NYSDOT contract D265554 bid tabulation

REPLACEMENT OF ROUTE 51 CULVERT OVER STEELE CREEK. Let by New York State DOT on September 11, 2025, Herkimer, Region 02. 5 bids received; low bid $2,633,382 by Slate Hill Constructors Inc.

Owner
New York State DOT
Letting
11 SEP 2025
Pay items
84
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Slate Hill Constructors Inc$2,633,382Low
2Maple Ridge Organics LLC$2,660,217+1.0%
3BP Excavation LLC$2,728,853+4.0%
4Bothar Construction LLC$2,824,242+7.0%
5Cci Companies Inc$3,219,281+22%
NYSDOT contract D265554: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Slate Hill Constructors Inc2. Maple Ridge Organics LLC3. BP Excavation LLC4. Bothar Construction LLC5. Cci Companies Inc
1Clearing and Grubbing (201.06)LS1$80,000$23,200$20,000$17,000$20,000
2Unclassified Excavation and Disposal (203.02)CY640$38.00$28.00$15.00$64.50$42.00
3Embankment In Place (203.03)CY3,175$32.00$54.00$42.00$42.20$42.00
4Select Granular Fill (203.07)CY160$95.00$54.00$59.00$83.25$100.00
5Select Structural Fill (203.21)CY950$80.00$54.00$54.00$81.00$110.00
6Structure Excavation (206.01)CY4,400$38.00$44.00$8.00$25.75$47.00
7Trench and Culvert Excavation (206.0201)CY350$45.00$61.00$35.00$56.90$60.00
8Geotextile Separation (207.21)SY300$8.00$4.00$13.00$3.30$2.00
9Prefabricated Composite Structural Drain (207.26)SY250$16.00$14.00$7.00$37.90$15.00
10Seed and Mulch – Temporary (209.1003)SY25$70.00$9.50$21.00$50.00$20.00
11Check Dam, Prefabricated – Temporary (209.1105)LF100$50.00$19.00$187.00$96.00$16.00
12Rolled Erosion Control Product, Class II Type B, Intermediate (209.190201)SY275$8.50$8.50$11.00$6.70$5.50
13 (209.23010009)350$12.50$9.50$25.00$13.00$8.00
14Subbase Course, Type 2 (304.12)CY750$80.00$84.00$102.00$63.00$70.00
15 (404.0001)TON43$90.00$90.00$90.00$90.00$90.00
16 (404.0982)TON210$155.00$176.00$150.00$164.00$152.00
17 (404.2589)TON630$115.00$126.00$106.00$132.00$130.00
18Diluted Tack Coat (407.0102)GAL260$2.50$8.50$2.50$6.30$2.50
19Asphalt Pavement Joint Adhesive (418.7603)LF750$3.50$2.50$3.50$2.00$3.50
20Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY400$30.00$16.00$26.00$18.55$25.00
21Shields and Shoring (552.17)SF280$5.00$6.50$14.00$42.40$1.00
22 (553.020001)EACH1$1.00$21,600$25,000$75,000$176,000
23 (553.020002)EACH1$1.00$21,600$25,000$55,000$176,000
24Footing Concrete, Performance (555.0011)CY255$1,300.00$743.00$1,600.00$945.00$1,050.00
25Concrete for Structures, Performance (555.0021)CY80$2,200.00$1,440.00$2,800.00$1,685.00$1,750.00
26Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$6.00$6.00$6.00$6.00$6.00
27Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$11.00$11.00$11.00$11.00$11.00
28Uncoated Bar Reinforcement for Concrete Structures (556.0201)LB23,400$2.15$2.50$2.00$2.35$2.00
29Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB3,100$3.20$3.50$2.00$2.60$2.25
30 (560.13000001)25$500.00$150.00$600.00$120.00$675.00
31 (562.0101)SY176$2,000.00$1,950.00$2,500.00$2,670.00$2,750.00
32Performance Concrete Quality Adjustment (562.99)QUALITY UNIT1$17.00$17.00$17.00$17.00$17.00
33Steel Bridge Railing (Three-Rail) (568.54)LF95$260.00$303.00$250.00$287.50$270.00
34Transition Bridge Railing (568.70)LF128$220.00$254.00$230.00$240.90$220.00
35Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH300$135.00$122.00$51.00$66.50$40.00
36 (595.50000018)1,750$5.00$5.50$3.00$3.15$3.00
37 (603.171216)EACH2$565.00$411.00$1,500.00$835.00$600.00
38 (603.171912)EACH1$2,400.00$2,200.00$3,000.00$2,420.00$2,500.00
39 (603.9815)LF20$35.00$41.00$100.00$44.00$90.00
40 (603.9836)LF50$80.00$112.00$200.00$118.00$130.00
