NJDOT contract 25139 bid tabulation
Route 36, Bridge over Troutman's Creek. Let by New Jersey DOT on February 12, 2026, Monmouth, C1. 9 bids received; low bid $7,948,323 by Midlantic Construction, LLC.
- Owner
- New Jersey DOT
- Letting
- 12 FEB 2026
- Pay items
- 153
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Midlantic Construction, LLC | $7,948,323 | Low |
| 2 | Colonnelli Brothers, Inc. | $8,335,105 | +5.0% |
| 3 | George Harms Construction Company, Inc. | $9,465,104 | +19% |
| 4 | Joseph M. Sanzari, Inc. | $9,989,937 | +26% |
| 5 | Ritacco Construction, Inc. | $10,068,000 | +27% |
| 6 | Carbro Constructors Corp. | $10,372,621 | +31% |
| 7 | Anselmi & Decicco, Inc. | $11,462,731 | +44% |
| 8 | C.J. Hesse, Inc. | $12,398,020 | +56% |
| 9 | Marbro, Inc. | $13,317,117 | +68% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Midlantic Construction, LLC | 2. Colonnelli Brothers, Inc. | 3. George Harms Construction Company, Inc. | 4. Joseph M. Sanzari, Inc. | 5. Ritacco Construction, Inc. | 6. Carbro Constructors Corp. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $33,000 | $50,000 | $40,000 | $75,000 | $50,000 | $75,000 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $8,000.00 | $20,000 | $17,000 | $10,000 | $15,000 | $13,000 |
| 0003 | Progress schedule (153003P) | LS | 1 | $100.00 | $3,500.00 | $7,300.00 | $10,000 | $6,000.00 | $45,000 |
| 0004 | Progress schedule update (153005M) | U | 9 | $1.00 | $500.00 | $1,850.00 | $1,000.00 | $200.00 | $440.00 |
| 0005 | Mobilization (154003P) | LS | 1 | $1,120,000 | $569,044 | $1,415,000 | $1,300,000 | $1,510,200 | $1,190,000 |
| 0006 | Field office type F set UP (155018M) | U | 1 | $32,000 | $15,000 | $75,000 | $45,000 | $20,000 | $127,355 |
| 0007 | Field office type F maintenance (155036M) | MO | 17 | $5,600.00 | $1,500.00 | $4,900.00 | $4,000.00 | $2,500.00 | $500.00 |
| 0008 | Materials field laboratory set-UP (156003M) | U | 1 | $1,000.00 | $15,000 | $105,000 | $45,000 | $30,000 | $2,500.00 |
| 0009 | Materials field laboratory maintenance (156006M) | MO | 17 | $500.00 | $100.00 | $3,365.00 | $4,000.00 | $2,750.00 | $350.00 |
| 0010 | Nuclear density gauge (156015M) | U | 1 | $1,000.00 | $5,000.00 | $15,300 | $10,000 | $5,000.00 | $10,000 |
| 0011 | Concrete compression testing equipment (156021M) | U | 1 | $100.00 | $7,500.00 | $18,000 | $10,000 | $5,000.00 | $12,000 |
| 0012 | Heavy duty silt fence, orange (158009M) | LF | 883 | $14.00 | $7.00 | $11.00 | $7.00 | $10.00 | $15.00 |
| 0013 | Haybale (158015M) | U | 25 | $0.01 | $50.00 | $53.00 | $50.00 | $40.00 | $11.00 |
| 0014 | Inlet filter type 2, 2' X 4' (158030M) | U | 17 | $25.00 | $100.00 | $275.00 | $450.00 | $200.00 | $150.00 |
