NYSDOT contract D265388 bid tabulation
MOBILITY IMPROVEMENTS - CLEARVIEW EXPRESSWAY - Route I-295. Let by New York State DOT on January 23, 2025, Queens, Region 11. 7 bids received; low bid $2,942,165 by Es II Enterprises LLC /DBA El Sol Enterprises.
- Owner
- New York State DOT
- Letting
- 23 JAN 2025
- Pay items
- 146
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Es II Enterprises LLC /DBA El Sol Enterprises | $2,942,165 | Low |
| 2 | Restani Construction Corp | $3,274,673 | +11% |
| 3 | Bove Industries Inc | $3,725,000 | +27% |
| 4 | Jrcruz Corp | $4,004,850 | +36% |
| 5 | Grace Industries LLC | $4,223,235 | +44% |
| 6 | Oliveira Contracting Inc | $4,525,869 | +54% |
| 7 | Quintal Contracting Corp | $6,323,599 | +115% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Es II Enterprises LLC /DBA El Sol Enterprises | 2. Restani Construction Corp | 3. Bove Industries Inc | 4. Jrcruz Corp | 5. Grace Industries LLC | 6. Oliveira Contracting Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 0.50 | $25,000 | $300,000 | $200,000 | $50,000 | $33,000 | $50,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 919 | $75.00 | $200.00 | $75.00 | $65.00 | $190.00 | $150.00 |
| 3 | Embankment In Place (203.03) | CY | 350 | $125.00 | $5.00 | $40.00 | $65.00 | $100.00 | $200.00 |
| 4 | Select Granular Fill (203.07) | CY | 414 | $10.00 | $20.00 | $40.00 | $65.00 | $85.00 | $95.00 |
| 5 | Trench and Culvert Excavation (206.0201) | CY | 1,628 | $100.00 | $28.00 | $10.00 | $65.00 | $115.00 | $120.00 |
| 6 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 610 | $20.00 | $65.00 | $35.00 | $125.00 | $150.00 | $225.00 |
| 7 | (206.03180010) | 20 | $300.00 | $30.00 | $200.00 | $125.00 | $260.00 | $225.00 | |
| 8 | (209.11010024) | 7 | $250.00 | $300.00 | $900.00 | $200.00 | $300.00 | $550.00 | |
| 9 | (304.00010018) | 550 | $1.00 | $1.00 | $0.02 | $20.00 | $8.50 | $10.00 | |
| 10 | Subbase Course, Type 1 (304.11) | CY | 259 | $200.00 | $120.00 | $40.00 | $125.00 | $160.00 | $200.00 |
| 11 | (402.25020018) | 204 | $40.00 | $45.00 | $40.00 | $25.00 | $62.00 | $31.00 | |
| 12 | (404.0001) | TON | 31 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 | $175.00 |
| 13 | (404.0189) | TON | 80 | $225.00 | $90.00 | $150.00 | $300.00 | $310.00 | $300.00 |
| 14 | (404.1281) | TON | 230 | $225.00 | $200.00 | $285.00 | $300.00 | $300.00 | $350.00 |
| 15 | (404.1959) | TON | 306 | $200.00 | $175.00 | $275.00 | $300.00 | $310.00 | $375.00 |
| 16 | Diluted Tack Coat (407.0102) | GAL | 368 | $4.00 | $15.00 | $25.00 | $10.00 | $5.50 | $15.00 |
| 17 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 3,000 | $1.00 | $2.50 | $2.00 | $2.00 | $5.50 | $8.00 |
| 18 | (490.10120011) | 1,925 | $35.00 | $25.00 | $20.00 | $20.00 | $25.00 | $50.00 | |
| 19 | (502.0021) | 231 | $600.00 | $630.00 | $1,300.00 | $2,000.00 | $1,010.00 | $850.00 | |
| 20 | (502.31010018) | 155 | $6.00 | $100.00 | $150.00 | $100.00 | $290.00 | $165.00 | |
| 21 | (502.32010011) | 161 | $100.00 | $50.00 | $50.00 | $100.00 | $23.00 | $125.00 | |
| 22 | (502.33010018) | 161 | $50.00 | $50.00 | $50.00 | $100.00 | $23.00 | $125.00 | |
| 23 | (502.34010018) | 141 | $20.00 | $40.00 | $12.00 | $75.00 | $30.00 | $35.00 | |