41Underdrain Filter, Type II (605.1001)CY30$110.00$92.00$75.00$104.00$175.00
42 (605.1701)LF250$5.00$5.50$17.00$4.20$17.00
43Box Beam Guide Railing (606.10)LF542$55.00$58.00$55.00$54.60$50.00
44Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF419$60.00$63.00$56.00$59.00$55.00
45Box Beam Guide Railing With Extra Long Posts (606.1001)LF207$58.00$61.00$55.00$57.20$52.00
46Box Beam Guide Railing with Extra Long Posts (Shop Bent or Shop Mitered) (606.100102)LF45$65.00$69.00$63.00$65.25$60.00
47Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH8$2,200.00$2,540.00$2,150.00$2,415.00$2,200.00
48Removing and Disposing Corrugated Beam Guide Railing (606.71)LF360$7.00$5.50$6.00$6.60$4.25
49Removing and Disposing Box Beam Guide Railing (606.73)LF820$7.00$6.00$6.00$7.70$5.25
50Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH3$550.00$319.00$1,500.00$824.00$125.00
51Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$90.00$90.00$90.00$90.00$90.00
52Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON8$385.00$339.00$450.00$304.00$300.00
53Stone Curb – Near Vertical Face (NVF) (609.0212)LF110$145.00$109.00$175.00$125.00$130.00
54Turf Establishment – Performance (610.1605)SY450$32.00$14.00$35.00$76.00$25.00
55Basic Work Zone Traffic Control (619.01)LS1$240,000$112,000$38,000$154,000$100,000
56Type III Construction Barricades (619.04)EACH16$50.00$188.00$40.00$125.00$100.00
57 (619.0501)LS1$72,000$254,000$200,000$220,000$280,000
58Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF100$50.00$78.00$150.00$68.80$30.00
59Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF40$85.00$115.00$150.00$72.00$55.00
60Mailboxes (619.27)EACH1$100.00$263.00$150.00$270.00$300.00
61Stone Filling (Light) (620.03)CY125$135.00$102.00$164.00$184.00$130.00
62Stone Filling (Medium) (620.04)CY15$150.00$180.00$133.00$124.00$150.00
63Bedding Material, Type 1 (620.0801)CY175$110.00$82.00$93.00$114.00$130.00
64 (620.14020009)750$220.00$315.00$246.00$242.00$275.00
65Survey Operations (625.01)LS1$31,000$60,200$72,000$40,220$75,000
66Concrete Right of Way Markers Type H (High) (625.03)EACH5$500.00$715.00$3,000.00$1,120.00$700.00
67 (627.50140008)60$10.00$3.00$5.00$26.40$10.00
68Concrete Cylinder Curing Equipment (637.04)EACH1$1,000.00$7,480.00$3,500.00$5,000.00$500.00
69Engineer’s Field Office – Type 2 (637.12)MONTH5$2,650.00$3,590.00$2,000.00$2,500.00$4,000.00
70Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00$1.00
71Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF14$45.00$51.00$60.00$47.45$45.00
72Type A Sign Posts (645.81)EACH4$215.00$248.00$240.00$235.00$220.00
73Reference Marker Panel (646.21)EACH1$55.00$61.00$50.00$57.50$55.00
74Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH8$25.00$28.00$20.00$25.90$25.00
75Steel Post, 2.0 lb/ft (646.32)EACH6$100.00$108.00$100.00$102.00$95.00
76Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH4$170.00$182.00$175.00$172.50$155.00
77Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH7$11.00$61.00$100.00$57.50$155.00
78White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF1,750$3.50$3.50$3.50$3.45$3.10
79Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF1,150$3.50$3.50$3.50$3.45$3.10
80Field Change Payment (FCP) (697.03)DOL100,500$1.00$1.00$1.00$1.00$1.00
81Asphalt Price Adjustment (698.04)DOL576.19$1.00$1.00$1.00$1.00$1.00
82Fuel Price Adjustment (698.05)DOL384$1.00$1.00$1.00$1.00$1.00
83Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
84Mobilization (699.040001)LS1$80,000$102,000$100,000$104,778$123,000
NYSDOT contract D265554: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of September 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy