NYSDOT contract D265545 bid tabulation
BRIDGE DECK REPLACEMENT PROJECT. Let by New York State DOT on August 21, 2025, Warren, Region 01. 4 bids received; low bid $9,428,815 by Bette & Cring LLC.
- Owner
- New York State DOT
- Letting
- 21 AUG 2025
- Pay items
- 104
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bette & Cring LLC | $9,428,815 | Low |
| 2 | Winn Construction Services Inc | $10,298,113 | +9.0% |
| 3 | Ing Civil Inc | $11,634,400 | +23% |
| 4 | Kubricky-Jointa Lime LLC | $12,646,500 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bette & Cring LLC | 2. Winn Construction Services Inc | 3. Ing Civil Inc | 4. Kubricky-Jointa Lime LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $20,000 | $15,000 | $955.00 |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type B (202.2202) | SF | 18,577 | $37.00 | $32.00 | $50.00 | $27.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 557 | $100.00 | $70.00 | $18.00 | $92.00 |
| 4 | Embankment In Place (203.03) | CY | 83 | $125.00 | $240.00 | $34.00 | $165.00 |
| 5 | Select Structural Fill (203.21) | CY | 185 | $125.00 | $149.00 | $104.00 | $115.00 |
| 6 | Structure Excavation (206.01) | CY | 417 | $70.00 | $109.00 | $20.00 | $92.00 |
| 7 | Prefabricated Composite Structural Drain (207.26) | SY | 58 | $25.00 | $13.00 | $27.00 | $34.00 |
| 8 | Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312) | SF | 41 | $200.00 | $245.00 | $200.00 | $235.00 |
| 9 | (210.481201) | SF | 6,715 | $40.00 | $50.00 | $40.00 | $47.50 |
| 10 | (304.12110001) | 249 | $150.00 | $198.00 | $125.00 | $225.00 | |
| 11 | (404.0001) | TON | 26 | $75.00 | $75.00 | $75.00 | $75.00 |
| 12 | (404.0982) | TON | 447 | $350.00 | $425.00 | $340.00 | $415.00 |
| 13 | (404.1989) | TON | 47 | $350.00 | $403.00 | $790.00 | $415.00 |
| 14 | (404.3789) | TON | 115 | $350.00 | $403.00 | $600.00 | $415.00 |
| 15 | Straight Tack Coat (407.0103) | GAL | 327 | $65.00 | $75.00 | $5.00 | $77.00 |
| 16 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,038 | $1.00 | $1.00 | $5.00 | $1.20 |
| 17 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,045 | $17.00 | $16.50 | $21.00 | $26.00 |
| 18 | (520.09000010) | 256 | $10.00 | $5.25 | $24.00 | $18.50 | |
| 19 | Concrete for Structures, Performance (555.0021) | CY | 95 | $3,500.00 | $5,500.00 | $4,000.00 | $3,550.00 |
| 20 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $10.54 | $10.54 | $10.54 | $10.54 |
| 21 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 13,439 | $2.00 | $1.80 | $1.60 | $3.00 |
| 22 | Stud Shear Connectors for Bridges (556.03) | EACH | 16,782 | $5.00 | $5.50 | $5.00 | $6.80 |
| 23 | (557.1019) | SY | 772 | $540.00 | $600.00 | $1,000.00 | $460.00 |
| 24 | (557.1119) | SY | 2,075 | $740.00 | $1,000.00 | $725.00 | $1,300.00 |
| 25 | (557.25000016) | 602 | $15.00 | $24.50 | $40.00 | $11.00 | |
| 26 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 2,832 | $0.01 | $3.00 | $0.01 | $1.00 |
| 27 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $9.56 | $9.56 | $9.56 | $9.56 |
| 28 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 2,346 | $16.00 | $17.61 | $18.00 | $19.00 |
| 29 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 22,713 | $0.50 | $0.69 | $0.60 | $1.60 |
| 30 | Protective Sealing of New Structural Concrete (559.02) | SF | 6,466 | $0.75 | $1.96 | $0.80 | $3.15 |
| 31 | (564.0501) | LS | 1 | $750,000 | $421,500 | $1,000,000 | $550,000 |
| 32 | (564.510001) | LB | 1,200 | $1.00 | $3.00 | $7.00 | $5.50 |
| 33 | (564.700001) | EACH | 120 | $870.00 | $1,100.00 | $100.00 | $780.00 |
| 34 | Type E.B. Fixed Bearing (56 to 111 k) (565.2022) | EACH | 30 | $2,500.00 | $2,250.00 | $4,000.00 | $2,600.00 |
| 35 | Type E.B. Fixed Bearing (112 to 168 k) (565.2023) | EACH | 6 | $2,500.00 | $2,225.00 | $4,000.00 | $2,600.00 |
| 36 | Type E.B. Expansion Bearing (56 to 111 k) (565.2032) | EACH | 78 | $2,500.00 | $1,775.00 | $4,000.00 | $2,600.00 |
| 37 | Type E.B. Expansion Bearing (112 to 168 k) (565.2033) | EACH | 30 | $2,500.00 | $1,775.00 | $4,000.00 | $2,600.00 |
| 38 | Armorless Bridge Joint (567.60) | LF | 148 | $300.00 | $275.00 | $400.00 | $655.00 |
| 39 | Transition Bridge Railing (568.70) | LF | 640 | $220.00 | $250.00 | $268.00 | $260.00 |
| 40 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 1,471 | $350.00 | $380.00 | $310.00 | $320.00 |
| 41 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $10.91 | $10.91 | $10.91 | $10.91 |
| 42 | Lead-Exposure Control Plan (570.01) | LS | 1 | $2,500.00 | $2,500.00 | $5,000.00 | $2,950.00 |
| 43 | Medical Testing (570.02) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 44 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Decontamination Facilities (570.04) | CALENDAR WEEK | 8 | $20.00 | $100.00 | $50.00 | $17.50 |
| 46 | (570.150001) | LS | 1 | $30,000 | $42,500 | $50,000 | $41,400 |
| 47 | (570.150002) | LS | 1 | $30,000 | $42,500 | $50,000 | $41,400 |
| 48 | (570.150003) | LS | 1 | $30,000 | $42,500 | $50,000 | $41,400 |
| 49 | (570.150004) | LS | 1 | $30,000 | $42,500 | $50,000 | $41,400 |
| 50 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 2,520 | $1.00 | $1.10 | $1.00 | $1.20 |
| 51 | (572.020001) | LS | 1 | $20,000 | $30,000 | $20,000 | $39,600 |
| 52 | (572.020002) | LS | 1 | $20,000 | $30,000 | $20,000 | $37,500 |
| 53 | (572.020003) | LS | 1 | $30,000 | $40,000 | $40,000 | $63,900 |
| 54 | (573.010001) | LS | 1 | $70,000 | $120,000 | $100,000 | $95,700 |
| 55 | (573.010002) | LS | 1 | $70,000 | $120,000 | $100,000 | $95,700 |
| 56 | (573.010003) | LS | 1 | $70,000 | $120,000 | $100,000 | $95,700 |
| 57 | (573.010004) | LS | 1 | $70,000 | $120,000 | $100,000 | $95,700 |
| 58 | Removal of Structural Concrete (580.01) | CY | 130 | $1,600.00 | $1,900.00 | $1,800.00 | $2,150.00 |
| 59 | Removal and Replacement of Structural Concrete (582.0051) | CY | 1 | $20,000 | $9,750.00 | $15,000 | $6,650.00 |
| 60 | (582.99) | 1 | $50.00 | $50.00 | $50.00 | $50.00 | |
| 61 | (585.01) | EACH | 30 | $4,000.00 | $2,000.00 | $5,000.00 | $4,000.00 |
| 62 | (585.02) | EACH | 30 | $4,000.00 | $2,000.00 | $5,000.00 | $4,000.00 |
| 63 | (585.03) | EACH | 30 | $4,000.00 | $2,000.00 | $5,000.00 | $4,000.00 |
| 64 | (585.04) | EACH | 30 | $4,000.00 | $2,000.00 | $5,000.00 | $4,000.00 |
| 65 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,272 | $75.00 | $42.00 | $33.00 | $71.00 |
| 66 | Bridge Railing Removal and Disposal (587.01) | LF | 1,256 | $10.00 | $9.75 | $20.00 | $12.50 |
| 67 | (589.520001) | EACH | 120 | $825.00 | $880.00 | $100.00 | $1,300.00 |
| 68 | (589.520002) | EACH | 80 | $375.00 | $580.00 | $1,000.00 | $790.00 |
| 69 | (589.520003) | EACH | 40 | $200.00 | $480.00 | $1,000.00 | $695.00 |
| 70 | Box Beam Guide Railing (606.10) | LF | 640 | $50.00 | $55.00 | $60.00 | $59.00 |
| 71 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,300 | $6.20 | $6.00 | $10.00 | $5.30 |
| 72 | Removing and Disposing Concrete Barrier-Half Section (606.7510) | LF | 1,356 | $20.00 | $39.00 | $40.00 | $63.50 |
| 73 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 48 | $350.00 | $389.00 | $790.00 | $415.00 |
| 74 | Stone Curb – Bridge (Type A) (609.0301) | LF | 156 | $335.00 | $359.00 | $377.00 | $385.00 |
| 75 | Topsoil - Roadside (610.1402) | CY | 12 | $125.00 | $175.00 | $210.00 | $415.00 |
| 76 | (610.16010524) | 92 | $20.00 | $1.50 | $42.00 | $32.50 | |
| 77 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $350,000 | $480,500 | $800,000 | $1,793,448 |
| 78 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 11,000 | $12.00 | $7.25 | $6.50 | $7.70 |
| 79 | (619.100103) | LF | 20,200 | $6.75 | $5.00 | $4.50 | $5.30 |
| 80 | (619.111113) | EACH | 3 | $10,000 | $11,000 | $25,000 | $590.00 |
| 81 | (619.111122) | EACH | 1 | $10,000 | $36,250 | $50,000 | $590.00 |
| 82 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 5,080 | $15.00 | $33.00 | $40.00 | $42.50 |
| 83 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,240 | $20.00 | $40.00 | $50.00 | $62.50 |
| 84 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 160 | $100.00 | $42.00 | $120.00 | $63.50 |
| 85 | Stone Filling (Light) (620.03) | CY | 32 | $200.00 | $150.00 | $150.00 | $250.00 |
| 86 | Bedding Material, Type 1 (620.0801) | CY | 40 | $150.00 | $146.00 | $130.00 | $205.00 |
| 87 | Survey Operations (625.01) | LS | 1 | $25,000 | $40,000 | $200,000 | $111,000 |
| 88 | Concrete Cylinder Curing Equipment (637.04) | EACH | 2 | $100.00 | $5,500.00 | $10,000 | $590.00 |
| 89 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 24 | $2,500.00 | $3,000.00 | $2,000.00 | $3,300.00 |
| 90 | Office Technology and Supplies (637.34) | DOL | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 91 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 49 | $40.00 | $44.00 | $44.00 | $47.50 |
| 92 | Type A Sign Posts (645.81) | EACH | 16 | $170.00 | $187.00 | $240.00 | $200.00 |
| 93 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 16 | $22.00 | $24.00 | $30.00 | $26.00 |
| 94 | Steel Post, 2.0 lb/ft (646.32) | EACH | 16 | $68.00 | $75.00 | $91.00 | $80.50 |
| 95 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 12 | $60.00 | $55.00 | $60.00 | $71.00 |
| 96 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 10,258 | $1.75 | $1.25 | $1.20 | $1.40 |
| 97 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 4,863 | $2.50 | $2.50 | $1.60 | $1.90 |
| 98 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 2,432 | $3.10 | $2.50 | $1.60 | $1.90 |
| 99 | (691.04000020) | 73,000 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 100 | Field Change Payment (FCP) (697.03) | DOL | 668,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 101 | Asphalt Price Adjustment (698.04) | DOL | 400 | $1.00 | $1.00 | $1.00 | $1.00 |
| 102 | Fuel Price Adjustment (698.05) | DOL | 400 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Mobilization (699.040001) | LS | 1 | $359,000 | $386,562 | $446,916 | $480,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 21, 2025. Compiled by Mirage Metrics.