| 24 | (502.37010018) | 176 | $20.00 | $40.00 | $12.00 | $70.00 | $30.00 | $35.00 | |
| 25 | (502.38010018) | 176 | $20.00 | $5.00 | $35.00 | $40.00 | $21.00 | $35.00 | |
| 26 | Longitudinal Joints (502.9110) | LF | 775 | $20.00 | $30.00 | $15.00 | $45.00 | $37.00 | $35.00 |
| 27 | Performance Concrete Quality Adjustment - PCC Pavement (502.99) | QUALITY UNIT | 1 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 28 | (502.99110011) | 2 | $1,000.00 | $3,000.00 | $1,300.00 | $2,500.00 | $5,000.00 | $3,000.00 | |
| 29 | (520.05000010) | 860 | $5.00 | $5.00 | $4.50 | $6.00 | $8.00 | $2.00 | |
| 30 | Shields and Shoring (552.17) | SF | 15,324 | $1.00 | $1.50 | $1.00 | $2.00 | $1.00 | $1.00 |
| 31 | (603.6002) | LF | 121 | $100.00 | $230.00 | $350.00 | $375.00 | $315.00 | $571.00 |
| 32 | (603.6003) | LF | 146 | $150.00 | $230.00 | $500.00 | $385.00 | $400.00 | $704.00 |
| 33 | (603.6005) | LF | 290 | $200.00 | $450.00 | $700.00 | $400.00 | $540.00 | $813.00 |
| 34 | Concrete Collars (603.77) | EACH | 2 | $500.00 | $1,500.00 | $1,050.00 | $2,500.00 | $4,880.00 | $4,000.00 |
| 35 | (604.02020011) | 24 | $800.00 | $1,500.00 | $700.00 | $1,250.00 | $1,130.00 | $2,235.00 | |
| 36 | (604.04850011) | 26 | $800.00 | $1,000.00 | $900.00 | $400.00 | $860.00 | $3,500.00 | |
| 37 | (604.071101) | EACH | 1 | $4,000.00 | $1,000.00 | $10,000 | $5,000.00 | $13,000 | $3,500.00 |
| 38 | (604.07200110) | 1 | $4,000.00 | $1,500.00 | $2,500.00 | $2,500.00 | $1,990.00 | $2,500.00 | |
| 39 | (604.07210110) | 2 | $4,000.00 | $1,000.00 | $1,500.00 | $1,000.00 | $1,990.00 | $1,500.00 | |
| 40 | (604.07240110) | 1 | $4,000.00 | $5,000.00 | $8,500.00 | $5,000.00 | $13,000 | $3,750.00 | |
| 41 | (604.07260011) | 3 | $4,000.00 | $500.00 | $1,500.00 | $1,250.00 | $2,650.00 | $2,100.00 | |
| 42 | (604.07280010) | 5 | $25.00 | $150.00 | $400.00 | $200.00 | $340.00 | $200.00 | |
| 43 | (604.13000011) | 4 | $2,500.00 | $2,500.00 | $2,500.00 | $3,500.00 | $6,170.00 | $2,000.00 | |
| 44 | HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27) | EACH | 1 | $7,000.00 | $10,000 | $8,500.00 | $15,000 | $13,200 | $9,350.00 |
| 45 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 713 | $50.00 | $70.00 | $55.00 | $100.00 | $92.00 | $60.50 |
| 46 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 1 | $6,000.00 | $9,000.00 | $7,000.00 | $15,000 | $12,200 | $7,700.00 |
| 47 | (607.36000011) | 160 | $200.00 | $110.00 | $150.00 | $130.00 | $170.00 | $165.00 | |
| 48 | (607.41010010) | 770 | $10.00 | $10.00 | $10.00 | $6.00 | $17.00 | $50.00 | |
| 49 | Concrete Sidewalks and Driveways (608.0101) | CY | 7 | $1,000.00 | $700.00 | $775.00 | $1,850.00 | $1,550.00 | $2,000.00 |
| 50 | (608.02010015) | 7 | $500.00 | $400.00 | $75.00 | $65.00 | $370.00 | $500.00 | |
| 51 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 42 | $250.00 | $300.00 | $300.00 | $500.00 | $640.00 | $600.00 |
| 52 | Embedded Detectable Warning Units (608.21) | SY | 3 | $700.00 | $400.00 | $400.00 | $162.00 | $1,010.00 | $150.00 |
| 53 | (609.04030510) | 762 | $70.00 | $100.00 | $135.00 | $85.00 | $115.00 | $200.00 | |
| 54 | (609.06000008) | 755 | $10.00 | $1.00 | $95.00 | $50.00 | $31.00 | $10.00 | |
