NYSDOT contract D265445 bid tabulation
BRIDGE REHABILITATION VARIOUS LOCATIONS. Let by New York State DOT on March 27, 2025, Rockland, Westchester, Region 08. 3 bids received; low bid $16,375,164 by Harrison & Burrowes Bridge Constructors Inc.
- Owner
- New York State DOT
- Letting
- 27 MAR 2025
- Pay items
- 111
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Harrison & Burrowes Bridge Constructors Inc | $16,375,164 | Low |
| 2 | Paul J Scariano Inc | $16,380,800 | 0.0% |
| 3 | Iew Construction Group, Inc | $18,134,725 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Harrison & Burrowes Bridge Constructors Inc | 2. Paul J Scariano Inc | 3. Iew Construction Group, Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $95,000 | $25,000 | $47,420 |
| 2 | (202.120001) | LS | 1 | $600,000 | $750,000 | $750,000 |
| 3 | Removal of Substructures (202.19) | CY | 93 | $0.01 | $1.00 | $0.01 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 650 | $75.00 | $125.00 | $175.99 |
| 5 | Embankment In Place (203.03) | CY | 308 | $85.00 | $100.00 | $125.97 |
| 6 | Select Structural Fill (203.21) | CY | 378 | $105.00 | $100.00 | $145.63 |
| 7 | (203.24010017) | 10 | $225.00 | $100.00 | $171.10 | |
| 8 | Structure Excavation (206.01) | CY | 613 | $85.00 | $125.00 | $177.54 |
| 9 | Prefabricated Composite Integral Abutment Drain (207.27) | SY | 449 | $3.00 | $25.00 | $103.27 |
| 10 | Silt Fence - Temporary (209.13) | LF | 967 | $11.00 | $15.00 | $12.58 |
| 11 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 820 | $13.00 | $15.00 | $12.11 |
| 12 | Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312) | SF | 120 | $135.00 | $75.00 | $302.65 |
| 13 | (210.481201) | SF | 4,381 | $55.00 | $75.00 | $51.86 |
| 14 | (304.11000008) | 580 | $135.00 | $125.00 | $103.75 | |
| 15 | (404.0001) | TON | 44 | $120.00 | $120.00 | $120.00 |
| 16 | (404.0983) | TON | 188 | $335.00 | $300.00 | $295.51 |
| 17 | (404.1989) | TON | 138 | $325.00 | $300.00 | $369.68 |
| 18 | (404.3789) | TON | 208 | $320.00 | $300.00 | $275.82 |
| 19 | Straight Tack Coat (407.0103) | GAL | 140 | $100.00 | $25.00 | $12.11 |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,680 | $5.25 | $5.00 | $6.05 |
| 21 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 1,100 | $55.00 | $25.00 | $36.87 |
| 22 | Interim Steel Sheeting (552.15) | SF | 732 | $90.00 | $150.00 | $199.01 |
| 23 | Concrete for Structures, Performance (555.0021) | CY | 161 | $3,500.00 | $2,000.00 | $4,287.86 |
| 24 | (555.80010001) | 63 | $150.00 | $250.00 | $181.59 | |
| 25 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $8.00 | $8.00 | $8.00 |
| 26 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 28,596 | $3.00 | $4.00 | $4.26 |
| 27 | Stud Shear Connectors for Bridges (556.03) | EACH | 2,996 | $8.00 | $10.00 | $4.84 |
| 28 | (557.05010011) | 3,294 | $250.00 | $300.00 | $438.92 | |
| 29 | (557.1011) | SY | 373 | $625.00 | $1,000.00 | $756.05 |
| 30 | (557.1013) | SY | 111 | $850.00 | $1,000.00 | $1,080.61 |
| 31 | (557.1111) | SY | 272 | $950.00 | $1,500.00 | $987.97 |
| 32 | (557.1113) | SY | 214 | $1,500.00 | $1,500.00 | $1,645.47 |
| 33 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 986 | $0.01 | $25.00 | $24.21 |
| 34 | Sidewalks and Safety Walks (557.30) | SY | 182 | $350.00 | $500.00 | $491.70 |
