | 2 | $1,500.00 | $20,000 | $3,053.88 | $35,000 | $50,000 | $50,000 |
| 0026 | HMA patch (159138M) | T | 5 | $300.00 | $500.00 | $765.81 | $600.00 | $0.01 | $250.00 |
| 0027 | Snow removal (159190M) | LS | 1 | $5,000.00 | $10,000 | $37,824 | $0.01 | $0.01 | $50,000 |
| 0028 | Temporary crash cushion, compressive barrier, type 3, width narrow (159212M) | U | 2 | $20,000 | $60,000 | $39,621 | $35,000 | $30,000 | $15,000 |
| 0029 | Temporary crash cushion, compressive barrier, type 3, width medium (159215M) | U | 1 | $20,000 | $45,000 | $21,403 | $35,000 | $30,000 | $20,000 |
| 0030 | Construction identification sign, iija 8' X 5' (159262M) | U | 1 | $900.00 | $1,575.00 | $1,997.87 | $3,000.00 | $1,092.50 | $1,000.00 |
| 0031 | Fuel price adjustment (160004M) | DOL | 1 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 | $1,900.00 |
| 0032 | Asphalt price adjustment (160007M) | DOL | 1 | $3,800.00 | $3,800.00 | $3,800.00 | $3,800.00 | $3,800.00 | $3,800.00 |
| 0033 | Steel price adjustment (160009M) | DOL | 1 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0034 | Final cleanup (161003P) | LS | 1 | $10,500 | $20,000 | $5,000.00 | $1,000.00 | $0.01 | $50,000 |
| 0035 | Clearing site (201003P) | LS | 1 | $30,000 | $50,000 | $30,000 | $30,000 | $20,000 | $550,000 |
| 0036 | Stripping (202003P) | ACRE | 2 | $1,000.00 | $25,000 | $68,406 | $0.01 | $0.01 | $12,500 |
| 0037 | Excavation, unclassified (202009P) | CY | 358 | $50.00 | $120.00 | $222.42 | $125.00 | $50.00 | $60.00 |
| 0038 | Dense-graded aggregate base course, 6" thick (302036P) | SY | 916 | $20.00 | $30.00 | $37.22 | $30.00 | $17.00 | $15.00 |
| 0039 | HMA milling, 3" or less (401009P) | SY | 7,225 | $7.00 | $5.00 | $6.56 | $11.00 | $6.32 | $20.00 |
| 0040 | Polymerized joint adhesive (401027M) | LF | 4,568 | $0.10 | $1.00 | $0.11 | $1.00 | $0.10 | $4.00 |
| 0041 | Tack coat (401030M) | GAL | 800 | $0.10 | $1.00 | $0.11 | $0.01 | $0.10 | $5.00 |
| 0042 | Hot mix asphalt 12.5 M E surface course (401061M) | T | 1,066 | $175.00 | $170.00 | $200.64 | $170.00 | $193.32 | $165.00 |
| 0043 | Hot mix asphalt 25 M 64 base course (401099M) | T | 540 | $210.00 | $210.00 | $283.53 | $160.00 | $230.00 | $210.00 |
| 0044 | Core samples, hot mix asphalt (401108M) | U | 15 | $150.00 | $154.00 | $171.25 | $225.00 | $150.00 | $1,000.00 |
| 0045 | Fog seal strip (422004M) | LF | 3,819 | $2.00 | $2.00 | $1.43 | $40.00 | $2.00 | $1.00 |
| 0046 | Temporary sheeting (501003P) | SF | 250 | $10.00 | $400.00 | $0.01 | $0.01 | $0.01 | $150.00 |
| 0047 | Reset existing casting (602099M) | U | 1 | $2,000.00 | $1,300.00 | $3,094.42 | $800.00 | $350.00 | $1,000.00 |
| 0048 | Cleaning drainage structure (602216M) | U | 2 | $500.00 | $3,500.00 | $2,283.28 | $800.00 | $500.00 | $2,000.00 |
