Midlantic Construction, LLC: NJDOT bid record
Midlantic Construction, LLC submitted 52 bids on New Jersey DOT contracts in the data, from 22 JUN 2017 to 12 FEB 2026, and was the low bidder on 4 of them (8%). When it was not low, its total sat a median +28% above the low bid.
- Owner
- New Jersey DOT
- Low bid volume
- $25,988,236
- Latest bid
- 12 FEB 2026
- Data through
- 16 APR 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2017 | 5 | 0 | 0% |
| 2018 | 22 | 0 | 0% |
| 2019 | 10 | 1 | 10% |
| 2020 | 2 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2023 | 3 | 1 | 33% |
| 2024 | 4 | 0 | 0% |
| 2025 | 4 | 1 | 25% |
| 2026 | 1 | 1 | 100% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| C1 | 19 | 3 | 16% |
| S1 | 13 | 1 | 8% |
| C4 | 7 | 0 | 0% |
| S4 | 4 | 0 | 0% |
| H4 | 3 | 0 | 0% |
| N1 | 3 | 0 | 0% |
| N4 | 3 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Excavation, unclassified | 202009P | CY | 94 | 51 (54%) | $58.00 | $78.60 |
| Fuel price adjustment | 160004M | DOL | 31 | 31 (100%) | $2,400.00 | $2,700.00 |
| Prime coat | 401036M | GAL | 25 | 25 (100%) | $0.01 | $0.01 |
| Pollution liability insurance | 152015P | DOL | 40 | 24 (60%) | $10,000 | $8,500.00 |
| Concrete pier column and cap, HPC | 504026P | CY | 65 | 22 (34%) | $2,426.57 | $2,291.62 |
| Asphalt price adjustment | 160007M | DOL | 22 | 22 (100%) | $5,350.00 | $10,200 |
| Soil sampling and analyses, regulated | 202030M | U | 24 | 21 (88%) | $550.00 | $941.21 |
| Performance bond and payment bond | 151006M | DOL | 41 | 17 (41%) | $30,000 | $32,468 |
| Progress schedule update | 153005M | U | 18 | 17 (94%) | $100.00 | $600.00 |
| Telephone service | MMG010M | DOL | 12 | 12 (100%) | $1.00 | $1.00 |
| Overtime differential (OD) | MMG025M | DOL | 12 | 12 (100%) | $1.00 | $1.00 |
| Solid waste disposal | MMB173M | DOL | 12 | 12 (100%) | $1.00 | $1.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Iew Construction Group, Inc. | 35 | 24 of 35 |
| South State, Inc. | 19 | 14 of 19 |
| Joseph M. Sanzari, Inc. | 14 | 11 of 14 |
| Mount Construction Co., Inc. | 13 | 12 of 13 |
| Ritacco Construction, Inc. | 12 | 4 of 12 |
| Earle Asphalt Company | 11 | 8 of 11 |
| Green Construction, Inc. | 11 | 7 of 11 |
| Anselmi & Decicco, Inc. | 10 | 4 of 10 |
| Berto Construction, Inc. | 9 | 8 of 9 |
| Ferreira Construction Co., Inc. | 9 | 4 of 9 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 FEB 2026 | 25139 | C1 | Route 36, Bridge over Troutman's Creek | 1 of 9 | $7,948,323 | Low, 5.0% under the second |
| 23 OCT 2025 | 25134 | C1 | RT 35, BRIDGE OVER NORTH BRANCH OF WRECK POND | 3 of 5 | $9,943,399 | +20% |
| 03 APR 2025 | 25103 | S1 | Route 47, Bridge over Menantico Creek | 1 of 3 | $11,041,484 | Low, 6.0% under the second |
| 18 MAR 2025 | 25438 | C4 | MTN Infrastructure Repair Central - 2025 | 6 of 7 | $8,594,695 | +44% |
| 28 JAN 2025 | 24153 | C1 | GROVE AVENUE, BRIDGE OVER PORT READING RAILROAD | 8 of 11 | $13,094,374 | +31% |
| 06 JUN 2024 | 24119 | N1 | CR 583 (Princeton Pike), Bridge over Rt 295 & Ramps B & D | 5 of 9 | $22,188,178 | +13% |
| 23 APR 2024 | 24439 | S4 | MTN Infrastructure Repair South 2024 | 3 of 3 | $9,801,750 | +17% |
| 18 APR 2024 | 24438 | C4 | MTN Infrastructure Repair Central 2024 | 4 of 4 | $13,413,500 | +39% |
| 22 FEB 2024 | 18450 | H4 | Maintenance Bridge Fender Replacement Contract 2018-1 | 5 of 5 | $26,434,530 | +45% |
| 08 JUN 2023 | 23104 | C1 | Forest Resource Edu. Center Access Rd Bridge over Toms River | 1 of 5 | $2,616,989 | Low, 16% under the second |
| 08 JUN 2023 | 23125 | S1 | Route 47 Bridge over Big Timber Creek | 4 of 4 | $58,521,555 | +23% |
| 01 JUN 2023 | 23121 | C1 | Route 34 Bridge over Former Brick Yard Road | 5 of 6 | $2,121,209 | +28% |
| 15 DEC 2022 | 22135 | S1 | Route 130, Bridge over Big Timber Creek | 4 of 4 | $78,115,860 | +44% |
| 10 NOV 2020 | 20134 | S1 | Route 30 over Beach Thorofare | 6 of 6 | $39,265,100 | +101% |
| 02 JUN 2020 | 20121 | C1 | Wright-Debow Rd, Bridge over Rt 195 | 7 of 8 | $4,111,139 | +47% |
| 31 DEC 2019 | 19147 | C1 | RIVER ROAD, BRIDGE OVER RARITAN VALLEY RAILROAD | 1 of 5 | $4,381,441 | Low, 21% under the second |
| 05 DEC 2019 | 20442 | C4 | MTN CONCRETE ,STEEL & ALUMNM STRUC. REP. CENTRAL 2020 | 4 of 4 | $24,809,775 | +54% |
| 20 JUN 2019 | 19129 | S1 | Tomlin Station Road (CR 607) Over Route 295 | 4 of 5 | $3,481,809 | +17% |
| 20 JUN 2019 | 19130 | C1 | ROUTE 34, BRIDGE OVER FORMER FREEHOLD AND JAMESBURG RAILROAD | 2 of 8 | $9,871,974 | +2.0% |
| 06 JUN 2019 | 19131 | C1 | Route 295 Northbound, Exit Ramp To Route 195 Eastbound | 10 of 10 | $6,441,019 | +93% |
| 30 MAY 2019 | 19123 | N1 | Rattlesnake Bridge Rd, Bridge over Rt. 78 | 3 of 6 | $4,851,388 | +29% |
| 21 MAY 2019 | 19107 | C1 | ALEXANDER RD, BRIDGE OVER D&R CANAL | 2 of 8 | $5,331,358 | +10% |
| 28 FEB 2019 | 19102 | S1 | Route 9 SB Bridge over Route 440 Ramp GM | 2 of 7 | $4,451,459 | +7.0% |
| 24 JAN 2019 | 18464 | H4 | Maintenance JOC Bridge Repairs, North-2018 | 4 of 4 | $13,718,750 | +172% |
| 17 JAN 2019 | 18147 | C1 | SIGN STRUCTURE REPLACEMENT CONTRACT 2013-2 | 6 of 6 | $24,125,556 | +55% |
How this record was read
NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
- Every bid counted here matched its published total to within one dollar; NJDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.