| 35 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $11.44 | $11.44 | $11.44 |
| 36 | Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902) | QUALITY UNIT | 1 | $10.23 | $10.23 | $10.23 |
| 37 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 739 | $45.00 | $100.00 | $138.47 |
| 38 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 9,420 | $0.90 | $5.00 | $2.42 |
| 39 | Protective Sealing of New Structural Concrete (559.02) | SF | 900 | $2.00 | $5.00 | $6.05 |
| 40 | Protective Sealing of Existing Structural Concrete and Existing Bridge Decks (559.03) | SF | 2,633 | $5.00 | $5.00 | $2.42 |
| 41 | (564.0501) | LS | 1 | $250,000 | $400,000 | $550,000 |
| 42 | (564.0502) | LS | 1 | $250,000 | $400,000 | $650,000 |
| 43 | (564.20010008) | 92,150 | $0.33 | $1.00 | $0.36 | |
| 44 | Type E.B. Expansion Bearing (56 to 111 k) (565.2032) | EACH | 12 | $2,500.00 | $2,000.00 | $3,865.02 |
| 45 | (565.30130101) | 12 | $350.00 | $500.00 | $872.72 | |
| 46 | (566.50030008) | 613 | $5,200.00 | $7,500.00 | $7,621.14 | |
| 47 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 218 | $450.00 | $500.00 | $488.50 |
| 48 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 107 | $350.00 | $300.00 | $407.56 |
| 49 | Transition Bridge Railing (568.70) | LF | 256 | $330.00 | $300.00 | $338.00 |
| 50 | Removal of Structural Concrete (580.01) | CY | 302 | $3,050.00 | $2,500.00 | $4,197.79 |
| 51 | Removal of Concrete Approach Slab (580.04) | SF | 2,771 | $10.50 | $15.00 | $18.90 |
| 52 | Removal and Replacement of Structural Concrete (582.0051) | CY | 5 | $14,000 | $5,000.00 | $25,791 |
| 53 | Removal of Structural Concrete- Replacement with Vertical and Overhead Patching Material (582.0061) | SF | 188 | $225.00 | $300.00 | $429.79 |
| 54 | (582.99) | 1 | $36.00 | $36.00 | $36.00 | |
| 55 | (582.99000016) | 260 | $20.00 | $50.00 | $125.19 | |
| 56 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,126 | $35.00 | $150.00 | $202.99 |
| 57 | Box Beam Guide Railing (606.10) | LF | 204 | $80.00 | $75.00 | $78.41 |
| 58 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 275 | $100.00 | $90.00 | $94.73 |
| 59 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 3 | $3,000.00 | $3,500.00 | $3,091.76 |
| 60 | Box Beam End Assembly Type III (606.1203) | EACH | 1 | $10,000 | $10,000 | $10,588 |
| 61 | Weak-Post, Corrugated Beam Guide Rail (606.18) | LF | 38 | $52.00 | $50.00 | $52.65 |
| 62 | Resetting Anchorage Units for Corrugated Beam Guide Railing or Median Barrier (606.5910) | EACH | 1 | $1,300.00 | $2,500.00 | $1,400.33 |
| 63 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 448 | $35.00 | $25.00 | $21.46 |
| 64 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 447 | $35.00 | $25.00 | $21.46 |
| 65 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 4 | $350.00 | $500.00 | $338.33 |
| 66 | (607.06400016) | 146 | $175.00 | $150.00 | $162.46 | |
| 67 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 |
| 68 | Concrete Sidewalks and Driveways (608.0101) | CY | 4 | $2,600.00 | $2,000.00 | $3,026.52 |
| 69 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 30 | $700.00 | $400.00 | $656.75 |
| 70 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 45 | $200.00 | $250.00 | $181.59 |
| 71 | Stone Curb – Bridge (Type F1) (609.0302) | LF | 323 | $135.00 | $250.00 | $181.59 |
| 72 | Topsoil - Roadside (610.1402) | CY | 110 | $140.00 | $100.00 | $90.80 |
| 73 | Turf Establishment - Roadside (610.1601) | SY | 925 | $3.25 | $5.00 | $12.11 |
| 74 | (617.11000024) | LS | 1 | $1,500.00 | $10,000 | $21,505 |
| 75 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $4,384,494 | $1,750,000 | $2,275,000 |
| 76 | Type III Construction Barricades (619.04) | EACH | 82 | $125.00 | $200.00 | $197.26 |
| 77 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 2,670 | $5.00 | $2.00 | $3.63 |
| 78 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 6 | $100.00 | $50.00 | $242.12 |
| 79 | (619.100103) | LF | 3,000 | $3.50 | $2.00 | $3.03 |
| 80 | (619.100203) | EACH | 6 | $100.00 | $150.00 | $363.18 |
| 81 | (619.100303) | EACH | 16 | $175.00 | $150.00 | $302.65 |
| 82 | (619.110743) | EACH | 11 | $15,000 | $25,000 | $13,681 |
| 83 | (619.111112) | EACH | 2 | $6,000.00 | $25,000 | $10,393 |
| 84 | (619.1301) | EACH | 1 | $100,000 | $50,000 | $22,478 |
| 85 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 50 | $60.00 | $200.00 | $166.78 |
| 86 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 500 | $25.00 | $100.00 | $122.84 |
| 87 | Temporary Positive Barrier – Category 4 (Pinning Permitted) (619.1714) | LF | 80 | $55.00 | $200.00 | $128.90 |
| 88 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 80 | $65.00 | $200.00 | $128.90 |
| 89 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 29 | $40.00 | $75.00 | $334.03 |
| 90 | Temporary Impact Attenuator - Gating (Test Level 2) (619.1812) | EACH | 1 | $8,000.00 | $25,000 | $13,812 |
| 91 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $400,000 | $250,000 | $51,136 |
| 92 | Traffic Control Supervisor (619.25) | MONTH | 4 | $45,000 | $25,000 | $26,421 |
| 93 | (619.99230101) | LS | 1 | $30,800 | $30,800 | $30,800 |
| 94 | Stone Filling (Light) (620.03) | CY | 7 | $300.00 | $250.00 | $405.78 |
| 95 | Bedding Material, Type 1 (620.0801) | CY | 6 | $300.00 | $150.00 | $462.82 |
| 96 | Survey Operations (625.01) | LS | 1 | $150,000 | $275,980 | $99,980 |
| 97 | (627.50140008) | 496 | $7.50 | $25.00 | $24.21 | |
| 98 | Concrete Cylinder Curing Equipment (637.04) | EACH | 2 | $1,000.00 | $5,000.00 | $6,065.71 |
| 99 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 19 | $4,500.00 | $15,000 | $5,095.94 |
| 100 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 101 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 6 | $75.00 | $75.00 | $76.75 |
| 102 | Steel Post, 2.0 lb/ft (646.32) | EACH | 4 | $450.00 | $150.00 | $166.74 |
| 103 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 2,654 | $1.75 | $2.00 | $3.63 |
| 104 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 1,742 | $1.75 | $2.00 | $3.63 |
| 105 | (691.04000020) | 70,000 | $1.00 | $1.00 | $1.00 | |
| 106 | Field Change Payment (FCP) (697.03) | DOL | 528,000 | $1.00 | $1.00 | $1.00 |
| 107 | Asphalt Price Adjustment (698.04) | DOL | 750 | $1.00 | $1.00 | $1.00 |
| 108 | Fuel Price Adjustment (698.05) | DOL | 350 | $1.00 | $1.00 | $1.00 |
| 109 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 110 | (698.93940008) | LS | 1 | $150,000 | $150,000 | $150,000 |
| 111 | Mobilization (699.040001) | LS | 1 | $629,000 | $625,000 | $650,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.