| 55 | (609.26020111) | 45 | $150.00 | $300.00 | $500.00 | $250.00 | $130.00 | $500.00 | |
| 56 | Topsoil - Lawns (610.1403) | CY | 260 | $90.00 | $100.00 | $50.00 | $100.00 | $140.00 | $138.60 |
| 57 | Turf Establishment - Roadside (610.1601) | SY | 1,560 | $2.00 | $2.00 | $15.00 | $2.50 | $3.00 | $5.50 |
| 58 | Watering Vegetation (610.19) | 1,000 GALLONS | 333 | $150.00 | $150.00 | $1.00 | $150.00 | $205.00 | $50.60 |
| 59 | Care of Trees up to 12” Diam. at Breast Height – Pruning (614.0411) | EACH | 4 | $450.00 | $450.00 | $750.00 | $550.00 | $700.00 | $825.00 |
| 60 | Care of Trees Over 12” to 24” Diam. at Breast Height - Pruning (614.0421) | EACH | 3 | $600.00 | $600.00 | $900.00 | $750.00 | $930.00 | $900.00 |
| 61 | Tree Root Zone Treatment (Vertical Mulching/Aeration) (614.08) | SY | 200 | $45.00 | $45.00 | $34.00 | $55.00 | $70.00 | $27.22 |
| 62 | (614.08120009) | 255 | $60.00 | $60.00 | $125.00 | $75.00 | $93.00 | $95.00 | |
| 63 | Tree Root Pruning (614.09) | LF | 205 | $75.00 | $25.00 | $110.00 | $5.00 | $220.00 | $150.00 |
| 64 | (615.33010011) | 3 | $250.00 | $1,000.00 | $1,200.00 | $250.00 | $1,550.00 | $2,000.00 | |
| 65 | (615.43000011) | 1,517 | $40.00 | $15.00 | $20.00 | $5.00 | $35.00 | $50.00 | |
| 66 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $180,000 | $486,000 | $350,000 | $165,633 | $500,000 |
| 67 | (619.100101) | LF | 200 | $5.00 | $9.50 | $4.90 | $5.50 | $7.00 | $5.00 |
| 68 | (619.110511) | EACH | 1 | $10,000 | $30,000 | $15,000 | $20,000 | $4,220.00 | $45,000 |
| 69 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 755 | $40.00 | $150.00 | $75.00 | $115.00 | $70.00 | $80.00 |
| 70 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 1 | $25,000 | $20,000 | $8,000.00 | $80,000 | $28,100 | $20,000 |
| 71 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $40,000 | $50,000 | $124,158 | $100,000 | $46,600 | $75,000 |
| 72 | (619.67020010) | LS | 1 | $90,000 | $100,000 | $75,000 | $150,000 | $88,600 | $62,000 |
| 73 | Cleaning Closed Drainage Systems (621.03) | LF | 175 | $25.00 | $15.00 | $10.00 | $25.00 | $31.00 | $33.00 |
| 74 | Cleaning Drainage Structures (621.04) | EACH | 4 | $400.00 | $750.00 | $1,200.00 | $2,200.00 | $1,160.00 | $1,200.00 |
| 75 | Survey Operations (625.01) | LS | 1 | $75,000 | $50,000 | $85,000 | $125,000 | $45,000 | $60,000 |
| 76 | (625.09010015) | LS | 1 | $5,000.00 | $15,000 | $9,000.00 | $10,000 | $9,970.00 | $25,000 |
| 77 | Cleaning, Sealing and/or Filling Joints (633.13) | LF | 204 | $20.00 | $27.00 | $30.00 | $25.00 | $42.00 | $26.00 |
| 78 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 155 | $30.00 | $200.00 | $100.00 | $185.00 | $910.00 | $110.00 |
| 79 | (634.07050003) | 556 | $10.00 | $10.00 | $9.00 | $10.00 | $17.00 | $27.00 | |
| 80 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,000.00 | $500.00 | $5,550.00 | $3,000.00 | $5,040.00 | $5,000.00 |
| 81 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 14 | $5,000.00 | $15,000 | $13,000 | $7,500.00 | $11,500 | $12,000 |
| 82 | (637.31020020) | 14 | $950.00 | $1,000.00 | $950.00 | $1,000.00 | $1,000.00 | $1,000.00 | |