| 0015 | Inlet filter type 2, 4' X 4' (158033M) | U | 1 | $50.00 | $150.00 | $300.00 | $450.00 | $225.00 | $200.00 |
| 0016 | Floating turbidity barrier, type 3 (158048M) | LF | 145 | $35.00 | $35.00 | $66.00 | $98.00 | $40.00 | $150.00 |
| 0017 | Concrete washout system (158063P) | LS | 1 | $2,825.00 | $5,000.00 | $17,000 | $5,954.00 | $4,500.00 | $2,500.00 |
| 0018 | Oil only emergency spill kit, type 1 (158072M) | U | 2 | $1,925.00 | $1,000.00 | $2,500.00 | $1,100.00 | $500.00 | $1,500.00 |
| 0019 | Erosion control sediment removal (158084M) | CY | 35 | $0.01 | $25.00 | $55.00 | $311.00 | $10.00 | $1.00 |
| 0020 | Breakaway barricade (159003M) | U | 30 | $50.00 | $50.00 | $65.00 | $90.00 | $20.00 | $165.00 |
| 0021 | Drum (159006M) | U | 50 | $50.00 | $40.00 | $50.00 | $40.00 | $10.00 | $66.00 |
| 0022 | Traffic cone (159009M) | U | 50 | $50.00 | $25.00 | $23.00 | $15.00 | $1.00 | $22.00 |
| 0023 | Construction signs (159012M) | SF | 829 | $24.00 | $15.00 | $35.00 | $28.00 | $15.00 | $80.00 |
| 0024 | Construction identification sign, 4' X 8' (159015M) | U | 2 | $1,975.00 | $1,000.00 | $1,900.00 | $825.00 | $900.00 | $1,000.00 |
| 0025 | Construction barrier curb (159021P) | LF | 120 | $200.00 | $35.00 | $220.00 | $250.00 | $120.00 | $5.00 |
| 0026 | Arrow board, 2' X 4' (159024M) | U | 2 | $500.00 | $3,500.00 | $1,000.00 | $3,500.00 | $500.00 | $1,500.00 |
| 0027 | Portable variable message sign (159030M) | U | 2 | $500.00 | $10,000 | $2,000.00 | $14,000 | $1,000.00 | $2,500.00 |
| 0028 | Traffic control truck with mounted crash cushion (159108M) | U | 2 | $1,000.00 | $15,000 | $5,800.00 | $18,000 | $2,000.00 | $5,000.00 |
| 0029 | Traffic director, flagger (159141M) | HR | 500 | $0.01 | $100.00 | $115.00 | $147.00 | $125.00 | $1.00 |
| 0030 | Construction identification sign, iija 6' X 4' (159260M) | U | 2 | $1,975.00 | $1,000.00 | $2,350.00 | $884.00 | $800.00 | $900.00 |
| 0031 | Fuel price adjustment (160004M) | DOL | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0032 | Asphalt price adjustment (160007M) | DOL | 1 | $3,300.00 | $3,300.00 | $3,300.00 | $3,300.00 | $3,300.00 | $3,300.00 |
| 0033 | Steel price adjustment (160009M) | DOL | 1 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0034 | Final cleanup (161003P) | LS | 1 | $1,000.00 | $7,500.00 | $15,000 | $25,000 | $11,500 | $15,000 |
| 0035 | Clearing site (201003P) | LS | 1 | $100,000 | $275,000 | $150,000 | $120,000 | $150,000 | $150,000 |
| 0036 | Excavation, test pit (202006M) | CY | 54 | $0.01 | $50.00 | $380.00 | $700.00 | $50.00 | $200.00 |
| 0037 | Excavation, unclassified (202009P) | CY | 947 | $92.00 | $60.00 | $72.00 | $110.00 | $60.00 | $60.00 |
| 0038 | Removal of pavement (202021P) | SY | 2,366 | $30.00 | $15.00 | $28.00 | $15.00 | $20.00 | $30.00 |
