NYSDOT contract D265413 bid tabulation
HIGHWAY - ADA IMPROVEMENTS - US RT 11, NYS RT 12E, 180, 411. Let by New York State DOT on January 23, 2025, Jefferson, Region 07. 4 bids received; low bid $1,182,132 by Bothar Construction LLC.
- Owner
- New York State DOT
- Letting
- 23 JAN 2025
- Pay items
- 41
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bothar Construction LLC | $1,182,132 | Low |
| 2 | Tadcon Electric LLC | $1,545,331 | +31% |
| 3 | Mattoon Construction Services Inc | $1,545,877 | +31% |
| 4 | Vector Construction Corp | $1,669,999 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bothar Construction LLC | 2. Tadcon Electric LLC | 3. Mattoon Construction Services Inc | 4. Vector Construction Corp |
|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 717 | $103.00 | $158.45 | $91.83 | $100.00 |
| 2 | Embankment In Place (203.03) | CY | 42 | $57.00 | $156.04 | $439.85 | $350.00 |
| 3 | Seed and Mulch – Temporary (209.1003) | SY | 1,020 | $5.50 | $5.54 | $18.42 | $6.00 |
| 4 | Drainage Structure Inlet Protection, Prefabricated – Temporary (209.1703) | LF | 50 | $65.44 | $50.93 | $57.79 | $25.00 |
| 5 | Subbase Course, Type 2 (304.12) | CY | 349 | $148.00 | $424.61 | $188.82 | $200.00 |
| 6 | (404.0001) | TON | 9 | $75.00 | $75.00 | $75.00 | $75.00 |
| 7 | (404.0983) | TON | 44 | $443.00 | $1,183.92 | $287.64 | $500.00 |
| 8 | (404.2589) | TON | 118 | $253.00 | $491.67 | $183.36 | $500.00 |
| 9 | Stabilized Gravel Surface Course (411.01) | CY | 1 | $493.90 | $340.24 | $528.78 | $150.00 |
| 10 | (604.070101) | EACH | 2 | $1,125.00 | $1,132.32 | $895.63 | $3,400.00 |
| 11 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $75.00 | $75.00 | $75.00 | $75.00 |
| 12 | Concrete Sidewalks and Driveways (608.0101) | CY | 95 | $2,400.00 | $3,306.80 | $3,172.67 | $2,500.00 |
| 13 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 9 | $250.70 | $438.93 | $393.20 | $500.00 |
| 14 | (608.21000003) | 152 | $285.65 | $504.58 | $570.97 | $675.00 | |
| 15 | (609.0401) | LF | 837 | $127.00 | $159.33 | $74.58 | $180.00 |
| 16 | Turf Establishment – Performance (610.1605) | SY | 511 | $28.00 | $12.84 | $22.85 | $25.00 |
| 17 | (615.02060124) | 1 | $1,209.00 | $7,739.39 | $1,296.53 | $5,000.00 | |
| 18 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $360,000 | $266,101 | $404,409 | $625,000 |
| 19 | Type III Construction Barricades (619.04) | EACH | 50 | $200.00 | $415.86 | $150.27 | $340.00 |
| 20 | (619.080102) | LF | 3,114 | $3.25 | $3.60 | $9.97 | $4.00 |
| 21 | Survey Operations (625.01) | LS | 1 | $11,000 | $3,600.00 | $141,376 | $15,000 |
| 22 | (625.09010015) | LS | 1 | $998.00 | $3,600.00 | $11,000 | $100.00 |
| 23 | (627.50140008) | 2,571 | $6.00 | $22.89 | $18.53 | $8.00 | |
| 24 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 3,681 | $2.85 | $3.60 | $4.05 | $4.00 |
| 25 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 18 | $2,000.00 | $4,047.99 | $2,510.25 | $2,000.00 |
| 26 | Office Technology and Supplies (637.34) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Construction Testing supplies – Consumables (637.36) | DOL | 120 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 6 | $69.40 | $448.49 | $416.55 | $500.00 |
| 29 | Type A Sign Posts (645.81) | EACH | 24 | $342.50 | $224.60 | $280.18 | $500.00 |
| 30 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 20 | $253.65 | $395.24 | $181.87 | $400.00 |
| 31 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 18 | $169.10 | $191.86 | $73.95 | $90.00 |
| 32 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 18 | $169.10 | $119.39 | $84.95 | $90.00 |
| 33 | Adjust Existing Valve Box Elevation (663.33) | EACH | 2 | $391.10 | $451.86 | $1,369.13 | $2,000.00 |
| 34 | Adjust Existing Hydrant Elevation (663.34) | EACH | 1 | $2,500.00 | $2,603.31 | $2,572.42 | $2,000.00 |
| 35 | (670.14480010) | 1 | $617.85 | $3,032.39 | $605.70 | $2,000.00 | |
| 36 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 3,812 | $4.50 | $4.80 | $7.50 | $6.00 |
| 37 | Field Change Payment (FCP) (697.03) | DOL | 53,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 38 | Asphalt Price Adjustment (698.04) | DOL | 312 | $1.00 | $1.00 | $1.00 | $1.00 |
| 39 | Fuel Price Adjustment (698.05) | DOL | 202 | $1.00 | $1.00 | $1.00 | $1.00 |
| 40 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 41 | Mobilization (699.040001) | LS | 1 | $45,402 | $59,436 | $59,457 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 23, 2025. Compiled by Mirage Metrics.