| 83 | Office Technology and Supplies (637.34) | DOL | 8,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 84 | (639.10210011) | LS | 1 | $55,000 | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
| 85 | (642.31200024) | 4,680 | $1.00 | $3.50 | $10.00 | $1.00 | $16.00 | $2.00 | |
| 86 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 139 | $65.00 | $85.00 | $84.00 | $100.00 | $130.00 | $77.00 |
| 87 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 75 | $85.00 | $90.00 | $87.00 | $100.00 | $140.00 | $85.70 |
| 88 | (645.62000110) | 176 | $65.00 | $120.00 | $75.00 | $140.00 | $180.00 | $82.50 | |
| 89 | Type A Sign Posts (645.81) | EACH | 9 | $325.00 | $300.00 | $350.00 | $350.00 | $470.00 | $385.00 |
| 90 | Concrete Footing for Type A, or Breakaway Wooden Sign Posts with Steel Tube Inserts (645.8107) | EACH | 9 | $300.00 | $1,200.00 | $300.00 | $1,500.00 | $1,810.00 | $330.00 |
| 91 | Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25) | EACH | 1 | $500.00 | $12,500 | $750.00 | $17,500 | $19,400 | $14,130 |
| 92 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 24 | $65.00 | $175.00 | $65.00 | $200.00 | $260.00 | $71.50 |
| 93 | Remove and Store Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.42) | EACH | 2 | $125.00 | $175.00 | $150.00 | $200.00 | $260.00 | $165.00 |
| 94 | (655.00040011) | 2 | $600.00 | $1,000.00 | $500.00 | $600.00 | $1,390.00 | $2,000.00 | |
| 95 | (655.00050011) | 2 | $2,700.00 | $1,000.00 | $1,100.00 | $550.00 | $1,060.00 | $2,000.00 | |
| 96 | (655.00060011) | 2 | $2,000.00 | $500.00 | $300.00 | $425.00 | $810.00 | $2,000.00 | |
| 97 | (655.00120011) | 2 | $1,500.00 | $1,500.00 | $1,200.00 | $360.00 | $600.00 | $2,000.00 | |
| 98 | Miscellaneous Metals (656.01) | LB | 350 | $20.00 | $17.50 | $2.00 | $5.00 | $33.00 | $10.00 |
| 99 | (660.09020011) | 5 | $5,200.00 | $15,000 | $8,500.00 | $10,500 | $13,700 | $8,440.00 | |
| 100 | (660.09040011) | 2 | $9,600.00 | $15,000 | $10,000 | $13,500 | $15,000 | $11,130 | |
| 101 | (660.75000010) | 8 | $700.00 | $390.00 | $1,200.00 | $475.00 | $1,290.00 | $390.00 | |
| 102 | (661.03020011) | 380 | $5.00 | $6.50 | $6.75 | $8.00 | $5.50 | $6.50 | |
| 103 | (661.03050011) | 100 | $7.00 | $9.00 | $9.05 | $10.00 | $7.50 | $8.70 | |
| 104 | (661.03060011) | 3,395 | $12.00 | $10.00 | $10.00 | $11.50 | $15.00 | $9.65 | |
| 105 | (661.03080011) | 733 | $16.00 | $14.00 | $14.00 | $17.00 | $21.00 | $14.00 | |
| 106 | (661.24020011) | 5 | $500.00 | $1,000.00 | $600.00 | $1,560.00 | $1,970.00 | $500.00 | |
| 107 | (661.24110011) | 5 | $1,200.00 | $1,500.00 | $815.00 | $950.00 | $2,820.00 | $780.00 | |
| 108 | (661.34070011) | 5 | $6,000.00 | $2,750.00 | $6,000.00 | $3,775.00 | $6,120.00 | $1,650.00 | |
| 109 | (670.01100039) | 5 | $850.00 | $950.00 | $1,000.00 | $1,150.00 | $890.00 | $945.00 | |
| 110 | (670.11200011) | 5 | $440.00 | $715.00 | $745.00 | $875.00 | $970.00 | $715.00 | |
| 111 | (670.11250611) | 5 | $7,000.00 | $5,100.00 | $5,300.00 | $6,220.00 | $14,900 | $5,090.00 | |
| 112 | (670.14480010) | 3 | $500.00 | $400.00 | $500.00 | $1,075.00 | $860.00 | $1,850.00 | |
| 113 | (670.14480011) | 3 | $3,000.00 | $5,850.00 | $900.00 | $7,100.00 | $13,200 | $5,815.00 | |
| 114 | (670.2003) | LF | 505 | $75.00 | $65.00 | $65.00 | $75.00 | $97.00 | $62.20 |