| 0039 | Geotextile, roadway stabilization (203041P) | SY | 2,627 | $2.50 | $25.00 | $3.45 | $2.00 | $5.00 | $4.00 |
| 0040 | Dense-graded aggregate base course, 8" thick (302042P) | SY | 2,501 | $22.00 | $15.00 | $25.00 | $18.00 | $22.00 | $30.00 |
| 0041 | Polymerized joint adhesive (401027M) | LF | 1,617 | $2.00 | $1.00 | $1.40 | $2.00 | $2.00 | $2.00 |
| 0042 | Tack coat (401030M) | GAL | 473 | $10.00 | $1.00 | $8.70 | $1.00 | $4.00 | $5.00 |
| 0043 | Prime coat (401036M) | GAL | 729 | $0.01 | $1.00 | $0.01 | $7.00 | $4.00 | $5.00 |
| 0044 | Hot mix asphalt 12.5 M 64 surface course (401054M) | T | 530 | $170.00 | $160.00 | $155.00 | $152.00 | $115.00 | $126.00 |
| 0045 | Hot mix asphalt 19 M 64 intermediate course (401084M) | T | 706 | $170.00 | $130.00 | $145.00 | $129.00 | $110.00 | $121.00 |
| 0046 | Hot mix asphalt 25 M 64 base course (401099M) | T | 882 | $170.00 | $130.00 | $128.00 | $119.00 | $105.00 | $118.00 |
| 0047 | Core samples, hot mix asphalt (401108M) | U | 20 | $565.00 | $250.00 | $154.00 | $206.00 | $300.00 | $300.00 |
| 0048 | 24" reinforced concrete pipe (601128P) | LF | 308 | $103.00 | $100.00 | $120.00 | $400.00 | $140.00 | $250.00 |
| 0049 | 15" reinforced concrete pipe, class IV (601158P) | LF | 114 | $132.00 | $100.00 | $110.00 | $250.00 | $130.00 | $230.00 |
| 0050 | 18" reinforced concrete pipe, class IV (601160P) | LF | 23 | $161.00 | $125.00 | $136.00 | $380.00 | $230.00 | $240.00 |
| 0051 | Subbase outlet drain (601404P) | LF | 185 | $65.00 | $55.00 | $56.00 | $50.00 | $60.00 | $60.00 |
| 0052 | Underdrain, type F (601416P) | LF | 422 | $65.00 | $55.00 | $70.00 | $18.00 | $60.00 | $80.00 |
| 0053 | Cleaning existing pipe, 12" to 24" diameter (601670M) | LF | 1,794 | $0.01 | $10.00 | $15.00 | $13.00 | $15.00 | $9.00 |
| 0054 | Cleaning existing pipe, over 24" to 48" diameter (601672M) | LF | 814 | $0.01 | $15.00 | $20.00 | $13.00 | $20.00 | $29.00 |
| 0055 | Concrete headwall (602006P) | CY | 10 | $1,150.00 | $2,000.00 | $2,800.00 | $2,850.00 | $2,000.00 | $9,000.00 |
| 0056 | Inlet, type B (602012M) | U | 3 | $11,000 | $6,000.00 | $7,100.00 | $10,500 | $5,500.00 | $13,000 |
| 0057 | Inlet, type double B (602013M) | U | 2 | $11,400 | $10,000 | $9,700.00 | $16,000 | $7,500.00 | $12,000 |
| 0058 | Inlet, type B-2 (602027M) | U | 2 | $9,150.00 | $12,500 | $8,800.00 | $11,000 | $7,500.00 | $10,000 |
| 0059 | Set inlet type B, casting (602105M) | U | 3 | $1,850.00 | $2,000.00 | $1,625.00 | $2,250.00 | $1,500.00 | $2,500.00 |
| 0060 | Reconstructed inlet, type E, using existing casting (602129M) | U | 1 | $2,100.00 | $3,500.00 | $3,875.00 | $2,500.00 | $2,000.00 | $2,500.00 |
| 0061 | Reconstructed inlet, type B, using new casting (602153M) | U | 1 | $5,150.00 | $5,000.00 | $5,055.00 | $5,250.00 | $3,000.00 | $3,000.00 |