| 0049 | 9" X 16" concrete vertical curb (607018P) | LF | 72 | $80.00 | $97.00 | $331.08 | $55.00 | $135.00 | $45.00 |
| 0050 | Nonvegetative surface, hot mix asphalt (608003P) | SY | 1,089 | $40.00 | $43.00 | $46.81 | $50.00 | $40.00 | $50.00 |
| 0051 | Beam guide rail (609003M) | LF | 1,329 | $36.00 | $40.00 | $43.38 | $42.00 | $42.90 | $42.00 |
| 0052 | Beam guide rail, dual-faced (609006M) | LF | 288 | $56.00 | $59.00 | $64.50 | $60.00 | $46.20 | $65.00 |
| 0053 | Tangent guide rail terminal (609027M) | U | 1 | $3,600.00 | $3,832.00 | $4,166.98 | $4,000.00 | $4,345.00 | $4,500.00 |
| 0054 | Beam guide rail anchorage (609039M) | U | 2 | $1,600.00 | $1,785.00 | $1,940.79 | $2,000.00 | $1,375.00 | $2,500.00 |
| 0055 | Approach guide rail transition TL-3 (609059M) | U | 2 | $4,300.00 | $4,557.00 | $4,954.71 | $5,000.00 | $4,950.00 | $5,000.00 |
| 0056 | Removal of beam guide rail (609075M) | LF | 1,874 | $4.00 | $15.00 | $5.42 | $5.00 | $0.01 | $10.00 |
| 0057 | Traffic stripes, 6" (610006M) | LF | 24,992 | $0.80 | $1.00 | $0.68 | $0.70 | $0.97 | $1.00 |
| 0058 | RPM, mono-directional, white lens (610012M) | U | 50 | $50.00 | $40.00 | $45.09 | $45.00 | $65.00 | $65.00 |
| 0059 | Traffic marking lines, 12" (610016M) | LF | 556 | $3.00 | $4.00 | $4.11 | $4.00 | $3.50 | $4.00 |
| 0060 | RPM, mono-directional, amber lens (610018M) | U | 25 | $50.00 | $40.00 | $45.09 | $45.00 | $65.00 | $65.00 |
| 0061 | Removal of RPM (610024M) | U | 75 | $50.00 | $75.00 | $87.63 | $45.00 | $0.01 | $50.00 |
| 0062 | Rumble strip (610033M) | LF | 1,505 | $10.00 | $9.00 | $10.24 | $13.00 | $16.00 | $30.00 |
| 0063 | Removal of traffic stripes (610036M) | LF | 20,371 | $0.95 | $1.00 | $0.86 | $0.85 | $2.00 | $1.00 |
| 0064 | Removal of rumble strip (610038M) | LF | 1,505 | $25.00 | $31.00 | $32.71 | $13.00 | $35.00 | $25.00 |
| 0065 | Topsoil spreading __" thick topsoil spreading 4" thick (804000P) | SY | 2,596 | $5.00 | $15.00 | $9.30 | $3.00 | $1.00 | $8.00 |
| 0066 | Fertilizing and seeding, type A-3 (806006P) | SY | 2,596 | $1.50 | $2.00 | $2.11 | $2.50 | $1.00 | $3.00 |
| 0067 | Straw mulching (809003M) | SY | 2,596 | $1.00 | $1.00 | $1.26 | $2.50 | $1.00 | $3.00 |
| 0068 | Vibration monitoring (162006P) | LS | 1 | $90,000 | $80,000 | $49,890 | $75,000 | $75,000 | $100,000 |
| 0069 | Clearing site, bridge (___) structure no. 1817-167 (201006P) | LS | 1 | $220,000 | $621,129 | $220,000 | $220,000 | $220,000 | $1,270,060 |
| 0070 | Asbestos removal, bridge no. ___ 1817-167 (201037P) | LS | 1 | $5,000.00 | $60,000 | $58,889 | $7,000.00 | $82,200 | $50,000 |
| 0071 | Temporary shielding (201039P) | LS | 1 | $750,484 | $336,000 | $120,350 | $777,000 | $3,275,000 | $201,948 |
| 0072 | Excavation, unclassified (202009P) | CY | 630 | $50.00 | $80.00 | $241.09 | $150.00 | $85.00 | $50.00 |