| 115 | (670.2004) | LF | 50 | $126.00 | $115.00 | $116.00 | $135.00 | $140.00 | $112.00 |
| 116 | (670.2005) | LF | 50 | $202.00 | $125.00 | $127.00 | $150.00 | $200.00 | $122.00 |
| 117 | (670.2007) | LF | 10 | $71.00 | $60.00 | $63.00 | $75.00 | $81.00 | $60.40 |
| 118 | (670.2602) | LF | 20 | $64.00 | $30.00 | $31.00 | $35.00 | $40.00 | $30.00 |
| 119 | (670.40010008) | 10 | $420.00 | $475.00 | $495.00 | $580.00 | $400.00 | $475.00 | |
| 120 | (670.75010005) | 1 | $750.00 | $830.00 | $865.00 | $1,015.00 | $2,170.00 | $830.00 | |
| 121 | (670.75020011) | 1,247 | $9.00 | $9.65 | $10.00 | $12.00 | $15.00 | $9.65 | |
| 122 | (670.75050011) | 40 | $5.00 | $9.00 | $9.00 | $10.00 | $7.50 | $8.70 | |
| 123 | (670.75080011) | 190 | $4.00 | $6.50 | $7.00 | $8.00 | $5.50 | $6.50 | |
| 124 | (670.94110010) | LS | 1 | $7,000.00 | $15,000 | $30,000 | $20,000 | $46,700 | $14,740 |
| 125 | (670.99010011) | 5 | $185.00 | $280.00 | $292.00 | $340.00 | $480.00 | $280.00 | |
| 126 | (680.51000010) | 1 | $3,000.00 | $2,000.00 | $1,050.00 | $1,600.00 | $860.00 | $3,500.00 | |
| 127 | (680.510501) | EACH | 2 | $6,700.00 | $7,500.00 | $4,200.00 | $5,560.00 | $10,000 | $3,890.00 |
| 128 | (680.51100010) | 3 | $835.00 | $625.00 | $250.00 | $760.00 | $1,010.00 | $625.00 | |
| 129 | (680.730310) | LF | 45 | $15.00 | $14.00 | $15.00 | $17.00 | $24.00 | $14.00 |
| 130 | (680.79300010) | 2 | $420.00 | $625.00 | $650.00 | $760.00 | $1,770.00 | $625.00 | |
| 131 | (680.81310039) | 2 | $2,000.00 | $1,205.00 | $1,250.00 | $1,475.00 | $4,430.00 | $1,205.00 | |
| 132 | (680.8151) | EACH | 1 | $2,500.00 | $2,125.00 | $2,200.00 | $2,600.00 | $3,620.00 | $2,125.00 |
| 133 | (680.8152) | EACH | 1 | $8,000.00 | $5,950.00 | $9,500.00 | $7,250.00 | $7,650.00 | $5,950.00 |
| 134 | Breakaway Transformer Base (680.8223) | EACH | 1 | $1,400.00 | $1,715.00 | $1,800.00 | $2,100.00 | $4,030.00 | $1,715.00 |
| 135 | (680.99120011) | 200 | $17.00 | $105.00 | $110.00 | $125.00 | $64.00 | $105.00 | |
| 136 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 690 | $2.00 | $1.80 | $2.00 | $3.00 | $3.00 | $5.00 |
| 137 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 200 | $2.00 | $1.80 | $2.00 | $3.00 | $3.00 | $5.00 |
| 138 | (685.16010014) | 4,514 | $2.00 | $1.95 | $2.00 | $3.00 | $3.00 | $5.00 | |
| 139 | (685.17010014) | 788 | $2.00 | $1.95 | $2.00 | $3.00 | $3.00 | $5.00 | |
| 140 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 16 | $150.00 | $150.00 | $175.00 | $200.00 | $230.00 | $500.00 |
| 141 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 8 | $200.00 | $200.00 | $225.00 | $250.00 | $310.00 | $500.00 |
| 142 | Field Change Payment (FCP) (697.03) | DOL | 265,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 143 | Asphalt Price Adjustment (698.04) | DOL | 757 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 144 | Fuel Price Adjustment (698.05) | DOL | 379 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 145 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 146 | Mobilization (699.040001) | LS | 1 | $110,000 | $115,000 | $140,000 | $153,069 | $162,000 | $172,918 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.