| 0062 | Reconstructed manhole, using existing casting (602180M) | U | 2 | $1,550.00 | $3,000.00 | $3,875.00 | $2,500.00 | $2,000.00 | $3,000.00 |
| 0063 | Cleaning drainage structure (602216M) | U | 4 | $0.01 | $500.00 | $370.00 | $2,690.00 | $350.00 | $440.00 |
| 0064 | Tidal check valve, size 24" (602346M) | U | 2 | $9,300.00 | $12,500 | $10,310 | $7,250.00 | $7,500.00 | $11,000 |
| 0065 | Riprap stone channel protection, 12" thick (D50=6") (603036P) | SY | 28 | $165.00 | $200.00 | $262.00 | $130.00 | $60.00 | $80.00 |
| 0066 | Concrete sidewalk, 4" thick (606012P) | SY | 568 | $170.00 | $63.00 | $117.00 | $120.00 | $50.00 | $150.00 |
| 0067 | Reset precast concrete pavers (606028P) | SY | 4 | $255.00 | $200.00 | $580.00 | $368.00 | $200.00 | $400.00 |
| 0068 | Hot mix asphalt driveway, 6" thick (606039P) | SY | 40 | $145.00 | $55.00 | $211.00 | $65.00 | $60.00 | $300.00 |
| 0069 | Stone or gravel driveway, 4" thick (606043P) | SY | 7 | $200.00 | $80.00 | $294.00 | $1,000.00 | $90.00 | $300.00 |
| 0070 | Concrete driveway, reinforced, 6" thick (606057P) | SY | 77 | $190.00 | $115.00 | $160.00 | $162.00 | $100.00 | $300.00 |
| 0071 | Concrete driveway, reinforced, 8" thick (606060P) | SY | 30 | $200.00 | $175.00 | $185.00 | $188.00 | $200.00 | $400.00 |
| 0072 | Detectable warning surface (606084P) | SY | 6 | $480.00 | $30.00 | $290.00 | $280.00 | $400.00 | $300.00 |
| 0073 | 9" X 16" concrete vertical curb (607018P) | LF | 1,149 | $51.00 | $42.00 | $55.00 | $53.00 | $35.00 | $60.00 |
| 0074 | Nonvegetative surface, porous hot mix asphalt, 4" thick (608004P) | SY | 122 | $110.00 | $75.00 | $102.00 | $102.00 | $100.00 | $175.00 |
| 0075 | Beam guide rail (609003M) | LF | 50 | $65.00 | $50.00 | $66.00 | $61.00 | $55.00 | $28.00 |
| 0076 | Tangent guide rail terminal (609027M) | U | 2 | $5,700.00 | $3,500.00 | $4,300.00 | $5,253.00 | $5,000.00 | $5,300.00 |
| 0077 | Beam guide rail anchorage (609039M) | U | 2 | $2,200.00 | $2,000.00 | $1,950.00 | $2,010.00 | $2,000.00 | $1,400.00 |
| 0078 | Beam guide rail post (609042M) | U | 9 | $97.00 | $100.00 | $128.00 | $88.00 | $80.00 | $91.00 |
| 0079 | Approach guide rail transition TL-2 (609058M) | U | 4 | $5,200.00 | $2,500.00 | $2,800.00 | $4,800.00 | $4,500.00 | $1,900.00 |
| 0080 | Removal of beam guide rail (609075M) | LF | 433 | $4.00 | $15.00 | $6.50 | $2.00 | $1.00 | $1.00 |
| 0081 | Traffic stripes, 4" (610003M) | LF | 2,317 | $1.15 | $2.00 | $0.95 | $1.00 | $1.50 | $1.10 |
| 0082 | Traffic stripes, 8" (610007M) | LF | 169 | $2.25 | $3.00 | $7.00 | $2.00 | $3.00 | $2.20 |
| 0083 | Traffic marking lines, 24" (610017M) | LF | 47 | $23.00 | $25.00 | $20.00 | $21.00 | $20.00 | $22.00 |