| 0073 | Coarse aggregate, size no. 57 (302060P) | CY | 54 | $90.00 | $200.00 | $268.91 | $150.00 | $200.00 | $50.00 |
| 0074 | Temporary sheeting (501003P) | SF | 2,254 | $1.00 | $85.00 | $0.01 | $0.01 | $0.01 | $200.00 |
| 0075 | Reinforcement steel, epoxy- coated (504006P) | LB | 10,400 | $3.00 | $2.00 | $2.66 | $3.00 | $3.00 | $3.00 |
| 0076 | Reinforcement steel, galvanized (504009P) | LB | 12,900 | $5.00 | $4.00 | $6.76 | $7.00 | $3.00 | $3.00 |
| 0077 | Concrete abutment wall (504024P) | CY | 21 | $7,500.00 | $5,500.00 | $11,583 | $9,000.00 | $8,500.00 | $6,500.00 |
| 0078 | Epoxy waterproofing (504036P) | SY | 48 | $60.00 | $108.00 | $86.54 | $90.00 | $85.00 | $40.00 |
| 0079 | Prefabricated superstructure units, HPC (505066P) | SF | 2,924 | $620.00 | $420.00 | $847.00 | $735.00 | $437.60 | $800.00 |
| 0080 | Precast concrete sleeper slab (505067P) | CY | 39 | $1,800.00 | $5,750.00 | $2,440.84 | $2,100.00 | $3,412.00 | $2,250.00 |
| 0081 | Reinforced elastomeric bearing assembly (506006P) | U | 24 | $7,500.00 | $3,200.00 | $3,218.71 | $9,000.00 | $4,300.00 | $5,250.00 |
| 0082 | Strip seal expansion joint assembly (507015P) | LF | 118 | $500.00 | $800.00 | $818.39 | $900.00 | $610.00 | $600.00 |
| 0083 | Date panel (507027M) | U | 2 | $2,500.00 | $1,000.00 | $2,282.08 | $2,000.00 | $2,500.00 | $2,500.00 |
| 0084 | Concrete bridge parapet, HPC (507039P) | LF | 102 | $600.00 | $1,000.00 | $881.98 | $700.00 | $950.00 | $450.00 |
| 0085 | Concrete sleeper slab (507050M) | CY | 19 | $2,400.00 | $2,000.00 | $1,567.47 | $3,000.00 | $6,666.34 | $1,250.00 |
| 0086 | Concrete bridge relief slab (507054P) | SY | 125 | $500.00 | $600.00 | $761.47 | $600.00 | $1,013.28 | $650.00 |
| 0087 | Diamond grinding, concrete deck surface (507073M) | SF | 4,321 | $10.00 | $15.00 | $15.47 | $9.00 | $16.00 | $5.00 |
| 0088 | Concrete bridge deck, uhpc (507123P) | CY | 8 | $28,000 | $26,000 | $22,546 | $40,000 | $29,375 | $4,000.00 |
| 0089 | Bridge deck and bridge approach sealing (507140P) | SF | 261 | $70.00 | $13.00 | $17.12 | $6.00 | $66.00 | $8.00 |
| 0090 | Substructure concrete repair (555003M) | SF | 25 | $400.00 | $410.00 | $576.99 | $260.00 | $200.00 | $200.00 |
| 0091 | Concrete barrier curb with moment slab (607040P) | LF | 80 | $1,600.00 | $1,600.00 | $1,121.60 | $1,700.00 | $1,850.00 | $1,300.00 |
| 0092 | 2" rigid metallic conduit (701015P) | LF | 208 | $70.00 | $59.00 | $66.95 | $70.00 | $80.00 | $100.00 |
| 0093 | I-9 soil aggregate (203009P) | CY | 100 | $90.00 | $130.00 | $278.31 | $120.00 | $96.00 | $65.00 |
| 0094 | Removal of pavement (202021P) | SY | 1,006 | $50.00 | $35.00 | $72.53 | $80.00 | $15.00 | $25.00 |
| 0095 | I-14 soil aggregate (203021P) | CY | 136 | $70.00 | $145.00 | $135.75 | $65.00 | $0.01 | $65.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of May 29, 2025. Compiled by Mirage Metrics.