| 0084 | RPM, BI-directional, amber lens (610021M) | U | 10 | $155.00 | $165.00 | $205.00 | $141.00 | $150.00 | $150.00 |
| 0085 | Removal of RPM (610024M) | U | 10 | $100.00 | $100.00 | $36.00 | $75.00 | $40.00 | $1.00 |
| 0086 | Rumble strip (610033M) | LF | 456 | $17.00 | $50.00 | $33.00 | $7.00 | $10.00 | $8.00 |
| 0087 | Removal of traffic markings (610039M) | SF | 95 | $11.00 | $5.00 | $3.00 | $10.00 | $4.00 | $11.00 |
| 0088 | Regulatory and warning sign (612003P) | SF | 24.60 | $85.00 | $85.00 | $89.00 | $100.00 | $40.00 | $55.00 |
| 0089 | 12" ductile iron water pipe, class 52 (651063P) | LF | 82 | $475.00 | $250.00 | $800.00 | $650.00 | $1,100.00 | $700.00 |
| 0090 | Water service connection (651243M) | U | 3 | $5,000.00 | $10,000 | $9,200.00 | $23,200 | $7,000.00 | $8,500.00 |
| 0091 | Reset water valve box (651255M) | U | 2 | $1,000.00 | $500.00 | $400.00 | $282.00 | $700.00 | $200.00 |
| 0092 | 12" valves and boxes (651272M) | U | 2 | $24,200 | $9,000.00 | $5,200.00 | $7,000.00 | $46,000 | $4,000.00 |
| 0093 | 12" water pipe, trenchless construction (651515P) | LF | 347 | $620.00 | $665.00 | $825.00 | $550.00 | $750.00 | $690.00 |
| 0094 | Sanitary sewer pipe lining (652414M) | LF | 210 | $502.00 | $350.00 | $300.00 | $300.00 | $250.00 | $475.00 |
| 0095 | Reset manhole, sanitary sewer, using existing casting (652432M) | U | 1 | $2,000.00 | $2,500.00 | $1,000.00 | $950.00 | $2,000.00 | $100.00 |
| 0096 | Reset sanitary sewer cleanout (652450M) | U | 2 | $1,000.00 | $1,250.00 | $1,000.00 | $866.00 | $2,000.00 | $250.00 |
| 0097 | Electrical utility relocation JCP&L (654007P) | LS | 1 | $380,000 | $25,000 | $355,000 | $434,000 | $480,000 | $415,000 |
| 0098 | 2" rigid metallic conduit (701015P) | LF | 840 | $56.00 | $55.00 | $55.00 | $45.00 | $45.00 | $55.00 |
| 0099 | 3" rigid metallic conduit (701021P) | LF | 473 | $67.00 | $65.00 | $68.00 | $58.00 | $60.00 | $93.00 |
| 0100 | 2 - 3" flexible nonmetallic conduit (701084P) | LF | 63 | $423.00 | $350.00 | $105.00 | $100.00 | $100.00 | $115.00 |
| 0101 | 18" X 36" junction box (701102M) | U | 2 | $3,200.00 | $3,200.00 | $3,700.00 | $2,500.00 | $2,500.00 | $3,000.00 |
| 0102 | Service wire, no. 2 AWG (701210P) | LF | 219 | $11.00 | $12.00 | $7.50 | $6.00 | $6.00 | $7.00 |
| 0103 | Junction box ITS type A (704003M) | U | 2 | $11,800 | $10,000 | $7,100.00 | $5,500.00 | $5,500.00 | $7,000.00 |
| 0104 | Junction box ITS type C (704009M) | U | 3 | $6,700.00 | $5,000.00 | $4,400.00 | $3,500.00 | $3,500.00 | $5,500.00 |
| 0105 | Meter cabinet ITS (704011M) | U | 1 | $5,100.00 | $4,500.00 | $6,300.00 | $6,500.00 | $6,500.00 | $8,400.00 |
| 0106 | Foundation ITS type C-MC (704022M) | U | 1 | $7,350.00 | $7,000.00 | $5,500.00 | $3,900.00 | $4,000.00 | $5,750.00 |
| 0107 | Foundation CSS (704035M) | U | 1 | $32,500 | $40,000 | $45,000 | $36,000 | $35,000 | $45,000 |
| 0108 | Camera standard type B (704051M) | U | 1 | $97,000 | $85,000 | $81,000 | $86,000 | $85,000 | $82,000 |
| 0109 | Camera (704060M) | U | 2 | $10,700 | $9,000.00 | $10,800 | $7,900.00 | $7,500.00 | $8,600.00 |
| 0110 | Controller, camera (704063M) | U | 1 | $38,600 | $35,000 | $29,000 | $45,000 | $45,000 | $28,000 |
| 0111 | Communications integration (704245P) | LS | 1 | $18,650 | $17,500 | $20,200 | $6,700.00 | $6,500.00 | $19,000 |
| 0112 | Topsoil spreading __" thick 4" thick (804000P) | SY | 1,091 | $5.00 | $5.00 | $5.50 | $8.00 | $4.00 | $8.00 |
| 0113 | Plant pit soil (804014P) | CY | 14 | $101.00 | $75.00 | $80.00 | $95.00 | $90.00 | $99.00 |
| 0114 | Borrow topsoil (804015P) | CY | 121 | $61.00 | $50.00 | $86.00 | $60.00 | $50.00 | $40.00 |
| 0115 | Fertilizing and seeding, type A-3 (806006P) | SY | 1,091 | $2.00 | $3.00 | $2.00 | $2.00 | $1.50 | $2.00 |
| 0116 | Fertilizing and seeding, type F (806018P) | SY | 143 | $2.00 | $3.00 | $2.00 | $5.00 | $2.00 | $2.00 |
| 0117 | Wildflower seeding (806030P) | SY | 570 | $3.50 | $5.00 | $3.50 | $3.00 | $3.00 | $4.00 |
| 0118 | Topsoil stabilization, type 1 mat (807003M) | SY | 896 | $5.00 | $7.00 | $5.00 | $5.00 | $5.00 | $6.00 |
| 0119 | Topsoil stabilization, type 2 mat (807006M) | SY | 195 | $5.00 | $7.00 | $5.10 | $5.00 | $5.00 | $6.00 |
| 0120 | Straw mulching (809003M) | SY | 1,234 | $1.00 | $3.00 | $1.10 | $1.00 | $1.00 | $2.00 |
| 0121 | Wood mulching (809018M) | SY | 61 | $7.00 | $7.00 | $6.50 | $6.00 | $5.00 | $7.00 |
| 0122 | Mowing (810006M) | SY | 1,091 | $0.01 | $5.00 | $0.50 | $1.00 | $0.50 | $1.00 |
| 0123 | Large deciduous tree 10-12' high, multi-stem, B&B (811016M) | U | 5 | $1,350.00 | $750.00 | $950.00 | $1,250.00 | $1,200.00 | $1,320.00 |
| 0124 | Small deciduous tree, 7-8' high, B&B (811031M) | U | 5 | $800.00 | $500.00 | $725.00 | $750.00 | $700.00 | $770.00 |
| 0125 | Deciduous shrub, 18-24" high, #3 container (811063M) | U | 110 | $67.00 | $100.00 | $65.00 | $63.00 | $60.00 | $66.00 |
| 0126 | Plant establishment and maintenance period (811138M) | LS | 1 | $1,750.00 | $5,000.00 | $4,200.00 | $1,800.00 | $1,750.00 | $2,000.00 |
| 0127 | Watering (811165M) | MG | 6 | $282.00 | $600.00 | $415.00 | $260.00 | $250.00 | $275.00 |
| 0128 | Vibration monitoring (162006P) | LS | 1 | $16,000 | $50,000 | $105,000 | $65,000 | $80,000 | $125,000 |
| 0129 | Clearing site, bridge (___) 1314-154 (201006P) | LS | 1 | $200,000 | $400,000 | $200,000 | $450,000 | $200,000 | $200,000 |
| 0130 | Excavation, unclassified (202009P) | CY | 1,600 | $0.01 | $55.00 | $86.00 | $60.00 | $75.00 | $75.00 |
| 0131 | I-9 soil aggregate (203009P) | CY | 670 | $88.00 | $60.00 | $110.00 | $110.00 | $95.00 | $150.00 |
| 0132 | Temporary cofferdam (501009P) | LS | 1 | $1,839,540 | $1,800,000 | $1,065,000 | $2,017,740 | $2,513,947 | $2,055,638 |
| 0133 | Furnishing equipment for driving piles (502003P) | LS | 1 | $375,000 | $100,000 | $150,000 | $175,000 | $175,000 | $200,000 |
| 0134 | Prebored hole (502006M) | LF | 340 | $0.01 | $10.00 | $25.70 | $120.00 | $0.01 | $110.00 |
| 0135 | Test pile, furnished (502009M) | LF | 570 | $130.00 | $155.00 | $125.00 | $105.00 | $150.00 | $154.00 |
| 0136 | Test pile, driven (502012M) | LF | 522 | $10.00 | $75.00 | $135.00 | $120.00 | $62.00 | $117.00 |
| 0137 | Dynamic pile load test (502018M) | U | 18 | $0.01 | $2,000.00 | $3,300.00 | $685.00 | $1,300.00 | $4,000.00 |
| 0138 | Cast-in-place concrete pile, furnished, 18" diameter (502030M) | LF | 5,580 | $53.00 | $155.00 | $100.00 | $70.00 | $150.00 | $150.00 |
| 0139 | Cast-in-place concrete pile, driven, 18" diameter (502054M) | LF | 5,394 | $10.00 | $40.00 | $92.00 | $80.00 | $35.00 | $62.00 |
| 0140 | Splice cast-in-place pile (502201M) | U | 68 | $0.01 | $2,000.00 | $1,300.00 | $1,000.00 | $1,750.00 | $1,100.00 |
| 0141 | Pile shoe (502207M) | U | 68 | $950.00 | $1,250.00 | $1,300.00 | $651.00 | $1,075.00 | $500.00 |
| 0142 | Reinforcement steel, galvanized (504009P) | LB | 62,417 | $2.75 | $3.00 | $3.70 | $3.00 | $2.50 | $3.00 |
| 0143 | Concrete footing (504015P) | CY | 213 | $608.00 | $650.00 | $1,050.00 | $900.00 | $700.00 | $1,480.00 |
| 0144 | Concrete wing wall (504018P) | CY | 133 | $750.00 | $1,500.00 | $2,315.00 | $2,200.00 | $900.00 | $2,000.00 |
| 0145 | Concrete pylon (504053P) | LF | 46 | $575.00 | $350.00 | $1,595.00 | $879.00 | $600.00 | $660.00 |
| 0146 | Precast concrete culvert (505057P) | LF | 56 | $7,750.00 | $11,000 | $8,700.00 | $10,000 | $10,800 | $8,000.00 |
| 0147 | Concrete bridge deck, HPC (507024P) | CY | 57 | $886.00 | $1,500.00 | $1,515.00 | $1,700.00 | $1,000.00 | $3,200.00 |
| 0148 | Date panel (507027M) | U | 3 | $550.00 | $1,500.00 | $2,300.00 | $4,000.00 | $2,000.00 | $1,500.00 |
| 0149 | Concrete bridge sidewalk, HPC (507033P) | CY | 19 | $1,200.00 | $1,750.00 | $2,945.00 | $1,750.00 | $1,600.00 | $1,800.00 |
| 0150 | Concrete bridge approach (507051P) | CY | 112 | $1,100.00 | $700.00 | $1,475.00 | $1,240.00 | $900.00 | $1,500.00 |
| 0151 | Steel 3 bar bridge railing (507084P) | LF | 160 | $560.00 | $650.00 | $770.00 | $500.00 | $500.00 | $700.00 |
| 0152 | Bridge deck and bridge approach sealing (507140P) | SF | 4,400 | $0.01 | $5.00 | $15.00 | $2.00 | $8.00 | $11.00 |
| 0153 | 8" perforated high density polyethylene pipe (601419P) | LF | 221 | $68.00 | $45.00 | $100.00 | $60.00 | $50.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of February 12, 2026. Compiled by Mirage Metrics.